Moving Heaven
and Earth to Widen U.S. 151
Safety upgrades sought for Wisconsin highway
by Jeffrey Steele
When construction team members working on one of the stretches
of the $130 million U.S. Highway 151 widening project got
a look at the soil under the proposed roadway, they did not
like what they saw.
The soil was unsuitable to support a road, according to the
Wisconsin Department of Transportation and Mashuda Contractors
Inc. of Princeton, Wis., a prime contractor on the project.
"We don't know if this is part of the Horicon Marsh,
which is a large marsh and wildlife preserve" in eastern
Wisconsin, said Mark Klipstein, project manager for WisDOT's
field office in Fond du Lac. "We seem to run into a lot
of marshy material that wasn't properly addressed in the design
process. It's silty, saturated, organic material.
Mashuda is hauling in clean soil from its borrow pit sites
adjacent to the project."
The project is designed to widen U.S. 151 to four lanes from
Waupun to Fond du Lac.
At State Trunk Highway 23 in Fond du Lac, the road will narrow
to two lanes for its last mile to State Trunk Highway 149
on the north side of Fond du Lac.
The original plans called for excavating about 2 million cu.
yds. of soil, said Cliff Mashuda Jr. of Mashuda Contractors.
But by the time the work is done, about 3 million cu. yds.
will be used because of the unsuitable subsoils, he added.
The contractor is using up to six scrapers, augmented by a
dozen CAT 740s loaded with CAT 385 backhoes. "That's
to bring all the fill from the offsite sources, and to take
out all the unsuitable soil - all the earthwork," Mashuda
said.
2007 Target Completion
This soil is just one of many obstacles likely to confront
WisDOT and the U.S. 151 project's prime contractors before
the widening and reconstruction effort is complete in fall
2007.
The 25-mi.-long stretch of roadway currently has three active
contracts totaling $45 million, each headed by a different
prime contractor. Mashuda is prime contractor on the section
extending from State Trunk Highway 49 to Hickory Road, a distance
of 3.7 mi. Work began in May 2002 and is slated for completion
in late fall, Klipstein said.
Another section runs from State Road Highway 149 to State
Trunk Highway 23, a distance of 3.4 mi. The prime contractor
is James Peterson & Sons of Medford, Wis.
Work began in September and is expected to be finished in
the fall.
The third section goes from Hickory Drive north to Thill Road,
a length of 5.3 mi. Streu Construction of Two Rivers, Wis.,
is the prime contractor. Work started in May and is slated
to finish in fall 2004.
Safety Upgrades Needed
WisDOT needed to turn its attention to U.S. 151, Klipstein
said. "It's been overlaid and overlaid so many times
that the ride condition is very poor right now," he added.
"The volume exceeds safety and traffic flow criteria,
and the crash rate in the area is above statewide average
for comparable thoroughfares."
As part of the project, WisDOT will eliminate access on some
sections of the road.
The additional lanes, median, realigned intersections and
reduced number of access points are likely to help improve
safety and traffic flow, Klipstein said.
The road is a major thoroughfare between Madison and Fond
du Lac, with high truck and auto volume, and parts of the
stretch are being built next to live traffic.
Nonetheless, dealing with traffic during construction is not
expected to be a serious problem.
On Mashuda's section, a frontage road was built first and
traffic diverted to it while widening work takes place on
the highway. On the other two sections, a new two-lane road
was built first, and traffic is being moved to that road while
construction teams attend to reconstructing existing lanes.
Six in. of crushed aggregate base course will be placed over
the soil subgrade on the highway. On top of the aggregate
base course will go 4 in. of open-graded base course. The
drain system will be installed within this layer, consisting
of a 4 in. pipe.
Over the open-graded base course goes 10 in. of concrete.
At the joints, construction teams will place dowel baskets
before pouring concrete.
The dowels are reinforcement bars that prevent the concrete
joints from faulting, or moving up and down, which severely
reduces both ride quality and pavement life, Klipstein said.
The baskets are designed to hold the dowels in place.
"So when you pour the concrete, since the baskets are
anchored down and they don't move, we get the bars exactly
where we want them," he added. "We end up sawing
that joint after the concrete is cured out, and we saw our
joint over the bars."
Bridge Work
In the section headed by Mashuda, two bridges are being replaced
over the Rock River. Six bridges in the Highway 26 interchange
and two in the Business 151 interchange are being added.
"The alignment is changing so the existing structures
were useless," Klipstein said.
"So we're just replacing them. Not only didn't the new
alignment match them, but the useful life of the structures
was over."
The U.S. 151 project will also feature one federally funded
experimental bridge. The structure is to be located in the
northern part of the section headed by Mashuda and will carry
U.S. 151 traffic over State Trunk Highway 26.
The experimental bridge is the result of a research project
involving the University of Wisconsin at Madison. It will
boast a fiberglass-reinforced bridge deck.
The deck is notable not only for its use of alternative materials
but because it won't contain steel, Klipstein said. That should
help eliminate delamination of the deck, which occurs when
steel rebar begins to rust.
The experimental structure also features unique construction
methods.
Typically, a plywood layer is laid down on the deck during
construction, then removed after the concrete is poured, Klipstein
said. "But we have a permanent deck made out of fiber-reinforced
material that stays in after the concrete is poured,"
he added. "It's just another part of the strengthening
of the deck."
Those involved in the project speak highly of the level of
coordination and cooperation thus far. "It was a very
well designed project, good materials to work with, good people
from the DOT," said Jeff Peterson, owner of James Peterson
& Sons Inc.
His company's only setback was finding a short stretch of
poor soils near a wetland mitigation site, he said. The discovery
of those soils necessitated working during freezing weather
in November and December to remove the material.
Klipstein said he is happy to be part of the project. "I've
been fortunate to be working with good contractors and Fond
du Lac County officials," he added.
|