Oswego
School Gets Advanced Grading
Change to Masonry on Part of High School Also Helps Ensure On-Time Opening
by Craig Barner
Foresight and teamwork are helping ensure the $70 million
Oswego East High School is ready for students on Aug. 1.
The project in Oswego, Ill., was awarded in December 2002,
and the timing immediately presented a problem, said William
Callahan, executive vice president of Hickory Hills, Ill.-based
Henry Bros. Co., the project's construction manager.
A substantial amount of grading was required for the 102-acre
site, yet the onset of winter portended a freezing ground.
The clay topsoil was to be stripped, and the site - once a
field harvested for crops - needed to be leveled to provide
a bench to seat the 435,000-sq.-ft. structure.
Delaying sitework until after the winter was out of the question
because of the potential for heavy spring rains, Callahan
said. The one or two weeks normally required for grading could
have stretched into four to six weeks during a wet spring.
And in the event of rains, a large amount of stone would have
been laid on the site to speed up work, adding to the cost.
|
A window of about 10 to 12 days was available for grading
in early December, and the decision was made to commence work
immediately. An armada of equipment "attacked" the
site, and the weather held up.
About 6 to 12 in. of topsoil were removed, and balancing was
done. Hills that ranged between 2 and 3 ft. were scraped away,
and fill that varied between 5 and 6 ft. was added to low
areas.
Overall, 95,000 cu. yds. of material were moved, said Matt
Blocker, controller with Oswego-based G.A. Blocker Grading.
"When spring finally broke in March 2003, we were able
to progress immediately with the footings and the foundations,
rather than by being delayed by the building of the bench,"
Callahan said.
Temporary roads and a parking lot were also built in December.
And, a bid package was developed to incorporate the remaining
sitework elements, such as the athletic fields and landscaping.
A Structural Change
The schedule remained a concern, even with the adroitness
exhibited on the project's grading.
The academic wing on the north was a crucial project element
primarily because enrollment in Oswego Community Unit School
District 308 is growing rapidly, Callahan said. Indeed, the
district about 35 to 40 mi. southwest of Chicago is reportedly
one of the fastest growing in the nation.
The structural support for the academic spaces - areas E,
F and G - was changed to be primarily masonry, said Michael
Benstent, senior project manager with Henry. Area D, a natatorium,
is also supported with masonry.
The switch sidestepped the long lead time sometimes needed
for structural steel, the material originally intended to
hold up those areas.
In addition, the academic area's structural bid package was
awarded four weeks ahead of the rest of the building. "That
way, we were able to start on the foundations, structure and
the masonry ahead of the completion of the entire design package,"
he added.
Steel was retained as the structural support for the remainder
of the building, and 2,113 tons of steel were used in the
building.
Getting a Schooling
A $150 million referendum was approved in November 2002 to
fund Oswego East, and the balance will be used for other district
projects.
The high school will have the capacity for 2,400 students,
though about 700 freshmen and sophomores will make up the
first class. There are approximately 340 rooms in the mostly
three-story school.
A number of spaces were incorporated in the design to enrich
the high school's academic offerings and make it welcoming
to the public, said Ed Skahan, partner and vice president
with Batavia, Ill.-based Kluber, Skahan + Associates Inc.,
the architect on the project.
Area B, which is devoted to performing arts, will hold spaces
on the school's east end that include choir and practice rooms
and an auditorium with capacity for 1,100 people, balcony
and stage. A 38-ft.-long, 26-ft.-wide hangar door that forms
the stage's eastern wall will open to an outdoor amphitheater.
"The back of the stage becomes the front of the stage,"
added Howard Mulford, field superintendent with Henry.
An 80-ft.-high masonry tower will rise above the stage and
incorporate the fly gallery, professional-level rigging and
equipment. "A lot of colleges would give their right
arm for a center like that," Mulford added.
Area A, a 10,575-sq.-ft. space to the west of B, will hold
the commons areas, such as the kitchen and cafeteria. About
1,300 people can sit under an approximately 148-ft.-long,
140-ft.-wide skylight held up with 55 steel trusses, each
custom made.
A visit was made to the fabricating plant in Jackson, Miss.,
to inspect the fabricating process for the trusses and convey
the urgency of the project, Mulford said.
"The building in Jackson was a quarter mile long and
almost a quarter mile wide," he added.
The athletic facilities in Area C west of A will be sizable.
C will hold three basketball courts, with a seating capacity
for 2,800 people in the main gymnasium; a varsity sports complex,
including wrestling, fitness room, dance rooms and related
classrooms; suspended five-lane running track; and 10 locker
rooms.
The natatorium on the school's western edge will include a
10-lane pool, diving well and seating for 500 spectators.
A second 80-ft.-tall tower near the school's west end will
mirror the one rising above the stage and hold the mechanical
systems.
Bidding for a 13,000-sq.-ft. annex building to hold vocational
programs will occur this month.
Managing Deliveries, Sequence
Coordination was important due in part to the project's size
and complexity.
More than 1.4 million pieces of masonry on the interior and
exterior form the building, said Jeff Roers, project manager
with Arlington Heights, Ill.-based Esche & Lee, a joint-venture
member of the masonry team.
An average of four to six semitrailers of mortar and grout
and eight to 10 semitrailers of block and brick were received
each day during the summer, Benstent said.
Sequencing the construction was important.
Openings were left in areas C and B to make sure masonry could
be brought in to erect the towers, Mulford said. Also, the
procurement of the mechanical units was carefully scheduled,
and temporary, oversized openings in the west tower ensured
the units could be lifted and seated.
A low-temperature air system is expected to realize cost savings
for the school district, said John Kluber, mechanical engineer
with project architect.
Traditionally, chillers produce 45-degree water so air expelled
from coils in air-handling units is 55 degrees. With a low-temperature
system, chillers deliver water at 38 degrees to produce air
at 47 degrees.
"That allows us to downsize the air-handling equipment
and ductwork," Kluber added.
The air-handling units also have heat pipes to recover heat,
rather than exhausting it, for environmental benefits.
Pleasing to the Public
A number of design elements were incorporated into the building
to make it pleasing to the public.
Three bands of architectural brick cladding the exterior -
dark brown, medium brown and tan - will encourage onlookers
to view the building horizontally, and tall and thin windows
will goad them to look at it vertically, architect Skahan
said.
In the natatorium, lights in the pool will be aimed so spectators
can avoid glare.
Clerestory windows were incorporated above seating, rather
than across from it, also to cut glare.
An acoustical consultant was brought it to provide advice
on sound deadening - an important idea for a learning environment,
Skahan said. One idea incorporated in the school was to design
the auditorium with a double-wide wall filled with sand to
squelch sound.
Useful Source
See additional progress photos and find out about plans for
Oswego East High School by visiting www.oswego308.org/oehs/
on the Internet.
"When spring finally broke in March 2003, we were able
to progress immediately with the footings and the foundations,
rather than by being delayed by the building of the bench."
| KEY
PLAYERS |
| OWNER
: |
Oswego Community Unit
School District 308, Oswego, Ill. |
| CONSTRUTON
MANAGER: |
Henry Bros. Co., Hickory
Hills, Ill. |
| ARCHITECT: |
Kluber, Skahan + Associates,
Batavia, Ill. |
| STRUCTURAL
ENGINEER: |
Pease Borst Associates,
Park Ridge, Ill. |
| MASS
EXCAVATION : |
G.A. Blocker Grading,
Oswego, Ill. |
| MASONRY:
|
G. Porter Masonry/Esche
& Lee Joint Venture, Oswego, Ill. |
| STRUCTURAL
STEEL: |
HLM Steel/Steel Service
LLC, Naperville, Ill. |
| HVAC:
|
Amber Mechanical, Alsip,
Ill. |
| PLUMBING:
|
C.R. Leonard Plumbing,
Joliet, Ill. |
| ELECTRICAL:
|
Fitzgerald Electrical,
Hinckley, Ill. |
| ALUMINUM
ENTRANCES: |
Lake Shore Glass &
Mirror, Chicago |
| ROOFING:
|
Olsson Roofing Co.,
Aurora, Ill. |
|