Chicago's U-505 Submarine
Legendary Vessel Makes Final Voyage
by Jeffrey Steele
Moving the historic U-505 submarine at Chicago's Museum of
Science and Industry to a new exhibit hall meant uprooting
the 60-year-old German submarine from the moorings cradling
it since 1954 and transporting it to its new home 40 ft. below
grade in the northeast corner of the front lawn of the museum's
east pavilion.
The first step was making structural repairs to the submarine
to ensure the World War II-era relic would survive the stress
of its move, said M. Richard Klarich, Museum of Science and
Industry capital program manager for Chicago-based Jones Lang
LaSalle, which manages the museum's facilities and operations
department.
The Jones Lang LaSalle project and development services division
is the overall program manager for the U-505 Relocation and
Conservation Project.
One Last Dive
After repairs were done, the 700-ton submarine was jacked
up, and self-propelled and self-jacking dollies were inserted
beneath it. Once 18 sets of dollies and 144 tires were in
place below the sub, the moving task began.
"It took a day to move it from its original position
west of the Henry Crown Space Center around to the south side
of the space center," Klarich added.
"And then it took one day to move the submarine to the
east side of the space center, and that included making a
180-degree turn. We used a thick, rigid kind of a reinforced
mat called DuraMat on the ground to spread the load."
In total, the submarine was moved about 1,000 ft.
The U-505 sat on the east side of the Crown Center for a few
days while eight supershoring towers were prepared to lower
the sub into the underground hall.
When they were complete, the submarine was taken off of its
wheels.
Klarich said workers "skidded it off," using a jack
and beams with a slide pad. It took a full day to slide the
submarine into place and lower it the first few feet to the
towers.
Then it took another full day to get it down to its final
"resting place," moving it 4 in. at a time.
Each of the towers was built of structural steel, with a column
of wood cribbing. "That's the way they lower it 4 in.
at a time," Klarich said. "Each of those pieces
of timber is 4-by-4 in., and they stack them in a pattern
that allows one layer of 4-by-4 shoring to be removed from
the bottom of each of the eight shoring towers" at the
same time.
Bunker Mentality
Moving the submarine was just one of the tasks for Jones
Lang LaSalle and the general contractor on the project, W.
E. O'Neil Construction of Chicago.
Dennis Murzyn, the O'Neil project manager, said the project
is budgeted at $35 million, including soft costs. It began
in January 2003 and will be complete by the end of this year.
The U-505 exhibit is slated to reopen in its new quarters
sometime in 2005.
Once the project is done, no one at ground level will know
the climate-controlled underground exhibit hall is there because
it will be covered with grass and other landscape material,
Murzyn said.
Created of architecturally cast-in-place concrete, the vault
containing the submarine will measure 100 ft. wide and 300
ft. long and will stand 35 ft. high at the walls. It will
feature an underground connecting link to the main exhibit
hall at the same depth and extending about 55 ft. wide and
100 ft. long.
"That's cast-in-place concrete, too," Murzyn said.
"They wanted to recreate the look of old World War II-era
bunkers."
Two elevators will allow guests to travel to the exhibit floor
or a midlevel mezzanine, from which they will be able to look
over the submarine. A ramp winding down and around the submarine
from the mezzanine will allow guests to view the sub from
every angle.
"You can go into the queuing line, if you choose to go
inside the submarine," Murzyn said. "Or you can
go through the exhibit, bypassing the interior of the submarine.
There will be a lot of interactive [displays] around the submarine
on the main floor."
A Watery Depth
Perhaps the greatest problem in tackling the underground
vault was its proximity to Lake Michigan.
The water table at the site is 6 ft. below grade. What's more,
contractors had to work in close coordination with the nearby
Lake Shore Drive reconstruction project, which includes work
on an underpass at 57th Street.
The other issue was the delicate task of ensuring the Victorian-era
museum structure would not be damaged due to the excavation
of the link from the museum to the exhibit. The 70-year-old
Museum of Science and Industry is housed in a 111-year-old
building constructed for the 1893 World's Fair, also known
as the World's Columbian Exhibition.
Unlike the other grand buildings of the fair's "White
City," which were constructed of wood with plaster surfaces,
the museum building was the only major load-bearing masonry
structure in the World's Fair. It was dubbed the Palace of
Fine Arts because it housed some of the world's finest works
of art, and because of its masonry construction, it was the
only building to survive the fair.
Murzyn said contractors installed a jet-grout column wall
around and underneath the existing museum to cut off the water
underneath it. With water held back, underpinning pits could
be dug and poured to make excavation possible.
Micropile caps and underpinning were used to support the corner
of the museum.
Micropiles were drilled down to the hardpan clay, and then
caps were placed on top of the micropiles.
A post-tensioned beam 5 ft. high, 42 in. wide and 40 ft. long
was placed on top of the caps on the wall's exterior. Another
post-tensioned beam was installed on the inside, this one
5 ft. high, 2 ft. wide and 40 ft. long.
"They had tendons in there to post-tension it,"
Murzyn said. "That also helped support the building during
the construction. We just hung it in air."
Once the post-tensioned beams were in place, contractors got
to work on six underpinning piers, each roughly 3 ft. by 5
ft. by 40 ft. in depth. They were hand-dug and lagged all
the way down.
"They would be filled with concrete, one at a time,"
Murzyn added. "The whole purpose of this underpinning
process was so the existing building wouldn't settle."
Once these steps had been completed, a sequenced excavation
was undertaken.
Meanwhile, the team was at work creating the structural concrete
walls of the vault.
The walls were completed in one continuous pour.
If the walls had been designed to be vertical, as most walls
are, the construction team would have had little problem.
But these walls needed to slope out at an angle from the floor
of the vault. The fear was that if the pour took place from
above, air escaping upward would have created air pockets
in the walls.
"We ended up pumping the concrete from the bottom, using
pump valves and pushed the concrete up," Murzyn said.
At the top of the vault, contractors will use a combination
of vaulted steel box girders and structural steel girders.
The vaulted box girder will be just below grade, along with
acoustical metal decking, lightweight concrete, waterproofing
and geofoam fill.
Geofoam fill was used to lighten the load of earth on top
of the structure. Because the top of the vault is curved,
the amount of soil atop it could have varied from 1.5 ft.
in the center to 6 or 7 ft. at the edges. Geofoam fill allows
a consistent layer of just 1.5 ft. of soil to be placed over
the entire vault, with the fill making up the varying distances
from soil to vault top.
|