Two River Place Condominium
Problems Float Away at Chicago River Site
by Elaine Schmidt
Cramped urban sites are nothing new in the construction business,
but solving problems afloat is an innovative idea.
The tight site at Two River Place, an 18-story, loft-style
condominium project on the banks of the Chicago River, is
flanked by a building, street, parking-structure access ramp
and the river.
Josh Stark, project manager for the project's Chicago-based
general contractor, Bovis Lend Lease, said there was precious
little staging and storage space for the $39 million project
that includes a significant amount of architectural and structural
concrete.
|
The storage solution for the 20-month project, scheduled
for completion in July, was found flowing right beside the
site.
"We called a barge company to see if they would deliver
a barge," said Martin Maxey, project manager for the
West Chicago-based Concrete Structures of the Midwest. "We
had the barge delivered at about 7 o'clock one evening and
tied it up to the bank."
Maxey said the barge essentially came with the necessary permit,
but Concrete Structures had to take some safety precautions
and provide water safety training to its employees.
"Anytime anyone walked on the barge, we had to provide
them with a life vest," he added. He said safety training
focused on deploying life-safety devices in the event someone
should topple into the water. Stored items were transported
to and from the barge by a tower crane, while personnel used
a gangplank for access.
For safety, a barrier of two-by-fours supported by vertical
stanchions was erected around the perimeter of the barge.
Over the course of the six months the barge was in use, no
personnel or equipment went overboard.
The other safety requirement, navigational lights, alerted
river traffic to the barge's presence.
"The barge was long and narrow, 300 ft. by 20 ft., so
it didn't interfere with river traffic," Maxey said.
"We saw other barges and tourist boats going by every
day."
He said it was the first time Concrete Structures had used
a barge on a project, but the firm would do it again, in part
because it provided storage space that no one else could encroach
upon.
A Concrete Project
The project's use of architectural concrete played a big
part in creating a need for the floating storage space.
"The building is loft style, with exposed, round columns
and exposed concrete ceilings," Stark said. "We
had to make sure the finishes on those columns and ceilings
were far above what they would regularly be." Reusable
formwork had to be carefully stored to maintain that high
finish quality.
The building will have 169 units in one-, two- and three-bedroom
arrangements and a fitness center. Unit costs range between
the high $200,000 area and $800,000.
Brian Kidd, senior associate for project architect Pappageorge
& Haymes Ltd. of Chicago, said the extensive use of concrete
in Two River Place stemmed from economic and aesthetic concerns.
"Probably first and foremost was the economy of using
concrete," he added. "It's a structural material
but also a wall finish and exterior finish."
But aesthetic concerns, which he said included reflecting
the look of the One River Place structure, which is also a
concrete building, played a part on the decision.
"We were picking up on some of the vocabulary of One
River Place," Kidd said. "Also, this is a high-rise
loft building, and exposed concrete finishes are a part of
that style."
Kidd added that two six-story buildings flank the 18-story
tower and serve a dual purpose. Calling them "saddlebags,"
he said they add a different type of unit to the development,
one in which residents can effectively pull into a parking
space right outside the door to their individual units.
He also said they "enliven the ground floor where the
185-space parking garage is located and provide a base for
the building."
Concrete caissons and spread footings support the three linked
structures.
"The tower portion of the building is all on caissons,
and the two six-story sections are on spread footings,"
Stark said. "They are connected by expansion joints that
run the length of the building."
He said the building is set back from the river about 30 ft.
With concrete in abundance from the foundations to the finishes
and nestled inside the structure by way of 46 transfer beams,
each about 36-in. deep, delivery of concrete became another
concern. Stark said careful coordination was required to maintain
the steady stream of concrete trucks, which had only one staging
area on Larrabee Street because of environmental concerns
over diesel fumes in the residential neighborhood.
Tolerances were also an issue throughout the building.
"When you are doing a concrete building like this, the
tolerances for concrete floors and for pre-engineered concrete
floors are different," Stark said. "We have to keep
an eye on floor flatness and on the window openings. The tolerances
on the exterior columns had to be tight or the windows, which
had been preordered, wouldn't fit."
Mechanicals Present Concerns
"Any time you have two separate uses, a parking garage
and residential units, mixed up and combined, it becomes a
challenge to find out how you are going to run all your mechanical
work," Kidd said.
Part of the solution was found in creating greater floor heights
at the top of the tower building and at the point where the
tower meets the shorter buildings. That allowed room to thread
necessary MEP and HVAC systems through the three buildings.
Stark said installation of those systems required constant
communication between the trades.
"In floors seven through 17 there are 130 openings in
each floor, because you have a plumbing riser for every bathroom
and kitchen and duct opening for HVAC," he said. A mechanical
penthouse on the tower's 18th floor houses chillers and boilers
for all three buildings.
Stark said that all the electrical wiring has to run up into
the walls, which means crews have to know where the walls
will be before they pour the floors in order to line up the
openings in the floor slab with the 3.5-in. depth of the walls.
Other Site Issues
Not all of the project's issues stemmed from a tight site
and intricate concrete work.
Previous uses of the site also presented some headaches in
the project's earliest days.
"The site originally had a surface parking lot on it
and a small, one-story building that we demoed," Stark
said. Prior to that it was a Montgomery Wards warehouse.
"When we excavated, we found a lot of foundation materials,
wood piles, foundation walls and a bunch of rubble including
pegboards and water heaters," he added. "It looked
like they had just demoed the old building into the hole and
built over it."
John Shipka, principal with the Enterprise Cos., developer
of the project, said the underground obstructions cost nearly
three weeks on the project schedule as crews worked to clear
the site. He said the time has been made up by Bovis and Concrete
Structures working extra hours and tweaking schedules.
|