Indianapolis Schools' Plan
Getting an $832M Construction Schooling
by Craig Barner
An $832 million capital-improvement project in the Indianapolis
Public Schools system is so vast that it is expected to run
through 2011.
Work started in 2002, and the two-phase program will result
in new schools and infrastructure upgrades and renovations
to each of the 79 existing facilities, said Debra Kunce, program
manager for Indianapolis-based Schmidt Associates Inc., an
architecture firm. Financing for the $250 million phase one,
which runs through 2006, was obtained through a bond issue.
|
Alternative financing is being sought for
phase two, and discussions are being held with the local Chamber
of Commerce on funding options.
The venture is the fruit of community and internal meetings
that started in the late 1990s, said Steve Young, chief of
facilities management for IPS, which currently has an enrollment
of slightly more than 40,000 students in kindergarten through
high school. Input was sought from parents, business groups,
teachers and others on a strategic plan for the schools, and
improvements to educational quality were identified as the
No. 1 goal.
"The board realized that there were several things they
needed to do to try to improve student achievement,"
he said.
Schmidt Associates was selected as the program manager, and
a facilities analysis was initiated.
Outdated Schools
Several findings emerged, including the portrait of a district
with out-of-date facilities.
"A large number" of the district's elementary schools
are greater than 75 years old, and some are even approaching
a century of use, Young said.
About 90 percent of existing buildings will be retained, but
those schools in excessively poor condition are being replaced.
Three approximately $12 million each elementary schools are
under way - James Whitcomb Riley, Riverside and Eleanor Skillen.
They will replace schools with the same names and be complete
in 2005. Another school, Brookside, is expected to start in
the fall and for completion in 2006.
The site constraints on the James Whitcomb Riley project are
difficult because the existing school is next to the new one,
said Ray Kramp, vice president of Indianapolis-based Smoot
Construction LLC, the construction manager.
The choreography for the new school includes use of the existing
school. The garden was selected to stage some materials and
locate trailers, and the playground was used for faculty parking.
Construction employees park offsite, and most materials arrive
as they are needed.
"Then we have to tear down the old school to complete
the construction of the new one," Young added.
New facilities were also needed because of a slight increase
in enrollment expected during an ongoing phase-out of a desegregation
order, Young said. Students who had been bused for more than
20 years from city communities to surrounding districts are
returning to the IPS system.
As a result, plans call for two new elementary schools, Brightwood
and Haughville.
Though work has not yet started on them, the targeted completion
date is 2006.
"These two new schools are being built in areas where
we formerly had schools but were closed when students were
bused out of the district," Young added.
A Look at High Schools
The need for facility improvements applied to the high schools,
too.
Instruction at the Arsenal Technical High School dates to
the 1910s when former U.S. Army munitions facilities were
used for teaching, though the campus' existing Treadwell Hall
was erected in the 1920s and Stuart Hall in the 1930s.
A key problem in the secondary schools was the aging infrastructure.
The original heating and electrical systems in Arlington High
School, which was erected on the East Side in 1961, were still
in use when the $25 million renovation began in May, said
David Green, project manager for Indianapolis-based Geupel
Demars Hagerman LLC, a joint-venture Arlington construction
manager.
And, materials and finishes were antiquated. The glazed tiles
in Arlington's hallways are so old that their colors are no
longer available.
"Some of those hallways have what I call Brady Bunch
colors," Green added.
In addition to Arsenal Tech and Arlington, renovations have
started on Broad Ripple High School and John Hope Day Adult
High School. Renovations will start later on Emmerich Manual
High School and Northwest High School.
Thirty-six buildings will have been impacted during the first
phase of renovations. The per-school cost ranges between $250,000
and $25 million.
Focus on Labs, A/C
Two elements of critical importance have emerged in planning
and will receive special attention during renovations.
Laboratories will have been improved in the existing middle
and high schools because the state plans to incorporate the
testing of science knowledge in standardized exams that students
must pass to receive their diplomas, Schmidt Associates' Kunce
said. In phase one, the completed upgrade of laboratories
was done in 23 middle schools and seven high schools for $6
million.
These improvements will likely pay dividends in the local
market. Major Indianapolis employers include medical-product
giants, such as Eli Lilly and Co. and Guidant Corp., and automotive
component firms including Rolls Royce and Allison Transmission/GMC.
Another key part to the renovations is that air conditioning
will be installed in each existing school. Most do not already
have it.
"We think there is a direct correlation between the physical
environment from a conditioned standpoint that students get
into when they're taking tests, and we need to bring our buildings
up to that standard and give them that extra boost kids get
in other districts," Kunce said.
Integrating the HVAC ductwork and piping into the 300,000-sq.-ft.
Arlington school represents a problem for the construction
team, Green said. Existing spaces for utility lines were too
small, so ceilings were lowered. A 2,800-sq.-ft. chiller building
was also erected next to the school, rather than having the
components incorporated within.
"Back when this was built, nobody thought of technology,"
he added. "Now you got hot-water lines and cooling lines
[for the air conditioning.] They both take up massive space."
Other renovation activities will focus on classrooms, accessibility,
restrooms, security, playgrounds, distance learning and vocational
facilities.
Minimizing the renovation's impact was considered, especially
since the renovations to the high schools could take more
than two years, Kunce said.
No more than 10 to 13 classrooms undergo renovation work at
any one time because spaces are maxed out when students are
shifted around. At Arsenal Tech, only second-shift work is
done, and multiple shifts are scheduled at all schools when
students are not present.
"To say it's crazy during the summer is probably an understatement,"
Kunce added.
Designed for Students
Key guidelines emerged for the schools' design.
"We spent a significant time on our mechanical system
by asking our engineers to look at long-term operational costs
and how we can reduce these," Kunce said. "If we
save $40,000 a year in building utility costs, then we can
hire another teacher."
Systems were considered based on a number of factors, including
initial cost but also long-term cost effectiveness.
For instance, occupancy sensors and other building controls
were selected because of the potential cost savings in the
long term, the IPS' Young said. But cogeneration plants that
would have provided schools with their own energy were deemed
unfeasible.
The layout was designed in the small-learning-community format
so that particular teachers and programs, such as technology
or arts, are grouped in an area, Kunce said.
At Arlington High School, incorporating the concept has resulted
in building new offices and administrative support areas and
updating rooms with technology, said Green, the project manager
from Geupel Demars Hagerman.
Also, spaces were established for the community. And, durability
was sought so masonry was a primary building material.
"The board made it clear that they do not want cookie-cutter
schools, but we do have expectations from a maintenance perspective,"
Kunce said.
Because of the project's complexity, the Constructware Web-based
project management system is being used. It was employed in
design and construction to post all communications, such as
photographs, design changes and requests for proposals.
"Our rule is if it's not on Constructware, it doesn't
exist," Kunce said.
|