Features
 Current Features
 Past Features





Feature Story - November 2003
$171 million Fermilab Undertaking
A 'Smashing' Project in Illinois, Minnesota

by Craig Barner

An experiment that will involve hundreds of physicists from 32 different universities and research institutes has resulted in a $171 million project at the Fermi National Accelerator Laboratory in Batavia, Ill.

The experiment seeks to determine whether the neutrino, a shadowy subatomic particle, has mass, said Dixon Bogert, a physicist and deputy project manager for civil construction. Though the existence of the neutrino was postulated in the 1930s and first confirmed in the 1950s, the particle is so light that no measurement has been made of its mass.

advertisement

Previous experiments have revealed three different types of the particle - electron, muon and tau neutrino - and observations from nature suggest that a neutrino of one type might sometimes change into a neutrino of another and back again, a process known as neutrino oscillation. The experiment seeks to confirm the oscillation takes place to answer whether neutrinos have mass.

The Neutrinos from the Main Injector, or NuMI, experiment might result in developing spin-off knowledge, such as shedding light on fundamental issues about the nature of matter and energy like the sun and nuclear fusion.

"It (neutrino oscillation) is related to fusion processes and other things like that," Bogert said.

Sitework at the laboratory 40 mi. southwest of Chicago began in 1999, and construction is expected to finish in February, said Elaine McCluskey, Fermilab construction manager. Scientific instruments and materials will then be installed, and the experiment is expected to start in 2005 and could last one to two decades.

Physics for Construction Professionals

The Fermilab project's parameters are immense because construction is taking place in two states, on land and below ground where facilities to be used for the NuMI experiment are already located.

A proton beam will be extracted from the facility's underground main injector and shot into a target of carbon blocks, Bogert said. The collision between the quarks that make up the protons and those that make up the carbon will rain out a variety of particles, such as two-quark states of matter called pi mesons.

These will be focused with cylindrical magnets and dart through a 2,200-ft.-long, 6-ft.-diameter steel pipe lined in concrete. During flight, the anti-down quarks that make up the particles change into anti-up quarks and W particles. W particles, in turn, decay into muons and muon neutrinos.

These particles will shoot through blocks of metal surrounded by concrete to absorb the muons, and the muon neutrinos will zip through a detector made of 200 planes of steel equipped with scintillators to verify the muon-type neutrinos have been produced. Finally, the beam will project through 450 mi. of solid earth to Soudan, Minn., where another detector of 484 planes is located and already installed in an abandoned iron mine a half-mile underground.

"In Minnesota, the expectation is we're not going to get many muon neutrinos, but instead a high number of electron neutrinos and tau neutrinos," Bogert said. "They have a different signature than the muon neutrino."

Each neutrino bullet will take less than a second to travel between the Fermilab gun and the Minnesota target because the beam travels at the speed of light. The injector cycles every 1.9 seconds.

Project Elements

Several major elements make up the project at Fermilab to carry out the experiment.

Two shafts were opened with explosives, including one to service the target area and another to service the detector space, McCluskey said. Excavators were used to push debris in a container, and a crane removed the spoils.

A 4,150-ft.-long tunnel was mined and includes space for the two halls, in addition to a chamber between them for the absorber blocks. After the tunnel ends, the beam continues on to its target.

A tunnel-boring machine created the 21.5-ft.-diameter tunnel, and Lombard, Ill.-based S.A. Healy Co. served as the general contractor for this project element.

Above each shaft, structures have been built, the Target building and the Minos -Main Injector Neutrino Oscillation Search - building above the detector area. They will house equipment for the experiment, including a 30-ton crane in the Target structure that will be used to lower the carbon blocks, and two 15-ton cranes in Minos that will bring down the detector planes.

Park Ridge, Ill.-based Ragnar Benson Inc. served as the general contractor on the service buildings and outfitting.

Bridge cranes in the tunnel allow materials to be moved once they have been brought down.

A Material Project

Material distribution was an important issue partly because activity occurred above and below ground.

And, a large quantity of materials go into the project, McCluskey said. About 25,000 cu. yds. of concrete - an amount requiring 1,000 truckloads - was used to line the decay pipe alone. Additional concrete was needed for the target pit and tunnel walkways.

Considerable exertion went into stockpiling materials in the tunnel during the early stages of construction, said Phil Stearney, project manager for Ragnar Benson.

"It was a very large effort the first five months of the job to get all the materials required for the tunnel work into the tunnel so that we could build the building without having a lot more material stocking to be performed later," he added.

Designed for Science

Because of earth's curvature, the tunnel slopes downward 3.3 degrees, Bogert said.
The beam will be at its lowest point beneath Wisconsin and start to rise as it approaches its northern Minnesota target.

"As we go under Wisconsin, the beam is 6 mi. down," he added.

The two shafts vary in depth due to the slope. The Target shaft is 110 ft. deep, and the Minos shaft is 350 ft. deep.

Also because of the incline, dewatering was critical. Approximately 420,000 gallons of groundwater rushes toward the Minos hall, the lowest point, each day.

A pump with backup electrical system was installed. And, a diesel-powered auxiliary pump was put in just in case the first system goes down.

"The water never stops coming, even if the pumps stop running," Stearney said.

Trench drains channel water into a 20-ft.-deep sump pit in the Minos hall for efficient collection.

The shafts were lined in concrete to prevent water from dripping into the chambers below and to provide a work surface for the numerous risers.

The number of utility lines in the shafts is considerable. The Minos shaft, for instance, has two vent risers, three pipe risers and 24 conduit risers, and the Target shaft is also heavily outfitted.

Swing stages were suspended to hold workers during utility-line installation, Stearney said.

Shaft area was an issue because the space was used for hoisting, in addition to a channel for utility lines. Despite the lines' large number, they were not stacked but rather ring the shaft edge.

"Fermi told us exactly where to put these lines," he added. "We had to stay out of the hoisting zone."

The location of the decay pipe in the tunnel was required to be within .75 in. of tolerance, and a laser-guiding system was used to place it.

Worker, Employee Protection

Several elements ensured the safety of construction workers during construction and employees after project completion.

Construction could not occur in the above-ground structures when workers were in the shaft and vice versa, and weekly coordination meetings made certain subcontractors followed these guidelines.

"We slated times for installing risers in the shaft," Stearney said. "We said, 'When we have the swing stages in the shaft, we won't be doing anything else in the shaft.'"

A wall runs the entire depth of the shafts, creating two half moons, and the stairs in one semicircle can be used for exiting when the elevators in the other one cannot.

Keeping out fumes and proper ventilation were important.

Rather than gasoline, tuggers used to move materials before installation of the bridge cranes were powered with diesel fuel and had scrubbers. Air-handling units heat spaces with electric power.

In addition, the tunnel was ventilated during construction and for occupancy. Industrial fans were placed in the shafts and halls, and four ventilation holes were drilled during construction.

KEY PLAYERS
OWNER: Fermi National Accelerator Laboratory/U.S. Department of Energy, Batavia, Ill.
GENERAL CONTRACTOR (SERVICE BUILDINGS AND OUTFITTING): Ragnar Benson Inc., Park Ridge, Ill.
GENERAL CONTRACTOR (TUNNELING): S.A. Healy Co., Lombard, Ill.
ARCHITECT/ENGINEER (TUNNEL OUTFITTING): Montgomery Watson Harza, Chicago
ARCHITECT/ENGINEER (SERVICE BUILDINGS): Crawford, Murphy & Tilly, Springfield, Ill.
ARCHITECT/ENGINEER (CRANES AND PROCESS PIPING): Fermilab, Batavia, Ill.
CONSULTING ENGINEER: Hanson Professional Services, Springfield, Ill.

 

Useful Sources

  • Find out about the Neutrinos from the Main Injector project by visiting
    www-numi.fnal.gov/ on the Internet.
  • View the NuMI excavation by visiting
    www-visualmedia.fnal.gov/VMS_Site/s_videonews.html on the Internet.
  • See a 12-minute video about detecting neutrino oscillations by visiting vmsstreamer1.fnal.gov/VMS_Site_02/VMS/MINOS/MINOS.ram on the Internet.

    'It was a very large effort the first five months of the job to get all the materials required for the tunnel work into the tunnel so that we could build the building without having a lot more material stocking to be performed later.'
    - Phil Stearney, Ragnar Benson Inc.


    'The water never stops coming, even if the pumps stop running.'
    - Phil Stearney, Ragnar Benson Inc.
  •  Click here for more Features >>


     


    Sponsors

    © 2009 The McGraw-Hill Companies, Inc.
    All Rights Reserved