Acute
Care, Women's Health Facility
Twice the Construction for Lake Forest Hospital
by Jeffrey Steele
Before contractors could begin building the new Lake Forest
Hospital Outpatient & Acute Care Center in Grayslake,
Ill., the team had to deal with delicate sitework issues.
About 7.5 acres of the 44-acre site were wetlands that required
mitigation.
The water was handled three ways. Some was mitigated onsite,
some off-site to an adjacent landowner and some to a wetland
bank.
But mitigation was only part of the story, said Jim Killian,
vice president of Lake Forest Hospital. "As we were doing
the wetland work, the U.S. Army Corps of Engineers basically
modified its whole approval process and delegated it to the
local county authority, the Lake County Stormwater Management
Commission," he said.
"We were the first large project requiring wetland mitigation
delegated to the stormwater management commission. The approval
process took about two years."
As part of the building project, the hospital is maintaining
and restoring the natural site as prairie and wetlands, Killian
added. Formal landscaping will be undertaken only at the main
entrance to the facility.
|
Two Projects Under Way
The $39 million, 137,000-sq.-ft. acute care center is just
one of two projects the hospital is tackling simultaneously.
The other is the Hunter Family Center for Women's Health,
a wing to the existing facility in Lake Forest and 16 mi.
away from the Grayslake building.
Together, the twin projects represent the single largest construction
endeavor Lake Forest Hospital has undertaken since its founding
in 1899.
Budgeted at $22 million, the 77,000-sq.-ft. wing will feature
an entrance and parking lot separate from the rest of the
hospital. The project broke ground in August 2002 and was
ready for occupancy in January.
The acute care center in Grayslake broke ground in February
and is scheduled to be complete in March and occupied the
following month. It is being constructed at 1475 E. Belvidere
Rd.
"Grayslake is the center of Lake County, and it happens
to be the area of the most explosive growth in Lake County,"
Killian said. "A large portion of the people who seek
care from this area drive to Lake Forest, so our goal is to
move as many of the doctors and services as possible to this
growing population."
Killian described the center as "a hospital without beds."
It will feature three floors above a partial basement housing
mechanical space. The first floor offers hospital outpatient
and support services, the second and third floors will house
private offices for doctors.
The Grayslake facility has been "a piece of cake,"
because it's situated on a site formerly blanketed by farm
fields, Killian said.
Ties into Main Hospital
The Lake Forest project was another matter because it ties
into the existing facility at 660 N. Westmoreland Rd., and
all existing mechanical systems had to be integrated with
the new systems, Killian said.
The bottom floor of the four-level women's health wing features
outpatient services, including imaging, ultrasound, bone densitometry,
a health-screening clinic, conference and meeting space, chapel
and retail shop.
The floor above that, designated the first floor because the
wing is built on a hill and allows entry on two levels, features
postpartum maternity services. The second floor offers labor,
delivery and recovery services as well as nurseries. Medical
offices comprise the third floor.
"We had to avoid extended mechanical system shutdowns
in the existing facility, because of the potential negative
impact on patients," Killian said.
The solution required educating the contractor and all subcontractors
upfront about the delicacy of the situation and careful coordination
of scheduling and execution, he added.
Chris Siefert, senior project manager with Kenosha, Wis.-based
Riley Construction Co. Inc., the general contractor on the
Lake Forest project, said the mechanical, electrical and plumbing
work presented challenges.
In creating the new wing, Riley had to match the hospital's
existing 11-ft. floor-to-floor heights. The high ceilings
resulted in a compressed plenum space of just 14 to 20 in.
for the installation of mechanicals, Siefert said.
"That meant we spent an above-average amount of time
reviewing the coordination of the fire protection piping,
plumbing waste, vent and water piping, mechanical ductwork
and piping, medical gas piping and electrical conduit and
wiring," he added.
"If sprinkler pipe was headed north and ductwork was
headed west, you had to make sure one was above the other."
Four to five months of meetings coordinating all the mechanical
rough-ins, including those for isolation rooms, were required
before work could begin, he said.
Working Near a Hospital
Contractors had to work around an existing hospital, which
meant limited access to the facility. They also had to make
sure the day-to-day life activities of hospital neighbors
weren't hindered by construction.
"We had a difficult time with staging, finding areas
on the hospital grounds that would not be unsightly but still
were readily accessible," Siefert said. "We tried
to locate it within the construction limits we had on the
project. We really had just two areas for staging."
The work in Lake Forest also required the creation of a large
water detention basin adjacent to the new wing and parking
lot. The basin was carefully integrated into the campus and
"beautifully landscaped," Killian said.
It joins two other basins on the 160-acre campus.
Lake Forest Hospital chose two different general contractors,
Riley and Pepper Construction Co. for the acute-care facility,
to oversee the building of the two facilities, but there was
significant overlap among subcontractors working on the two
buildings.
Each project was bid separately, but subcontractors were asked
what kind of price break they might offer if awarded both
jobs.
Maintaining crew size on each of the projects wasn't easy.
"For example, if you have the same masonry contractor
awarded on both projects, you may want him on both projects
at the same time." Killian said. "You're competing
against yourself."
|