Parking Garages
To Camouflage Cars
Precast selected to frame two
parking facilities for speed of erection
by Jeffrey Steele
For years, driving by Soldier Field meant gazing at acre
upon acre of parking lots, in addition to a rundown stadium.
The beauty of the new Soldier Field is that it will be surrounded
by parkland. That meant hiding parking below grass, trees
and other attractive physical features.
Parking will be divided between two garages: a 2,500-car
multilevel garage, known as the North Garage, and a 1,600-car,
one-level structure called Waldron Garage, south of the stadium.
Because of their designs, neither garage will detract from
motorists' view of the lakefront as they drive past the new
Soldier Field, officials say.
Utility Lines Caused Woes
There were hurdles to surmount even before a single shovel
of dirt could be overturned for the garages' foundations.
Buried utilities were to be moved to construct the garages,
said Alice Hoffman, president of Hoffman Management Partners
LLC, the Chicago-based developer's representative for the
Chicago Bears.
"None of them were in the places they were shown to
be on the existing site plans," Hoffman said. "You
call up a company called Dig Safe and they come out and locate
them. But by then, you've already bid the work and designed
it. So if there's a change, you have to pay the cost overruns."
According to Mark Simonides, project executive with TBMK,
the joint-venture general contractor made up of Turner Construction
Co., Barton Malow Co. and Kenny Construction Co., some 2,550
pieces of precast concrete were used to create the North Garage,
and about 890 precast concrete pieces make up Waldron Garage.
Precast concrete was chosen, rather than poured-in-place
concrete, because of schedule considerations. "Precast,
once you get the foundations in, goes quicker than cast-in-place
concrete," said Joseph Burns, Chicago-based principal
of New York's Thornton-Tomasetti Engineers, the structural
engineering company on the Soldier Field project.
Precast concrete also fit more effectively into the budget,
Hoffman said. "We did cost studies and found out precast
was about $25 million cheaper than cast-in-place," she
added.
Both parking garages are connected to the stadium for quick
and convenient fan access. The new Soldier Field bears on
the North Garage, so when fans enter the North Garage and
park in their pre-assigned parking spaces, they will be able
to walk through the garage right into the stadium, Simonides
said. Fans will also have direct access from the top deck
of the North Garage into one of the mezzanine concourses within
Soldier Field.
Waldron Garage is also linked to the stadium. It features
vehicular access off 18th Street, Burns said. Pedestrians
will use an underpass beneath Waldron Drive to enter Soldier
Field.
Bowl Sits on North Garage
The North Garage is connected to the north end of the stadium,
and is four stories tall where it meets the stadium, fitting
below the north end zone seats. The north end zone seating
bowl actually rests upon the top of the southern portion of
the garage, Simonides said.
Because the grade along the garage slopes up as it moves
north toward McFetridge Drive, the garage is just two stories
high at its north end. On the roof of the garage is a park-like
plaza featuring attractive landscaping that helps hide the
garage from view.
From the standpoint of Thornton Tomasetti, the chief issues
were geometrical.
"The garage is very rectilinear, but there's a diagonal
slot that allows for a passage into the stadium from McFetridge
Drive and also serves as the pedestrian entrance to the garage,"
Burns said. "And this slot has a granite water wall that's
also serving as a memorial. It's different from a typical
rectilinear garage, where all the columns and beams are at
right angles."
Another challenge was the differing amount of earth pressure
bearing on the garage. A great deal of pressure was exerted
on the structure at its north end along McFetridge Drive,
but little, if any, on the south end underneath the stadium.
"We used a product called Voton foam concrete as backfill,"
Burns said. "It was used as backfill around the north
end to limit differential settlement and to reduce unbalanced
earth pressure on the garage."
The floor of the North Garage is at the same level as the
playing surface. Digging into the earth to create subterranean
garage levels would not have worked, because the water table
is mere feet below the playing surface this close to the lake,
Burns noted.
However, excavation did take place in building the garage,
because the foundations of the park district administrative
building, demolished in September 2001, had stood there.
"We had to excavate for foundations, for our own pile
caps and foundation walls," Simonides said. "There
really wasn't what I would consider mass excavation, just
mainly structural excavation."
A Curvaceous Garage
Situated between Waldron Drive and 18th Street, the Waldron
Garage features several distinctive differences from ordinary
garages, among them its curving design and the fact that it
supports tree planters, Burns noted.
"The design for the tree planters is the challenge,"
he said. "That's what makes this different from many
typical one-story designs. The perimeter of the garage is
circular, and that also makes it challenging and different
from a typical garage. Typically, you'll see a precast deck
in the suburbs that's just a big rectangular. But because
of the design of the museum campus, they wanted more of a
curved perimeter."
Hoffman describes the garage as teardrop in shape - a choice
some fans might deem appropriate given the home team's recent
tradition of disappointing its followers. "It's got curved
walls, is very pretty and is sunk 6 ft. into the ground,"
she added.
"It rises 6 ft. above the existing ground, and the idea
is to keep that elevation below the elevation of Lake Shore
Drive, so people driving by on Lake Shore Drive will see the
lake, not the garage.
Furthermore, we planted large trees on top of this garage
to additionally mask it."
|