Northwestern
University's Lurie Project
Medical-Lab Building Tests Sitework, Design Teams
by Craig Barner
The team for the $165 million Robert H. Lurie Medical Research
Center had to dig deep.
The facility in Northwestern University's downtown Chicago
campus required a cavernous space below grade, said Tony Louvis,
project manager with New York-based Davis Brody Bond LLP,
the architect.
The 40-ft.-deep basement will contain holding areas for animals
used in medical research. Because of regulatory requirements,
a large number of mechanical lines will feed the space, and
redundant services protect against loss in case a system goes
down.
"Many animals are the products of five years of breeding,"
Louvis added. "If anything should happen to the animals,
it's a catastrophic loss for the people doing the research."
The construction team was concerned about the project's location
in the city's building-dense Streeterville neighborhood, said
Joel Klahn, project executive in Chicago with Turner Construction
Co., the general contractor. Pressure from adjacent structures
on the excavation walls could cause them to move. And, unintended
outcomes could include the settlement of the street or adjacent
buildings, the cracking of foundations or damage to utility
lines.
As a result, an earth-retention system that employs grouted
steel tiebacks, or tendons, will make the building's foundation
rigid and secure.
"It was a lengthy review with the city to ensure we wouldn't
damage the public way or any public utilities," Klahn
said.
|
Let's Dance
The installation of the tieback system was choreographed
carefully.
The Passavant Pavilion previously on the spot was demolished
in the latter part of 2001, and steel sheeting was driven
the following spring about 60 ft. deep into the site perimeter.
Excavation began soon thereafter.
The installation of the approximately 950 permanent tiebacks
under the surrounding streets and properties was done over
three levels of depth, said Ron McAllister, Turner site superintendent.
Whaler beams were installed horizontally on the sheeting's
interior face, also at three levels. Through the beams, 4-in.-diameter
holes were drilled about 50 to 60 ft. in length. A grout tube
and either steel rods or steel cables were inserted, and grout
was pumped in under pressure and allowed to set.
Bolts on the sheeting's inner face were tightened to raise
the tension to precalculated levels, Louvis said. The friction
of the soil against the hardened grout ensures the stability
of the foundation and that of the surrounding properties.
"We're inducing stress in the cables to ensure that when
the sheeting wants to move, it can't," Klahn added.
The sheeting has a 10-ft.-deep toe below the basement's lowest
level to help anchor the base of the sheeted wall. An independent
foundation wall made of concrete rounds out on the below-grade
interior.
The independent wall helps ensure the space remains dry, Louvis
said. The site is only about a block from Lake Michigan.
Enhancing the Medical School
The facility is being built to elevate the stature of Northwestern's
Feinberg School of Medicine.
"The way you do that is to increase the research base,"
Louvis added.
Construction of the 418,000-gross-sq.-ft. facility on the
southeast corner of Superior and Fairbanks streets is expected
to finish in November.
The 12-story building will feature nine floors of laboratories,
and each level will have 12 laboratories, said Jo Le Mieux-Murphy,
project administrator with Northwestern's Facilities Management
Design & Construction department. The structure will house
about 700 researchers, postdoctoral students and laboratory
technicians.
Research in many advanced areas - cancer, genetics, neurology,
infectious diseases and nanotechnology - will be conducted
in the building.
The remainder of the facility will include lecture halls,
auditoriums and dining on the first floor and mechanical equipment
on the second and top levels, in addition to the basement.
Sensitivity to the surrounding campus buildings, many featuring
Gothic design elements, was important, Louvis said. Steel
columns will be exposed, and the steel crossing the top of
the building will call to mind flying buttresses. Architectural
precast dresses the building.
The facility is named after the late real estate developer
whose wife, Ann, a Northwestern trustee and principal of Lurie
Investments Inc. in Chicago, made a $40 million gift for the
project.
Setting Up the Site
The replacement or modification of utility lines around the
site was done as a precaution to ensure that they would not
fail in case settling did occur.
"The project inspired the utilities to do something they
had always wanted to do," added Gerald Pinka, chief maintenance
engineer in Facilities Management - Operations with Northwestern.
Many of these systems were originally built in the early part
of the previous century and were not sturdy enough to handle
movement were it to occur.
Gas mains and branches were replaced, steam lines were retrofitted
with flexible joints and a water main on Superior was taken
out of service. The replacements of some lines were extensive.
For instance, steam lines were replaced on Huron and Superior
streets. Because of the demolition of Passavant, a trench
was dug on the south side of the property to accommodate the
reroute of a steam line originally connected to that structure.
For gas, an approximately 6-ft.-wide trench was cut on three
streets surrounding the site.
A large number of footings for the support of buildings previously
on the site was unearthed and removed, including wood pilings
with concrete pile caps and caissons. More than 100 piles
were discovered.
Care was taken during removal. "We couldn't extract [the
footings] for fear it would encourage movement of the surrounding
soil and structures," Klahn said. A powerful backhoe
was used to break apart pieces and scoop them out.
Wiring a Lab
Planning was done to accommodate the large number of mechanical,
electrical and plumbing systems.
Two meetings were held every week for nine months to coordinate
the project and make it understandable, Klahn said. "There
were probably 15 people involved close to full time taking
the design and making it into a format the tradesmen in the
field could use to install the systems," he added.
Mock-ups were fabricated for the laboratory casework to ensure
the correct placement of plumbing, conduit and drawers. For
the building's lower levels, the most complicated interstitial
spaces were also replicated to ensure they were accessible
after completion of the building and could be maintained.
The floor-to-floor space on the lower levels is a relatively
generous 20 ft., and because of the complexity of the MEP
system, 12 ft. was devoted to the equipment. Air handlers
were stacked two high on the second floor and three high in
the penthouse.
Sixty-four fume hoods will provide independent exhaust to
the laboratory spaces. They feed the air into nine high-velocity
fans for exhaust.
Clean rooms that are to arrive in modular panels will be installed
on the building's 11th floor. Because of the sophisticated
research planned for the facility, one clean room will be
installed inside another.
The large number of materials for the project in the crowded
city neighborhood caused logistical headaches.
A lot at Erie and Fairbanks streets was available to stage
selected materials such as precast and steel.
But the just-in-time method was used for many other deliveries,
such as the 46 trucks needed to haul the second-floor equipment
alone. Even 28 deliveries were required for the cranes, 10
for the service crane and 18 for the tower crane.
The German tower crane is only one of two in the country,
Klahn said. Powered by electricity, the crane is noiseless.
"People want to sleep at the rehabilitation center near
the site," he added.
|