|
Weekend Construction Warriors Keep
'El' Trains Rolling
Reconstructed stations on
the CTA's Blue Line to sit on center platforms
between two sets of tracks May 2003
by Mary Beth Sammons
Tearing down rusted, century-old elevated train structures
and reassembling them isn't so easy when workers have only
the weekend and must make sure the tracks are reopened in
time for about 7,000 Chicago commuters to hop on board Monday
morning.
Add the time crunch to tracks that wind through city alleys
and new construction that brushes up against industrial and
residential buildings, in some cases less than a thumb's length
away from a bedroom window.
Indeed, the $482 million rehabilitation of the 105-year-old
Douglas branch of the Chicago Transit Authority's Blue Line
has proven to be a logistical feat and an engineering marvel.
It's one CTA officials agree they wouldn't want to have to
repeat, at least for another century.
It has taken ingenious and creative construction solutions
throughout the 2 1/2 years the project has been under way
to make sure those train lines are running again during weekday
rush hours so commuters from Chicago's West Side who depend
on the line can get to their jobs in the city.
"It's been a lot of pressure to be working while these
trains were keeping their schedule," said Glen Zika,
vice president of engineering for the CTA. "The challenge
was to do a tremendous amount of track work on weekends with
no margin for error because the trains had to be running on
Monday."
Though the weekend project is taking twice as much time to
complete, this weekend warrior method has prevented "a
lot of hardship for commuters," added Tom Krug, deputy
project manager for the CTA.
"We didn't want to shut down the whole West Side and
lose all that ridership," he said. "It was work
weekends or otherwise shut the whole line down for two years."
New Stations Arriving
Long besieged by a crumbling structure and slow-moving trains,
the Blue Line project includes eight new stations, replacement
of almost 400 structural spans, almost 200 column foundations
and an upgraded signal system.
In addition, station houses between Damen Avenue in Chicago
and 54th Street in Cicero are being equipped with elevators
for disabled riders and designed so that police in passing
squad cars can have a clear view of the stations. The elevators
and escalators at all the stations will be linked to devices
that notify maintenance officials when the equipment breaks
down.
Also new: the stations will sit on center platforms between
two sets of tracks, replacing the past one on each side.
Throughout the course of the construction, temporary stations
were built to accommodate commuters at five locales along
the 6.6-mi. track: 54th Street; Pulaski/Kildare; Central Park/Kedzie;
California; and Western/Hoyne. The first of the permanent
stations is set to open this spring and the openings will
be staggered throughout the summer and are scheduled for final
completion next fall.
The electrical switch work, which will not interrupt weekday
ridership, is not scheduled for completion until early 2004.
When the entire project is complete, the new and improved
rail line will shave off 20 minutes of travel time from the
end stop to the Loop, Krug said.
"This was a massive orchestration of events," said
Bill Jorgensen, project manager for Blue Line Managers, a
joint venture between DMJM/Harris of East Illinois and Kenny
Construction Co. of Wheeling, which is serving as construction
manager for the Blue Line rehabilitation.
"You've got to have all the construction materials in
place and ready to go and spend a lot of effort putting in
safety lines. It took aggressive scheduling to make sure the
crews were lined up and very proactive management to make
sure not a moment of work is wasted and that the job gets
done."
Construction crews are highly motivated to work fast. They
face damages of up to $70,000 if they are more than two hours
late completing the weekend work, Jorgensen added.
The heaviest work is being done during 45-hour increments
on weekends. Construction crews hit the tracks every Saturday
at 3 a.m., racing the clock until 1 a.m. Monday. During that
time, they demolish the existing elevated track structures
and attach new support columns to beams and girders along
the 5 mi. of elevated tracks, and then they replace them.
During weekdays, the 600-member crew generally works under
the tracks on constructing the six new stations and upgrading
controls.
The list of challenges and creative solutions was designed
to avoid the same mistakes that were made during a renovation
to the Green Line a decade ago, which suffered from major
cost overruns, mid-construction design changes and completion
of the project way behind schedule.
That two-year shutdown of the Green Line went $110 million
over budget and resulted in a 40 percent loss of ridership
that took five years to recoup.
Building Next to Original Track
Part of the challenge included erecting the new rapid transit
line right next to the original track in order to replace
the steel elevated columns that were put into place between
1896 and 1912, said John McCue, project manager for the general
contractor, a joint venture between Kiewit Construction Co.
of Omaha, Neb., and Delgado Erectors Inc. of Lansing, Ill.
The supports had deteriorated so badly that trains were forced
to crawl along the dilapidated tracks at 15 mph during the
rush hour through the city's Pilsen, Heart of Chicago, Little
Village and Lawndale neighborhoods.
The fix has required erecting steel beams within a half-inch
of the existing structure and adjacent residential properties.
In addition, during construction trains are sharing a single
set of tracks on parts of the route, using switchovers to
go between old tracks and the new tracks as sections of the
line are torn down and replaced.
That means that on weekends, train service temporarily stops,
allowing workers to use blowtorches and cranes to cut away
and remove old track and support columns. Sections of the
new, prefabricated steel track in 50-ft. sections are fastened
to the new concrete piers.
"In some cases we had to erect the steel columns within
a half an inch of buildings then get the 50-ft.-long tracks
moved in there over rooftops or between buildings," Krug
said. "We were fortunate. Our only damage was one cracked
sidewalk."
Working with Community
CTA officials launched an extensive community awareness effort
that included door-to-door fliers and updates on construction
progress at neighborhood meetings. Residents in the affected
neighborhoods were told in many cases person-to-person by
CTA officials about the monstrous cranes that would be blocking
their alleys and about noise that would be created from cutting
through 3/8-in.-thick steel on 400 rail spans. Innovations
included using galvanized steel to eliminate the need to paint
and repaint the structural supports, and the use of environmentally
friendly plastic ties.
When full service on the Douglas trains is restored in 2004,
the 15-mph slow zones that were required on about half of
the dilapidated system will disappear and nearby residents
will be exposed to less noise, the CTA's Zika said.
|
Century-Old
Tracks Get Plastic Surgery
|
|
|
Chicago schoolchildren cleaned up their
neighborhood streets to help the Chicago Transit Authority
rebuild the Blue Line. Call it an environmentally savvy
joint venture.
The CTA called on children at 41 public schools in neighborhoods
along the "El" line to collect plastic milk
and juice jugs, which were recycled to create 1,000 plastic
ties used in the rehabilitation of the train line.
Through the project, the CTA not only saved trees but
also removed plastic from the waste stream by creating
the plastic lumbers, which have several advantages over
traditional timber, said Anne McCarthy, CTA spokesperson.
The students jumped on board when the CTA launched the
"Renew the Blue" Recycling Project, an initiative
to collect recyclable plastic from the neighborhoods surrounding
the Cermak (Douglas) Branch of the Blue Line. The collected
plastic was melted down and turned into plastic railroad
ties.
The "Renew the Blue" recycling project was a
collaborative effort between the CTA, Chicago Public Schools,
the City of Chicago Department of Environment, Chicago
Park District and neighborhood residents, McCarthy said.
"We always encourage our students to do their part
to preserve the quality of our environment by recycling
at home and supporting our teachers as they implement
recycling programs in their classrooms," said Arne
Duncan, chief executive officer of the Chicago Public
Schools. "Through this community partnership, students
will be able to see firsthand the results of their recycling
efforts every time the new Blue Line travels through their
neighborhood."
This isn't the first time the CTA has used plastic in
its rehab projects.
Plastic lumber railroad ties are poised to penetrate the
railroad industry, which could use up to 17 million ties
per year, according to Mark Alsentzer, president and chief
executive officer of U.S. Plastic Lumber Corp., which
is based in Boca Raton, Fla. The ties must be strong enough
to support the weight of a locomotive, which weighs up
to 240 tons.
The CTA began replacing its creosote-soaked wood ties
with recycled plastic ties in 1998. The plastic ties offer
both performance and environmental advantages.
Wood ties require creosote treatments to extend the service
life of wood, especially in certain harsh climates. The
plastic ties resist decay, insect attack and water absorption
and do not require the use of toxic preservatives.
To date, the CTA has installed the largest number of plastic
composite ties of any public transit agency in the country.
Of the 650,000 track ties in use on the CTA system, 30,000
are made from plastic, with an additional 11,000 currently
on order. |
|