Chicago Skyway
Redo Shifts to Westbound Lanes
by Craig Barner
Crews rebuilding the Chicago Skyway have had too much work
to do to enjoy the views from the partly elevated thoroughfare.
The $250 million project began in 2001, but there's still
a large amount of construction under way on the 8-mi.-long
highway on the city's Southeast Side, said Kevin Fitzpatrick,
vice president and construction manager for Chicago-based
Alfred Benesch & Co., the construction manager.
The redo of the eastbound lanes has been completed, and the
project is now focused on $100 million in active contracts
on the westbound lanes and affiliated work. Chicago-based
Walsh Construction Co., Chicago-based F.H. Paschen/SN Nielsen
Inc. and Glendale Heights, Ill.-based Dunnet Bay Construction
are the general contractors.
Labor includes temporarily shoring and jacking the Skyway
so that most of the piers supporting the approximately 3.5
mi. of elevated structure can be replaced. Along with the
pier replacement, old bridge decks have to be removed and
new ones installed. Structural steel members forming the high
bridge that spans the Calumet River must be removed and replaced.
An entirely new interchange was installed at 92nd Street
- an element completed in July partly in anticipation of increased
traffic to the Solo Cup factory under construction on the
site of the razed United States Steel Corp. South Works plant
nearby. This included the construction of a retaining wall
with caissons only 15 ft. from the Norfolk Southern railroad
track.
New lanes were added to the 104th Street exit ramp and the
105th Street entrance ramp. An entrance ramp was added at
84th Street in case the existing one near the toll plaza at
87th Street is eliminated in the future to allow for the widening
of the toll plaza.
The Skyway project is expected to be complete in November,
just in time for Thanksgiving Day. Some clean-up work will
likely continue into the early part of 2005.
Overhaul Needed
Tom Powers, chief bridge engineer and deputy commissioner
for the Chicago Department of Transportation's Bureau of Bridges
and Transit, said the Skyway is being upgraded because detailed
inspections in the late 1990s revealed inadequacies.
The Skyway, which originally opened in 1958 as the Calumet
Skyway, showed corrosion, warping or cracks in components,
loads nearing design capacity, excessive maintenance costs
and other problems. The project is intended to upgrade the
Skyway for 50 years.
Other key project elements include the installation of 28
surveillance cameras, landscaping and the reduction of bridge
structure.
About 1,700 lin. ft. of bridge deck was removed between 75th
and 79th streets and about 3,000 lin. ft. at the 106th Street
viaduct, Powers said. Fill placed below the structure will
carry the roadway.
"We eliminated a mile of structure by placing retained
earth fill and thereby reducing long-term maintenance costs,"
Powers added.
Keeping Traffic Going
The project's unique elements required smart planning.
For instance, the Skyway gradually inclines and reaches its
apex on the high bridge, and some of the construction is taking
place at an elevation of about 80 to 100 ft., Fitzpatrick
said. Further adding to the complexity is that traffic has
continued to flow.
About 90,000 vehicles navigate the four-lane thoroughfare
every day.
A primary objective was to have the least impact on traffic
while also finishing the work with reasonable promptness.
Closing two lanes over three phases was considered, but work
could have dragged on for two additional years, Fitzpatrick
said. Instead, officials elected to shut one lane over two
phases.
A movable zipper wall - concrete barriers linked with pins
at project start - was used and allowed three lanes of traffic
to remain open.
In the morning when traffic headed downtown is heaviest,
two westbound lanes and one eastbound lane are open. At noon,
a specially equipped vehicle is driven through the zipper
wall's full 15,000-ft. length to shift the wall so that two
Indiana-bound lanes are open.
The switchover takes about 45 minutes to an hour and is repeated
at 8:30 p.m. for the rush hour the following morning.
"That wall enabled the Skyway to handle the traffic,"
Fitzpatrick said. "You couldn't have done it with one
lane in each direction because there is too much traffic."
The entire Skyway is occasionally shut for short periods
for especially delicate activities.
Recently, there was a 15-minute closing at midnight so the
thoroughfare could be jacked from its temporary shoring. Then,
new bearings were inserted between the bottom of the roadway
decks and the substructure.
Informing Motorists
The zipper wall and careful timing of work were initiatives
that could relieve only a portion of the congestion.
An "extensive" outreach sought to keep the public
informed, said Maria Castaneda, a CDOT media representative.
Pamphlets were handed to motorists to inform them of major
activities that might tie up traffic. Electronic message boards
suggested alternative routes when traffic backed up on the
Skyway or even the Dan Ryan Expressway that the tollway feeds.
Local aldermen were told about the project so they could keep
their constituents abreast of activities.
Onsite personnel monitored traffic flow and passed information
to radio stations that update traffic, including WBBM-AM and
its "Shadow Traffic" report. Newspaper reporters
from Illinois and Indiana were allowed access to key personnel
so that the project could be explained.
"We also have an intensive traffic information system
during the weekend" to help inform motorists going to
events such as a Chicago Bears game or a downtown festival,
Castaneda said.
Steeling the Project
Replacing structural steel members in the high bridge corridor
was an important element, and more than 4.5 million lbs. of
steel were installed.
About 50 floor beams that run perpendicular to the roadway
and underneath the deck are being replaced under the current
contract, as well as most of the associated steel stringers
extending from the beams and parallel with the roadway.
This element feeds off work on previous contracts. Last year,
floor beam sections were replaced under the eastbound lanes
with a splicing plate, and the replacements this year extend
from the splicing plate and under the westbound lanes. The
steel was lifted with cranes on the bridge.
The floor beams attach to trusses on the bridge's sides,
and some bottom chords needed replacement. Because the chords
are under stress, temporary tension rods were placed to maintain
the tautness.
"Then you're able to cut the bottom chord and replace
it and slowly take the load off those tension rods and put
stress back into the structural members," Fitzpatrick
said.
Other materials played an important role in the project,
too, because most of the 42 steel piers are being replaced,
and each new one is formed with cast-in-place concrete reinforced
with steel.
On top of the bridge, pneumatic hammers were used to break
the existing decks, and the pieces were pulled back with loaders
to a working platform. The existing decks had previously varied
between 5.5 and 7 in. in thickness, but the replacements will
be 8-in.-thick, high-performance concrete with a 2-in. latex
overlay.
"In 10 to 20 years, we'll go in and mill off this latex,
and the slab will still be in good shape," CDOT's Powers
said. "It's denser and resistant to the infiltration
of chlorides."
|