Megawatts
for Megabucks
Billion-Dollar Power Projects Hum in Midwest
by Craig Barner
The thirst for energy is generating billion-dollar projects
in the Midwest.
Indeed, the biggest single project overall in the region might
well be the $7 billion Power the Future initiative, an energy-producing
development that has been started by We Energies, the primary
utility subsidiary of holding company Wisconsin Energy Corp.
in Milwaukee.
Along with that project, a $1.3 billion plan addresses improvements
to the power grid.
The Transmission Expansion Plan received approval in June
from the board of Midwest Independent Transmission System
Operator Inc., a Carmel, Ind.-based organization of 28 transmission-owning
members and other energy firms in 15 Midwest states and Manitoba,
Canada. The transmission companies themselves fund their projects,
and the biggest is likely the $420 million Arrowhead-Weston
line, a 225-mi.-long project mostly in Wisconsin.
|
MTEP's formal announcement was timely. It
came just before a massive blackout in August that left millions
in the eastern Midwest and Northeast stranded in the summer
heat without power.
Around the rest of the Midwest, other power projects ensure
the region keeps buzzing.
A Power Struggle
A looming energy shortage in Wisconsin is driving the Power
the Future project.
"Based on predicted growth, we need more generation and
we need to replace old, outdated facilities currently in use,"
said Russ Mehrman, director of construction management for
Milwaukee-based We Power LLC, the building arm for Wisconsin
Energy Corp. We Power will lease new facilities constructed
as part of the initiative to We Energies.
About $3 billion in new generation will expand We Energies'
capacity from about 6,000 MW to approximately 8,300 MW.
The five coal-based generating units at the Port Washington
plant 35 mi. north of Milwaukee will be replaced with two
combined-cycle natural-gas-fired power blocks for $650 million,
Mehrman said. Combustion turbines will be installed, and the
exhaust gas will go to heat-recovery boilers that produce
steam to turn generators.
Two coal units have been knocked down, and demolition of the
remainder will start this fall.
"The first [coal] unit was put on line in 1935, so we
are looking at putting in much more efficient and environmentally
friendly generation," he added.
The balance for the initiative's generation element will provide
for two coal-fired units at the Oak Creek Power plant 10 mi.
south of Milwaukee.
The two projects are on different timelines. At Port Washington,
demolition of the coal units started in January 2003, and
the project is expected to finish in 2008. Work at Oak Creek
will likely start in March 2005 for completion in 2010.
About $2.7 billion will be channeled toward transmission upgrades,
including adding more than a dozen substations and "miles"
of power lines, Mehrman said.
And, $1.3 billion will go toward upgrading existing facilities
with selective catalytic reduction units and scrubbers. The
catalytic reduction units are designed to provide cleaner-than-normal
emissions produced by coal-fired turbines.
Logistics of Power
The constrained Port Washington site has affected project
logistics: The town is to the north and west, Lake Michigan
is to the east and a bluff and overflow channel to the south.
"What is unique is the site," Mehrman added. "[The
team] had to be creative."
The crew looked toward the water. Vessels on the Mississippi
River and Lake Michigan were used to deliver materials and
components, including stacks, ductwork and boilers. Some materials
were off-loaded in Milwaukee and taken via barge to the plant
where a crane on the existing coal dock was used for unloading.
Each of the two boilers, which were manufactured in Indonesia,
was shipped modularly, with the biggest part weighing 250
tons.
"Most of the major materials are onsite, and the only
thing we're waiting for is the steam generator," Mehrman
said, adding that the component was being stored on a rail
siding.
Even if the materials have mostly arrived, the site issues
do not ease up.
For instance, a pit for a water pump is needed to provide
cooling relief for the steam turbine, and the 40-ft.-deep
hole will be below the lake level just yards away. The concrete-lined
cofferdam is to be constructed to provide a watertight enclosure.
In January, the pit's walls were formed, yet keeping the concrete
from freezing in the frigid Upper Midwest temperatures can
be a struggle. Temporary encloses and propane heaters have
been brought in to keep the ground warm.
Boise, Idaho-based Washington Group International Inc. has
the engineer, procure and construct contract.
Two other recently started power-generation projects of note
in the Midwest are in the earliest stages of construction,
including a $180 million cogeneration project in Madison,
Wis., said Jeff Newman, vice president and treasurer of Madison
Gas & Electric Co. The project is slated for completion
in spring 2005.
Bloomington, Ind.-based Hoosier Energy, a power-supply cooperative
owned by 17 energy-distribution firms, is building a $90 million
natural-gas fired generating plant in nearby Mitchell, said
Chris Tryba, communications manager. It, too, is expected
to be finished in the early part of 2005.
Stringing Wisconsin, Midwest
Like the Port Washington project, the Arrowhead-Weston power
line under construction is intended to ensure reliability.
"Wisconsin has only four transmission lines coming into
it from outside the state," said Pete Holtz, project
manager for Waukesha, Wis.-based American Transmission Co.,
the owner. "Other states around us, such as Illinois
and Minnesota, literally have dozens."
The project between Duluth, Minn., and Wausau, Wis., is expected
to start in Minnesota in the first quarter and run through
2008. About half the line will go through existing transmission
corridors.
The construction cycle will begin with surveying and soil
testing and move into negotiating easements when needed. Construction
follows a typical pattern for the approximately 1,200 steel
towers to be raised, though variations are expected.
Concrete is poured for the foundations, while steel is received
in a staging area for partial assembly. The steel is moved
to the line site and erected by crane into towers 125 to 135
ft. tall. The wire is strung, sometimes in double circuits.
Between 20 and 30 vehicle visits will be necessary for each
tower - or 24,000 to 36,000 trips, Holtz said.
Biosecurity needs to be maintained, especially in agricultural
areas. Boots and tires are selected to ensure pathogens are
not transmitted among farms.
Arrowhead-Weston is on the high end of the more than 100 individual
projects Midwest ISO's members are pursuing, said Jeffrey
Webb, director of planning for the organization. Some cost
as low as $100,000, but all are intended to accommodate load
growth and new generation.
Getting the public to understand the importance of transmission
is the top issue. As a result, the group is working with the
Federal Energy Regulatory Commission and state regulators
to address residents' concerns and related issues.
"People are not used to looking at transmission line
that may originate in another state and then have parts of
it in their own state, so there's a share-benefit issue,"
Holtz added.
|