A Laboratory at Loyola
Careful Dig Precedes Lab Erection
by Elaine Schmidt
Adding a new Life Sciences Education and Research Building
to Loyola University's crowded urban campus has required delicate
excavation work and careful crane choreography.
Workers had to maintain the integrity of adjacent buildings,
relocate utilities, work in the extremely shallow water table
on the Lake Michigan shoreline and keep one of the campus'
arterial roadways functioning while tunneling beneath it.
The $40 million project began May 12 and is scheduled for
completion in November 2004.
|
"The building abuts, but does not share a common wall
with, the school's current chemistry building," said
Ryan Mahoney, project manager for general contractor Power
Construction Co. of Schaumburg, Ill.
Mahoney added that keeping the neighboring building stable
required earth retention work and careful excavation.
Steven Muzillo, project manager for Bensenville, Ill.-based
Lindahl Brothers Inc., the project's excavator, said that
before sheet piling was installed, "we had to probe and
remove any existing foundations that might have interfered
with the new construction."
He said that with the proximity of the neighboring building
required his crews to dig straight down in small sections,
to probe for old foundations and then backfill that hole before
moving on. He called the three-day process "very standard"
in urban construction around existing structures.
Tiebacks under the adjacent building help to maintain that
structure's stability.
"We have been doing vertical and lateral surveys on the
existing structure since we started digging," which is
consistent with work on a site of this type, Mahoney said.
Muzillo said installing sheet piling the entire footprint
of the building was a way of dealing with the site's proximity
to the lake.
"We were digging in sand just a few hundred feet away
from lake Michigan," he added.
"The groundwater conditions were an obvious obstacle."
The sheeting served as a bathtub of sort, allowing crews to
pump water away from the site.
Tunneling in Rogers Park
Excavation for a tunnel, designed to connect the new building
with a related structure across the street, presented additional
water concerns.
"If we couldn't maintain the tunnel in a watertight fashion,
water would come in and flood not just the tunnel but the
adjacent building," Muzillo said.
The tunnel also presented a scheduling issue because it runs
underneath a major arterial on the campus.
"The university asked us to get the tunnel squeezed in
between the summer and fall sessions, which meant that we
could close the road for only about three weeks," Mahoney
said.
Using what he called a "tremendous overtime push,"
Mahoney said crews got the 150-ft.-long, 16-ft.-deep tunnel
in place and reopened the road on time.
But the biggest challenge of digging the tunnel involved utilities.
A 12-KV Commonwealth Edison line, which ran perpendicular
to the tunnel, had to remain in place and in service throughout
the project.
"We had to ground our equipment so that it would not
cause serious injury to anyone if there was a break in the
line," Muzillo said. "Commonwealth Edison was there
with their people on standby through it all."
He added that the university put security personnel on the
site, too, in order ensure student safety.
The tight site has required careful crane choreography and
staging of work.
"We didn't have enough room outside the site to mobilize
a crane, so we put the crane down in the basement," Mahoney
said.
He explained that the building was divided into halves. The
crane was placed in the south half of the building's basement
and used to set steel in the north half. When that was complete,
the crane was moved to the southeast corner of the basement
to set steel for the southwest corner. The crane will be placed
on the site to set the steel for the southeast quadrant of
the structure.
"All the major mechanical components for the building
are in the north half of the job," Mahoney said. "Setting
the steel this way has allowed us to begin major mechanical
mobilization, such as generators, gear rooms and air-handling
equipment, with the steel still in progress on the other half
of the building."
Mahoney said it has been a tough job for the ironworkers who
have had work in extremely tight quarters.
Site Affects Design
The tight site had an impact on the building's design as well.
"We had to come up with a design that would tie the three
existing science buildings together and work as hub for all
of them" said James Lubawy, vice president and project
manager for architecture firm Solomon Cordwell Buenz and Associates
Inc. of Chicago. Those three buildings were a 1950s brick
structure, a 1960s precast structure and a tall Art Deco building,
called the Skyscraper, built in the 1920s.
"Our building is brick and glass with a corner tower
developed to relate to the Skyscraper," Lubawy said.
A deliberate, diagonal traffic flow through the building allows
students to come in through the main entrance on the southeast
corner and move toward the campus, exiting at the northwest
corner of the building.
But the structure's striking four-story atrium, complete with
floating pedestrian bridges and an ornamental circulation
stairway, is the element that unites student and faculty.
"The atrium faces the north," Lubawy said. "That
whole side of the building is a four-story curtain wall. It
takes advantage of the north light and it is open to the campus.
This allows the kids inside to see activity outside and draws
people in, creating a hub."
Meeting Codes
He added that working closely with the city of Chicago and
the university helped avoid what could have been major code
problems.
"You always want to exceed code," he said. "But
some of the codes were written as though we were building
a major chemical fabrication plant. The science building definitely
has chemicals in it, but in minuscule quantities when compared
to a chemical production plant."
Lubawy said that an ongoing dialog between the construction
team, city and university allowed all parties to understand
what sort of chemicals would be used, and in what quantities,
and therefore to understand what sort of codes the structure
really had to meet.
He added that high-rise safety requirements had to be met
because the high ceilings needed to accommodate exhaust ducts
for the various labs made the building qualify as a high-rise
structure.
At the same time, the structure had to meet the life-safety
requirements of a school structure. Sometimes one set of requirements
conflicted with the other.
"We had to sit down with the Fire Prevention Bureau to
work out how to mesh these sets of requirements," Lubawy
said. "The outcome of our discussions is that we are
very much in line with the requirement changes that have happened
after that terrible fire last fall [the Oct. 17 fire in the
Cook County Administration Building that cost six lives].
Lubawy added that the building also performs better than energy
codes for a structure of this nature require.
"A laboratory consumes a tremendous amount of energy
because you have to ventilate chemicals on a constant basis,"
he said. "In a school building you have peak periods
when a lot of teaching is going on and times when there is
very little."
He added that designers diversified energy loads, and the
building's exhaust volumes can be adjusted to reflect the
daily usage pattern.
|