Precision Guides
MEP Systems' Installation
Tight dimensions cramp space
for ductwork, plumbing and pipes at Soldier Field
by Jeffrey Steele
Tight tolerances between floors containing the Soldier Field's
133 skyboxes meant that precision and coordination were required
to make systems fit within the confined space.
"Space was at a premium above the ceilings of the suites
for MEP systems," said Mark Simonides, project executive
for TBMK, the joint venture of Turner Construction Co., Barton
Malow Co. and Kenny Construction Co. serving as general contractor.
"It took a lot of cooperation between the designers,
our joint venture and the subcontractors to fit the systems
in above the ceilings. It wasn't that different from a typical
office building."
Beam Penetrations Cause Woes
Because designers placed a premium on putting fans as close
to the action as possible, there wasn't a lot of extra room
between the floors holding skyboxes. Suites were given little
headroom, said Ben Wood, design principal with the LW+Z Joint
Venture. (The project is a joint venture of two architectural
firms: Chicago-based Lohan Caprile Goettsch Associates, with
primary responsibility for the master plan and North Burnham
Park project, and Boston-based Wood & Zapata, with primary
responsibility for the architectural design of the Soldier
Field stadium.)
"We were dealing with a lot of close tolerances and
beam penetrations," he said. "Beam penetrations
were the biggest headaches for everyone ... The engineers
had to make sure the beam penetrations didn't compromise the
structural integrity [of the] beams. And, the HVAC team had
to work very accurately to place the ductwork.
"In a stadium where everything is built to close tolerances,
you have to really draw where every pipe and every conduit
goes. You even have to figure out where all the electrical
lines will go, because you don't have the benefit of a lot
of additional space. You're trying to keep those suites and
club lounges, as well as every other seat, as close to the
field as possible."
The tight floor-to-floor dimensions eliminated the majority
of the interstitial space typically used to run ductwork,
plumbing and pipe, added Tony Montalto, associate and lead
site architect for the LW+Z Joint Venture. And while beam
penetrations were the only option for running many horizontal
pipes, holes couldn't be cut just anywhere.
"Dimensionally and structurally, you're limited to certain
areas of the beam where you can pop a hole through it,"
he said. "It forces all the ductwork and piping, all
the MEP through very specific zones."
The pursuit of precision was all the more crucial given that
there is no room for error in stadiums, Wood said. There have
been newly constructed stadiums that promised unblemished
sight lines but left some fans with views of the field marred
by obstructions.
"You can't say, 'Whoops, you're sitting behind a column'
or 'The overhang's too low,'" he said.
"You can't spend $620 million on a stadium and then ask
a couple thousand fans to sit in bad seats."
Timetable Affects MEP
Another MEP issue was the compressed 20-month timetable contractors
had to complete the project, Montalto noted.
The schedule necessitated the use of multiple trades working
in the same areas at the same times. "A sequential process
turns into an overlaying process," he said. "You
have to be far more precise, far quicker. You can't wait for
one system to be complete to realize the limitations of the
possibilities with the remaining space."
About 80 percent of the stadium's plumbing is exposed to
the fearsome winter winds blowing off Lake Michigan, Wood
said. Because most of the stadium is an outdoor structure,
the vast majority of the more than 60,000 fans in attendance
will be walking along unheated concourses, using unheated
bathrooms and standing in unheated concession areas, he said.
"You're running supply lines and waste lines, and all
the utilities that are serving those bathrooms and concession
areas are subject to the weather," Wood explained. "So
you have to protect all that in the winter time. Engineers
have to provide a lot of insulation and care in how these
pipes are treated."
The same insulation efforts were required for the exterior
pipes used to drain water from the approximately 400,000 sq.
ft. of exposed concrete in the seating bowl, he added.
Has Twin Scoreboards
Other MEP issues revolved around the twin scoreboards and
the playing field itself, said Alice Hoffman, president of
Hoffman Management Partners LLC, the Chicago-based developer's
representative for the Chicago Bears.
The scoreboards came in packages from the manufacturer, Daktronics,
and the individual panels were assembled and erected on substructure.
"It took only three days to get each one up," she
said. "During the day, they're as bright as a drive-in
movie is by night. It's that [high] quality a picture. Very,
very bright; very, very big."
The stadium doesn't have an onsite plant, Hoffman said. Instead,
three feeds come in from the utility ComEd, which added additional
power to the site in 2001. If a power failure occurs, the
stadium's large emergency generator will power emergency lights
and systems.
MEP came into play in the field's heated playing surface,
Hoffman added.
"In order to trick the grass into staying green through
January, we heat the roots to 50 degrees [Fahrenheit] by pumping
in heated glycol underneath the root zone in pipes,"
she said. "They had a field heating system at the old
stadium, but it had to be completely replaced because we drove
all our cranes out there and demolished the existing field.
It would have obviously crushed all the pipes."
In addition to the pipes pumping heated glycol, two other
piping systems are hidden beneath the grass: one for drainage
and another for sprinkling. "It's a pretty complicated
system," Hoffman added.
Indeed, intricacy defines the project.
"We had this landmark building to work around,"
Wood said. "We had to save the colonnades.
That had it's own geometry, and within that we had to place
the new geometry. I can't imagine a more complex building."
|