Milwaukee's Northwest Sewer
Tunnel Bends Beneath Residential Area
by Elaine Schmidt
Work is anything but boring when you are boring a tunnel
165 ft. beneath an urban residential neighborhood.
A 7.1-mile, 20-ft.-diameter tunnel is under construction on
Milwaukee's Northwest Side and intended to add 88 million
gallons, or 22 percent of current capacity, to the city's
405-million-gallon deep-tunnel system.
The $117 million Northwest Side Sewer Relief project began
in May 2002 and is slated for completion in 2006.
|
Martin Vliegenthart, project manager/general superintendent
for Bethesda, Md.-based J.F. Shea Inc. of the Shea Kenny Joint
Venture contracting team, said the project employed both traditional
drill and blast methods of tunneling and a tunnel-boring machine.
Wheeling, Ill.-based Kenny Construction Co. is the other member
of the contracting team.
He said of the 11 shafts required on the project, which include
drop shafts, access shafts and diversion structures, seven
were bored and four were created with drill and blast. A TBM
was used for the length of the tunnel itself.
Having a Blast
Blasting the various shafts in densely populated neighborhoods
required communication with residents nearest the blasting
operation and proactive steps to ensure that no damage was
caused on the surface.
"We had complaints when we first started blasting,"
said Roger Maurer, conveyance section manager for the Milwaukee
Metropolitan Sewerage District. "But that's pretty normal."
He added that there were only two blasts per day, one in the
morning and one in the afternoon. At that pace, the shafts
descended at a rate of about 8 ft. per day.
Maurer said although the blasts sound like the rumble of thunder,
it took a significant effort to assure neighborhood residents
that no harm was being done to their homes.
In addition to setting up six seismographs at various points
on the surface during blasting, the MMSD visited homes within
a radius of about 500 ft. of the blast beforehand to establish
the condition of the properties.
"We went through and recorded cracks in the walls and
foundation on videotape beforehand," Maurer said.
A local TV station aired a segment on the blasting and its
effect on homes, which also helped allay fears. During the
segment, a seismograph was set up in the living room of a
home to monitor a blast. The test demonstrated that someone
walking through the room created more vibrations in the house
than the blasting.
"They control blasts now so that not all the charges
go off at once," Maurer said. "There are millisecond
delays in the fuses - you can't really hear that - but it
helps control surface vibrations."
Bill Graffin, public information manager for the MMSD, said,
"We had some calls when the tunnel-boring machine was
right under people's homes. Most would call and say they heard
a rumbling, not loud, more like the fan on the furnace kicking
on."
Vliegenthart called the operation a success, saying, "Nobody
sued us."
Using a TBM
The boring machine, a 22-ft. Robbins TBM that was 800 ft.
long with its trailing gear, was shipped to Milwaukee in pieces.
It had to be assembled and given a test run above ground before
it could be disassembled, lowered into the ground and reassembled
to begin work on the tunnel.
The test was performed in a vacant Allis Chalmers shop in
nearby West Allis.
Once underground, the machine relied on a computerized global
positioning system unit to guide it, and several geologists
to predict what was ahead. Both water and uneven limestone
lay in the machine's path.
Maurer said crews removed water from the tunnel at a rate
of about 2,500 gallons per minute, but, "It's always
hard to predict how much water you are going to hit."
He said that it is always preferable to err on the conservative
side. The prediction was closer to 5,500 GPM.
"If we hit more water than we expect, we simply don't
have the facilities to deal with it," he said.
Water pumped from the tunnel was treated at a temporary treatment
facility and then funneled into a nearby river. Tunneling
on a slight upgrade, about 0.05 percent, kept water flowing
away from the operation.
"But the big unknown is what the rock is going to be
like down there," Maurer said. "We did borings every
1,000 ft., in 2.5-in. bore holes. But usually when you hit
bad areas, they are right between bore holes."
In the case of this tunnel, the problems were a long crack
that made the area generally weak and crumbly. Although the
weak rock and the additional water inflow it created were
concerns, proceeding slowly and carefully got the machine
through it. The job is set to come in under bid price.
Maurer said the problems were nothing compared to what some
tunneling operations have hit in other parts of the country.
"The industry is awash in horror stories of tunneling
jobs gone bad," he said, citing projects in which levels
of corrosive hydrogen sulfide in the tunnels have presented
significant hazards to workers and have crippled TBMs. In
extreme cases, the hydrogen sulfide levels can require abandonment
of the tunnel with the boring machine still in it.
Muck Trains from Abroad
Although the tunneling itself went relatively smoothly on
this project, with the machine coming to within a quarter
of an inch of its mapped goal, "Planning was a nightmare,"
Maurer said.
He added that the tunnel and some of the drop shafts had to
be located close to a Moss-Superfund site and some on privately
owned land. A lengthy process of letter writing eventually
got the project moving forward, but in some areas the top
5 ft. of top soil had to be removed to waste management before
shaft work could begin.
Finding an above-ground site for the operation in an urban
location also presented a problem. The solution was found
on vacant land that is part of the Milwaukee County Institution.
Although the site offered sufficient open land for the project,
it also presented some vibration concerns. Maurer said a nearby
building, in which eye surgery is performed, necessitated
testing and also presentations to hospital staff.
Removing the muck created by the immense boring machine is
always an issue in large tunnel projects. Unlike Chicago's
Deep Tunnel project, which employed a conveyor to move muck
from the tunnels, the Milwaukee project used an underground
train system.
"We used five muck trains with five locomotives,"
Vliegenthart said. "These are the same muck cars that
were used to do the Chunnel between England and France. We
bought all of them."
The muck was hauled to a shaft where it was transferred to
the surface by a vertical belt and then trucked to designated
dump areas.
The tunneling operation, which took a little under one year,
is now complete. In mid-June, crews were preparing to pour
the concrete lining of the tunnel.
"We will hopefully pour between 205 and 245 ft., or 660
cu. yds., per day," Vliegenthart said. "We have
a concrete pump that can pump 120 yds. per hour."
He said concrete is pumped down from the surface into steel
forms in 3,000-ft. increments. Then the pump is moved 6,000
ft. down the tunnel to the next drop hole and the process
begins again.
Once the concrete is in place grout will be applied to stop
any seepage.
|