|
State Place
Mixed-Use Project Steers Clear
of CTA
by Craig Barner
Teams for the $100 million State Place mixed-use project
in the South Loop navigated around the Chicago Transit Authority.
State Place, a four-building residential and retail project,
is located between State Street and Holden Court, and a below-grade
CTA tunnel goes through the property, said Tom Conroy, project
manager for Chicago-based James McHugh Construction Co., the
general contractor. The passageway allows pedestrians on the
transit system to cross between two different train lines.
The subway that carries the Red Line is to the project's west,
and the elevated tracks that hold the Green and Orange lines
are to its east.
Accommodating these and other CTA structures - escape hatches
and an elevator on State that handicapped riders can use to
access the subway - was critical to ensure against a conflict
between the State Place and the transit system.
Sarv Nayyar, president of Chicago-based structural engineer
Nayyar & Nayyar International, said transfer beams were
incorporated into the design to shift pressure to foundations
away from those supporting the pedestrian tunnel.
The placement of the transfer beams was a knotty issue.
Putting them below the tunnel was out of the question. The
CTA instructed the team to stay clear of the tunnel.
Plus, underpinning the tunnel for the placement of the beams
would have been dicey. The soil under it was not satisfactory
for the caissons and steel H-pile foundations used throughout
the project.
Locating the beams above the tunnel but below grade was also
impossible because the pedestrian tunnel's top is only about
4 ft. under the surface, and the design called for the transfer
beams to be 4 ft. deep, Nayyar said. Slating the project's
ground level for the beams was unfeasible because space was
needed for the 60,000 sq. ft. of retail that planning had
called for.
As a result, the project's second level was picked for the
beams' location.
Other transfer beams, some of which measure 20 to 25 ft. in
length, are below grade to avoid existing caissons from previous
structures. The beams shift pressure to new foundations.
CTA on My Mind
Even with the placement of the beams solved, CTA structures
like the pedestrian tunnel were always kept in mind.
Excavation included the use of backhoes positioned above,
and the machines were used to their maximum reach to remove
debris, Conroy said. In addition to the operator, a "seasoned"
employee was designated to monitor the excavation to ensure
against damage to other structures.
"We worked closely with American Demolition [Corp.]
to probe during the demolition process for below-grade obstructions
at locations where we had piles or caissons going in,"
Conroy said.
Above grade, a platform was erected over the CTA's elevated
line to catch debris. "Our coordination came down to
how far the hook would extend out toward the track,"
he added.
The project's east wall comes within "inches" of
the elevated structure. Because masons could not easily form
the walls from the outside, they constructed the exterior
at that area from the inside.
Stages were hung so that the masonry could be washed, but
good safety practices precluded performing this task while
the trains were running. As a result, the work was done between
1 and 4 a.m. - the only period when the elevated trains do
not run.
Coordination was so deeply imbedded in the team's mindset
that a sudden city request could be accommodated.
Lanes of State and Roosevelt Road had been barricaded so
that materials and equipment could be staged adjacent to the
site. In February, the Chicago Department of Transportation
requested that the lanes be cleared by March 15 in anticipation
of a flood of people and traffic for the city's mammoth St.
Patrick's Day parade.
The construction team mobilized immediately.
A 350-ton crane was brought in to lift a smaller crane that
had previously been on grade, and it was placed on the fourth
level that had been shored to handle the pressure. Precast
concrete clads the project's four lowest levels, and the precast
contractor began erection immediately. Other materials were
lifted from street level to a low-rise building for staging.
And during this period, the People's Energy utility was laying
a gas main on State while concrete was being poured for the
mostly cast-in-place concrete project. An extra rig was brought
in so as much concrete as possible was pumped into the building
before the barricades were withdrawn.
"We spent most of that week talking with the city to
reconfigure the [street] canopy and to accommodate more material
movement onsite," he said.
Former Police HQ
The project is on the storied site of the former Chicago
Police Department headquarters. In spring 2000 the CPD moved
to 3510 S. Michigan Ave.
Construction began in July 2003 and will finish in March,
though some units will be turned over to residents sooner.
The most dramatic element is the 26-story tower on State
Street, which is interconnected with the other structures
via the first three levels.
The first level holds the retail space, and second and third
floors incorporate 243 parking spaces, said Denise Kallow,
senior project manager for Chicago-based Mesirow Stein Real
Estate Inc., a partner in the State Street Associates development
team.
Four courtyards are atop the parking garage, and between
them are the three "terrace" buildings. Each rises
four levels.
There will be 243 residences in the project, comprising 159
condominiums and 84 houses. Unit prices range between $300,000
and $800,000, and penthouse units could fetch about $2 million
each.
In early August, the residential units were about 72 percent
sold, Kallow said. Six businesses had leased the retail space.
Amenities include a pool, guest suites, community room and
24-hour security. Chicago-based Fitness Formula has leased
some of the retail, giving residents who join the club access
to athletic facilities.
'Green' Design
The city wanted the "maximum" amount of space for
trees and grass, and these were located on the courtyard level.
The greenery echoes Mayor Richard Daley's strong emphasis
for a green Chicago. More important, it might help attract
buyers.
"It's bringing the suburbanites into an urban setting
and not stripping them of that suburban, homey feel,"
Kallow added.
Soundproofing was key to allay concerns about traffic and
CTA noises.
Above the fourth floor, brick and concrete dress the building,
and there is double insulation throughout. Aerated concrete
block, a material developed in Europe and used there for 30
years, was used structurally.
Besides soundproofing, the advantages of aerated block include
lower weight compared with conventional block, insulation
and fire rating, Kallow said.
Accelerating the Project
The project was put on a fast track so that residences can
be turned over to buyers quickly.
Rather than the typical four or five days, concrete pours
were performed in three-day cycles, Kallow said. Crews were
doubled to accomplish this goal.
The extra time allowed for changes to plans to be executed.
For instance, the original plans called for individual water
heaters in the low-rise structures, but a concern emerged
about whether these would provide sufficient supply.
A redesign was done, and the low-rise units will be fed with
hot water from boilers atop the tower, Conroy said. The boilers
were sized to be larger than the originals to accommodate
the increased demand.
|