Features
 Current Features
 Past Features





Feature Story - August 2003
Upgrades to Pump Up Water Plant's Capacity
Treatment process at Indiana facility maintained throughout project
by Craig Barner

Getting pumped has been important during the $56.9 million upgrade of the wastewater treatment plant in Lafayette, Ind.

Even during construction, water received from city sewers has continued to move through pipe in the 30-acre facility before being discharged into the Wabash River after treatment, said John Dettman, project manager for Indianapolis-based Bowen Engineering Corp., the general contractor on the project.

The requirement is a demanding one. Between 16 and 22 million gallons of water is processed in the plant every day.

Meantime, 26 different structures in the facility are being renovated or newly constructed, said Mike Kesler, project superintendent for Fort Wayne, Ind.-based Hagerman Construction Corp., the concrete contractor.

Maintaining water quality was especially tricky when systems were bypassed, Dettman said. Provisional systems were occasionally set up while components went offline for a week or more for replacement or renovation.

For instance, pumps were put in place for three weeks while the existing effluent pump station was demolished and built anew. This job included constructing a junction box, building gates and valves for it and connecting the entire structure to a 60-in.-diameter pipe.

"In essence, we were taking a chunk of pipe, plugging it here, plugging it there and pumping [water] while we did the work in the middle," Dettman added.

Another time, water was bypassed for a week from a primary settling tank while it was renovated.

Since the project started in July 2001, including during bypass operations, water discharged from the plant was still required to meet stringent state requirements on the levels of bacteria, suspended solids and similar measures.

"The city hasn't had one violation since we started," Dettman said.

Expanding Plant Capacity

The project was implemented because the plant has neared the limits of its capacity, said Brad Talley, water pollution control superintendent for Lafayette's Water Pollution Control Department. Indeed, a significant upgrade had not been done on the facility since 1954.

The facility's capacity will more than double, Talley added.

The treatment process is relatively typical but complex. Water comes into the facility from Lafayette's combined sanitary and storm sewer system, and four 250-horsepower pumps drive it into the headworks so treatment can begin. "Water comes in with dirt, grit, sewage, garbage - anything that can fit down a manhole," Dettman said.

Coarse screens remove the biggest contaminants, such as tree stumps, aluminum cans or even bicycles. The effluent is passed through fine screens, which sift the still large impurities, and fine-screen washers.

Grit collectors, the next station, remove sand, gravel and stone.

Solids are still in the effluent as it enters the primary settling tanks, despite the sifting processes already completed. The solids settle on the tank bottoms as sludge, and the sludge goes to digesters. There, biological agents consume the waste matter, and the effluent goes in another direction.

"It (the effluent) is a lot cleaner now than when it came into the plant," Dettman said. "You got a lot of settled sludge out of it, and you've got your grits and big materials out."

The effluent falls over several weirs and enters aeration tanks, where diffusers on the bottom blow air to keep beneficial biological agents alive. The effluent still has sewage in it, despite the previous sloughing off of the sludge.

"There are different bugs in different areas that do different things," Dettman said. Like the digesters, the agents consume the sewage.

Next, the increasingly clean effluent enters the final clarifiers. Like the primary tanks, solids in the water, now very small, settle on the bottom.

Through gravity, the water goes over weirs into a chlorine-contact tank because Indiana requires chlorination from April 1 through Nov. 1. The water is dosed and leaves the plant.

Methane gas, a byproduct, is produced during the digestion processes and has to be dealt with, Dettman said.

The gas can either be burned away or routed to boilers, some of which can run on methane. The gas is purified and fired to produce hot water, which can heat buildings on site.

"The city can potentially save money by using what they're producing anyway," Dettman said.

Systems Added, Renovated

The project called for many system components to be added or renovated, including:

  • The headworks facility, which is new, contains two coarse screens, three fine screens and two grit collectors.

  • A new primary settling tank, which was put up and joins the four existing tanks.

  • Two aerating tanks were added, and the four tanks on-site were renovated. Three blowers were added to the treatment system.

  • Four 90-ft.-diameter clarifiers, which were constructed while the existing 70-ft.-diameter clarifiers were scheduled for renovation.

  • A new sludge-thickening building with two thickeners, one for digested sludge and the other for waste sludge.

  • A new chlorination building, which doubled the capacity for this process.

    Besides the pump station, other new structures include process pipe, an administration building, vehicle storage building, maintenance building and warehouse space.

    "We added more volume to their existing process and we added new things to their existing process," Dettman said.

    Fighting the River

    The site location near the river presented difficulties.

    Two floods have occurred since the start of the project, Dettman said. Though the deluges did not go over the levee protecting the site, they did cause the groundwater to rise.

    Numerous systems were used to dewater the land, including deep wells, pumps and well points, but they provided only limited efficacy due to the high water table and the composition of the soil, Dettman said. It includes silt, sand, clay, gravel seams, fill and even plain garbage.

    "I could drill a hole 30 to 40 ft. in the ground with a pump, and in one day it'd be slurping air," he said. "It was the nature of the ground - it would not give up water."

    One flood occurred while the headworks facility was under construction, causing work to fall behind schedule. Time was later recouped, and the schedule was back on track.

    Adding to the soggy condition is a hillside from which water runs off and down into the site, Hagerman Construction Corp.'s Kesler said.

    The area's unstable nature resulted in more than 400 cast-auger piles being laid as foundations, Dettman said.

    Coordination among the team members was important in the intricate project.
    Hagerman alone had 20 subcontractors and suppliers in its contract package, Kesler said. The company scheduled frequent foreman's meetings, and a schedule was produced every three weeks to keep on track.

    Bowen also called superintendent's meetings, which helped plan the 26,000 cu. yds. of concrete that was laid, Kesler said. Flexibility was needed, because both pumping and crane and bucket were used to move material.

    Pollutant Levels Down

    Some of the new systems are online, and work is expected to finish in June.

    Already, the project has borne fruit in terms of the quality of water discharged from the plant, the Water Pollution Control Department's Talley said. "Since we put the new plant online, we're sending out half the stuff to the river we used to," he added.

  •  Click here for more Features >>


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved