Lancaster
Condominium
Lakeshore East Makes Maiden Voyage
by Elaine Schmidt
An entire town is under construction on Chicago's lakefront.
The first structure of Lakeshore East, a 28-acre, mixed-use
development that could eventually contain 15 buildings and
5,000 residential units, broke ground in August and is slated
for occupancy in November, with final occupancy in February
and March.
|
The initial building is an $84 million, 480,000-sq.-ft.,
209-unit condominium tower called the Lancaster. It will rise
29 stories.
The site, on a former golf course between Illinois Center
and North Lake Shore Drive, was largely landfill over what
was once a shipyard/rail facility on Lake Michigan.
"The amount of utilities on the site was a challenge
right from the start," said Joel Kuna, project manager
for Chicago-based general contractor James McHugh Construction
Co.
Kuna said workers had to deal with five banks of Commonwealth
Edison cables, water feeds for the city of Chicago's water
treatment facility and gas and phone lines.
"Everybody comes right through my corner of the project,
right down the center of the job between the caissons,"
he added.
The exact location of the utilities was something of a mystery.
"There was some survey information about things that
were supposed to be there," said Brian Scanlon, vice
president and project manager for the project's structural
engineer, Chicago-based Chris P. Stefanos Associates Inc.
"But when we got closer to construction, we found out
there was a lot more there than the drawings showed and it
was in places where it was not supposed to be."
The only solution was to unearth the utilities, map them and
proceed from there.
Kuna said workers moved cautiously and slowly.
"We went in to probe for the caissons that had to be
drilled and to remove any obstructions in the upper 15 to
20 ft.," said Steve Muzzillo, project manager for Lindahl
Brothers Inc. of Bensenville, Ill., the project's excavator.
"We knew there were some unmarked utilities, but we didn't
know to what extent."
"Part of the problem was that the city didn't have a
lot of these mapped so we were trying to find shutoff valves
so we would know how to shut things off or reroute them in
an emergency. The city was learning as fast we were."
The extensive probing took 10 to 11 workdays instead of the
usual three to four.
Moving Water
Kuna said one of the discoveries was that water service to
an existing high-rise was in the way of the project and had
to be moved without any interruption in service to that structure.
"It was a week-long process of putting in pipe and turning
it over," he said.
Muzzillo said the shallow water table at the lakeside site
and buried debris presented yet more obstacles.
"Probing down below the waterline was difficult,"
he said. "We were probing blind with water coming in.
There are old shipping yard slips well below the water table
that had been filled in with whatever debris was left over
when they demoed the rail- and shipyards."
Wood from old docks and boat slips, metal from the rail lines
and remnants of an old sea wall were among the debris used
as fill.
"We had to remove the buried material and sift through
it to get the large, undrillable matter out," Muzzillo
said. "We returned the drillable fill to the hole, things
in the range of 4 in. in diameter or smaller."
He said it took an experienced backhoe operator to pull the
debris from the hole.
Anything he could not pull up he would try to break off. Anything
that could not be removed or broken off was left behind and
mapped out so it could be avoided in caisson drilling.
Garage Redesigned
Once the utilities were located and mapped, it became apparent
that a redesign of the Lancaster's garage, a structure that
supports the first stage of a roadway that will eventually
run through the development, would be necessary.
"We already had that part of the building pretty much
done," Scanlon said. "We had to step back and sort
out where to fit a caisson down between the utilities. Once
we knew where the caissons could do, we had to redesign the
garage."
He said moving the caissons to avoid the underground utilities
required shifting column locations inside the garage and altering
framing in order to support the structure itself and the overlaying
roadway and the loads it will eventually bear.
He said that although the digging and redesign added a few
weeks to the front end of the project, it would have added
much more in time and cost if the underground obstacles had
not been discovered until crews were mobilized and work was
under way.
Muzzillo said caissons on the project ranged from 3 ft. to
5 ft. in diameter and extended to a depth of 90 ft. into the
lakebed below.
The garage is a unique feature of the project.
"We have a Chicago Department of Transportation bridge
deck sitting on top of a private garage," Kuna said.
We have post-tensioned concrete on garage floors two, three
and four, and we have a multistrand, tensioned bridge deck,
all of it cast-in-place concrete."
Coordination was essential in getting the garage and deck
in place before the tower was tall enough to hinder pouring
concrete and pulling cables on the smaller structure. Kuna
added that there was a limited window of time on the CDOT
portion of the project, dependant on concrete strength, in
which deck cables could be pulled and grout applied.
The road will go in piece by piece, constructed with each
structure that sits adjacent to it, until it connects the
various structures of Lakeshore East.
Fitting In
The Lancaster tower's facade will ultimately mesh with the
structures planned for the future of Lakeshore East and the
surrounding skyline.
"We are always fighting with the proportions of these
buildings," said David Lencioni, designer with project
architect Chicago-based Loewenberg + Associates Inc. "We
are fighting length versus height."
He said the challenge was to make a strong statement with
the 29-story tower while keeping the base of the building
at a scale that has a relationship to the town houses that
will eventually go in to the north and south of the tower.
"We have a base of precast concrete and a variety of
punched windows that give it a scale that relates to the town
houses," he added. "We also have a slick, reflective-glass
curtain-wall system, and we took that one step further and
gave it little curve to add more interest."
The gentle curve softens the lines of the building's exterior
and adds interest to the geometry of most of the residential
units on each floor.
The building's exterior also includes what Lencioni described
as a "monumental stair and elevator" that will allow
the public to go from Grant Park to the East Lakeshore's park
below. He said the Lancaster's fitness center and party room
will be located beneath the stairs.
"The stairs change direction about six times, with planters
and various different elevations and a pedestrian bridge 54
ft. in the air," Lencioni added. He called the stairs
and pedestrian bridge facet of the project "pure math."
The Lancaster's condominium units range in size from 710 sq.
ft. to 1,779 sq. ft., with several 1,950- to 2,800-sq.-ft.
duplex units on the lower levels. The single-level units are
selling for $249,000 to $739,000, with the duplex units ranging
from $642,000 to $928,000.
|
A
$2 Billion-Plus Vision
|
The
Lakeshore East development is unique among current urban
development projects in that it encompasses a 28-acre
site in the heart on of the country's most densely packed
urban areas.
Under development by Chicago-based Lakeshore East LLC,
a joint venture of Magellan Development Group Ltd. and
Near North Properties Inc., both of Chicago, the project
is slated to hold as many as 5,000 residential units and
house upwards of 10,000 people by the time it is completed
over the next eight to 10 years. The entire development
is projected to cost in excess of $2 billion.
In addition to the Lancaster, the first building to go
up on the site, the $113 million Shoreham is also under
construction. When complete, it will contain 550 rental
units.
Development for the site, part of which was once a nine-hole
golf course, includes a public park. The park is slated
for completion late this summer and will contain a dog
run, water terraces and a children's garden.
Other Lakeshore East amenities will include retail space
and an elementary school.
The development may also include office space, according
to Sean Linnane, vice president of development with Magellan
Development Group Ltd. Magellan. Market demands will determine
whether future plans include office or residential units. |
|