Redo
of U.S. Cellular Field
White Sox' Ballpark Takes Its Cuts
by Craig Barner
Cuts are being taken this off-season at U.S. Cellular Field,
home of the Chicago White Sox.
Rather than baseball bats, the implements being swung are
construction tools, and the ballpark itself is taking the
strikes.
The angled canopy and upper eight rows are being chopped from
the South Side playing field formerly known as New Comiskey
Park as part of a $28 million renovation. The park's Himalayan
height - frequently knocked among fans since the facility
originally opened in 1991 - will be reduced 20 ft. and 6,600
seats will be eliminated from the upper deck.
"The No. 1 challenge for us was to address fans' displeasure
with the upper bowl - in particular the steepness of it and
the perceived steepness of it," said Don Williams, vice
president of Dallas-based HKS Architects, the designer. Indeed,
the steepest part, at 36 degrees, will be removed, though
the remaining part of the upper deck with 35-degree angle
will be retained.
Two other key elements include the addition of a truss-framed
horizontal roof and the enclosure of the upper-deck concourse
with 25-ft.-tall translucent panels, said Dan Polvere, director
of development and facilities for the Illinois Sports Facilities
Authority, the Chicago-based landlord.
The roof, which will cover the back 13 of 21 rows, will help
add intimacy and charm to the ballpark. And, the panels will
cut down on wind, an important consideration in Chicago during
the early and late parts of the baseball season.
"Another thing is we've backlit all those panels,"
Williams added. "That whole area will glow at night."
Construction is expected to be finished before Opening Day
of the 2004 baseball campaign in early April.
The $68 million deal that gave away naming rights was structured
to bring in $40 million for the project, Polvere said. The
remaining payout will be distributed over 20 years.
The current project is the fourth of five phases, and the
previous three stages - each completed in consecutive off-seasons
starting in 2000-2001 - cost about $41 million, Polvere said.
Highlights included adding about 2,000 seats along the foul
lines in front of existing seating, relocating the moat-like
bullpens in the outfield and building an elevated fan deck
in center field for a patio atmosphere.
Several elements are expected for the $12 million final phase
to come in the subsequent off-season, including the completion
of interactive activities for kids and work on other items
still in discussion.
"It's something we might flesh out in July or so and
go out to bid at the end of summer," Polvere said.
When fully completed for the beginning of the 2005 season,
the renovation is expected to have cost about $81 million.
No taxes will have been assessed for the work on the publicly
owned facility with capacity for 42,000 fans.
Park's Partial Dismantling
The renovation is more akin to a disassembly than a demolition,
and this was done between mid-October and early December.
Holes were cut in the metal canopy so chains could be inserted
for removal, said Gary Hill, project executive in Chicago
with Turner Construction Co., the general contractor.
Making "Swiss cheese" out of the panels was also
done to prevent them from becoming wind-catching sails during
lowering, he added.
The light towers along each foul line were lowered via crane.
The two on the left-field side went into a fenced area of
35th Street for disassembly, and those on the right-field
side were stored in the parking lot between 35th and 37th
streets.
"Some of the [old] lamps are going to high schools,"
Hill said.
The seats were detached from risers and removed. The concrete
raker tips that previously held the risers were cut and lowered
in about 40 different picks.
Precautions were taken to ensure worker safety, especially
during the severing of the raker tips, Hill said. To guard
against the tips from falling, scaffold towers were built
below the tips with collars bolted on, and the saw and crane
were hooked on the tips during cutting.
In mid-December, the earliest elements of the new construction
had begun, including supports for the superstructure to come.
About 2,000 tons of steel will be erected.
New columns will be placed about five rows from the back to
support the roof and trusses, HKS' Williams said. About 300
seats will be obstructed.
Framing the roof will be 260 trusses, and a metal deck and
rooftop will complete the cover. The replacement light towers
and lamps will be installed and fed with power.
"The idea was to make it look like a traditional ballpark
and less like a stadium," Williams said.
The existing precast concrete seating risers not removed were
X-rayed with a ground-penetrating device to ensure nothing
essential will be cored through.
Ballpark Logistics
Ensuring the proper placement of construction materials and
machinery, such as the three cranes for demolition, was a
key element of the project logistics.
Putting the largest crane outside the field for the demolition
was always the plan, but the placement for steel erection
was considered inside the park, Hill said.
"There was a certain draw for us to put the cranes in
on the field, but we eventually let it go," he said.
"To build a big, heavy crane-way - and then take it out
and repair the field - was going to cause too much damage."
The decision resulted in a new issue because putting the machine
on the outside required a long reach due in part to the park's
ramps. A crane that had 120 ft. of vertical reach and 130
ft. of horizontal reach was selected.
Two lanes of 35th Street and the adjacent sidewalk were closed
to ensure pedestrian safety during the movement of the crane
around the ballpark perimeter. An interlocking plastic mat
was laid to protect the ground against damage.
Doing major construction in an occupied building was also
a matter. Offices for ISFA and the White Sox are in the park,
and the stadium club is a rented for wedding receptions and
other parties.
People were told, sometimes more than once a week, which parking
lots and which specific entrances they could use.
Steeling the Schedule
Ensuring work is done before players take the field in April
was the ownership's top concern, said ISFA's Polvere.
"Our biggest crowd is usually on the first day,"
he added.
The disassembly was done over two shifts to ensure a quick
jump on the work, and one shift was later instituted. The
timetable is being met partly because of the mild fall and
early winter, though Sunday and late shifts under lights will
be allowed if inclement weather causes missed days.
"I don't want to do that unless I have to because of
shadows," Hill said. "Iron workers don't like to
hang structure under lights unless you got great lights."
Even the approximately 1,000 sheets of structural-steel drawings
were put on the fast track. The fabricator, structural engineer,
architect and others have met face-to-face each Wednesday
to go over drawings and requests-for-information, and individuals
who reviewed drawings worked on Sundays.
"Everybody said if we want to get it done, this is the
way it has to work," Hill said.
|