Illinois
Tollway
Work on Oases Spans Obstacles
by Jeffrey Steele
The construction team working on the Illinois Tollway Oases
Redevelopment Project never had a chance to rest.
Contractors knew the existing Oases had been solidly built
in 1958, but they had no idea how solidly until it came time
to demolish them. And the work had to be done while traffic
flow was maintained on the roadways below.
The roof structures of the Oases were cast-in-place concrete
bridges standing 14 ft. above the "floor" bridges
spanning the tollways, said Joe Bodzioch, project manager
with James McHugh Construction Co., the Chicago-based general
contractor. Each roof structure bridge featured four 80-ton
cast-in-place concrete girders.
"We were able to demolish the bridge, down to just the
bare concrete girders," Bodzioch said. "The girders
were scaffolded and then cut into pieces that required a 450-ton
crane to hoist them out during evenings. Each of the four
girders was cut into six pieces."
|
The size of the girders surprised the construction team,
agreed Jay Wilton, CEO of Los Angeles-based Wilton Partners,
the development firm on the project.
"When we got to the demolition, we discovered they were
much thicker and heavier than we first estimated," he
said. "We had to get a different crane system and a different
overhead system because they were too big to pick off the
bridges without cutting them up."
After the demolition was completed, every other challenge
on the project seemed more manageable, Bodzioch added. But
that didn't mean the remaining work was free of obstacles.
Seven Oases
The project involves demolishing and rebuilding over-the-road
Oases at Des Plaines, O'Hare, Belvidere, Lake Forest, Hinsdale
and Lincoln, and expanding and remodeling a seventh Oasis,
a facility in DeKalb that stands south of the tollway.
The DeKalb Oasis was built in the 1970s and is in much better
condition than the others. It will undergo a wholesale renovation
and expansion and when finished will feature the same amenities
as the completed over-the-road Oases, Bodzioch said.
The project, with an overall budget of $94 million, will be
done in phases. Work started in July 2003 at O'Hare and Belvidere
and was completed this spring. These Oases reopened on July
1.
Work on the Hinsdale and Lake Forest Oases started in late
April. Work is expected to be complete by Dec. 31, with a
reopening set for late winter 2005. The remaining three Oases
will start construction in July and finish in April 2005,
for a reopening next spring.
The six over-the-road Oases will feature a Cordogan Clark
& Associates design chosen by the Downers Grove-based
Illinois State Toll Highway Authority and Wilton Partners.
Clad in curtain wall with 30-ft.-high ceilings, the masonry
and steel truss buildings showcase an arched design on the
sides overlooking the tollway.
There will be more bathrooms and considerably more restaurant
and service businesses in the Oases than before. The main
anchor restaurants will now feature drive-throughs for motorists
who do not want to leave their cars. There will be picnic
areas and dog runs outside.
Each Oasis will have 11 in-line or permanent tenants and another
10 free-standing tenants in main-concourse kiosks. Among the
tenants are Starbucks, Krispy Kreme, McDonald's, Subway, Panda
Express, Travel Mart and Illinois Lottery, as well as a Fifth
Third Bank ATM facility.
In addition, ExxonMobil is rebuilding all of its Oases gas
stations and is opening car washes at what the Illinois Tollway
calls "select facilities," including the Lake Forest
Oasis.
Tunneling Over a Roadway
One of the little-known facts about the over-the-road Oases
is that most of the utilities for the rest stops and their
bookend gas stations run through the bridge spanning the tollway
below.
Water and power come in on one side, and travel across the
bridge to the other side.
That meant logistical headaches for the contractors, Bodzioch
said. At the O'Hare Oasis, for instance, the gas stations
shut down at the beginning of the project in July and remained
shut through September.
"We had to complete a number of aspects of work in order
for the gas stations to be able to open," he said. "We
had to complete the Oasis utilities, water and sanitary sewer,
and electrical."
Work on the utilities also involved problems, Wilton said.
"The bridges are only about 4 ft. thick, and there was
a tight crawl space where the old utilities were laid in,"
he added.
"We had to demo out those spaces and put in all new utilities.
And that literally meant guys had to crawl into those tight
spaces to do the demolition, almost like they were in a mining
operation. It really is a tunnel."
Before those workers got accustomed to tight spaces, Wilton
Partners had to adjust to working with a state agency.
"Time frames were extended, and there was a lot of oversight
by consultants hired by the state," Wilton said. "We
ended up doing something akin to a public works project in
that we were doing all the design before the project was even
bid."
He added that in the private-sector retail development projects
Wilton Partners normally undertakes, work is fast-tracked.
The concept is finalized, working drawings are started and
all final design work is completed while the project is in
process.
But in the Oases Redevelopment Project "we were not able
to even begin demolition until 65 percent of the final drawings
were done," Wilton said.
Safety First
A major priority throughout the work has been the safety
of workers and the traveling public, Bodzioch said.
"We tried to minimize impact to the public by having
operations work during off-peak hours," he added. "We
have further ensured safety by doing certain operations in
conjunction with lane closures, such as demolition, steel
erection, masonry and curtain wall. We've worked closely with
the [Toll Highway Authority] to develop plans for each operation.
And we have a dedicated safety manager for the projects."
A great deal of nighttime work was performed to minimize impact
to traffic and to ensure lane closures were undertaken at
the safest times of the day.
"We had round-the-clock operations going on in multiple
sites at times," Bodzioch said.
Wilton termed the project "one of a kind" and said,
"It's a bellwether project for other toll authorities
and transportation agencies."
For instance, the Florida Turnpike Authority has pushed through
legislation that will open up development opportunities along
its roads. Pennsylvania has 22 rest stops in need of renovation,
and the state is preparing a request for proposal expected
to be issued later this year.
|