Mount Prospect Public Library
Constructing a Compelling Tale
by Pamela Dittmer McKuen
The Mount Prospect Public Library has an adventurous plot
that includes 15 years, five referenda and temporary quarters
for 330,000 books.
Built in the late 1970s, before the days of personal computers,
the square-ish brick building had 50,000 sq. ft. on one level,
with parking below and mechanical penthouse above. It was
designed with expansion in mind.
"Our original roof deck was reinforced concrete about
10 in. thick," said Tom Garvin, head of building services
for the library. "It was built to take a 150-lb. live
load per sq. ft. We always meant to go up."
Over the years, the size of the library's collection more
than doubled. The staff grew from 35 to 125 people, and many
amenity areas were eliminated to make way for more shelves
and offices.
"They were about as out of space as you will ever find
in a library," said architect Jack Poling, a principal
with Meyer, Scherer & Rockcastle in Minneapolis.
The renovation project added a second floor, doubling the
library's interior footage. It includes comfortable reading
niches, separate spaces for teens and tots, expanded and upgraded
public access computer area, meeting rooms and ergonomic staff
work areas. A striking two-story element of precast concrete
anchors the front door and reduces the civic feeling of the
original architecture.
Enormous floor-to-ceiling windows and rooftop light monitors
capture greater natural light. Reflective ceilings distribute
light more evenly and replace the direct lighting that no
longer matched up with work areas.
Further efficiencies are gained through four air handlers
and 90 variable air volume boxes that allow tighter climate
control throughout the building, and three copper-finned tube
boilers do more work with less energy than the two larger
but aging ones.
"The only things that were existing are the concrete
shell and brick on the first floor, and the parking lot,"
Poling said. "Just about everything else is new."
Getting Funding
From the library's standpoint, the major hurdle was funding.
Four referenda, starting in 1987, were defeated, until a $20.5
million bond issue succeeded in 2002.
"Finally, the pieces started coming together,"
added library Executive Director Marilyn Genther.
During the next year, the architect turned design drawings
into construction drawings. The library rented space in a
nearby business park and moved in. It hired Owner Services
Group in Lombard, Ill., to be its representative and the Meyne
Co., a division of Bulley & Andrews, in Chicago as the
general contractor. Construction, which ran about $13 million,
began in spring 2003. The library reopened this fall.
Streets Squeeze Site
The site, 10 S. Emerson St., was a tight squeeze, locked
by main thoroughfares and municipal construction. Illinois
Route 83 runs along the backside.
With limited exception, the erection of steel and precast
concrete was done from the front of the building. The task
required a 500-ton crane with more than 200 ft. of boom, and
a lot of counterweights, said project manager Sam Vaccarello
of Meyne.
"We just about had to build from the air," he said.
"It was an interesting logistical challenge."
"Steel took longer than anticipated to procure,"
said Justin Sager, the owner's representative. "We didn't
enclose the building as quickly as we would have liked, which
forced the project to become much busier during the later
months. Fortunately, our place in line wasn't impacted by
the increase in steel prices."
One of the variables in renovation work is not knowing what
will be found under layers of old construction. In this case,
it was widespread uneven floors. Leveling all of them would
have been cost-prohibitive, Vaccarello said.
The solution was to selectively choose the areas where dips
and deflections would be most apparent, such as beneath long
expanses of terrazzo, glass and millwork, and repair those.
"The issue was an important one," Vaccarello said.
"We involved the owner and rest of the team early on
to let them know the condition existed, and put our heads
together to minimize costs. It's almost impossible to cover
that sort of condition in the bid documents."
Half-Glass Facade
The most dramatic architectural change was made to the windows.
The original narrow vertical rectangles of glass have been
replaced by soaring bay windows that scale a story or more.
Artistically placed mullions divide the large panes and add
further visual interest. About 50 percent of the facade is
now glass, Poling said.
"The idea was to make the library more welcoming and
connected visually to what goes on around it," he added.
"The windows serve the purpose of opening up the building
on the inside, and at night, conversely, to make the library
and the activity and colors visible from the outside."
Sager said one thing that was nice architecturally was that
the glazing is a combination of translucent and clear. "There
aren't magnificent views to behold," he added. "They
wanted to let light in but didn't necessarily want to frame
the exterior views."
Also on the exterior, the brown brick that encases the second
level, although different, is a fortuitous match to the original.
"That was another brainstorm, to tuckpoint the lower
level so essentially the brick and mortar are the same,"
Vaccarello said. "The bricks blend so well they are hardly
noticeable."
Meyne did the tuckpointing.
"One of the comments made often by visitors is how well
the brick matches," Genther said.
|