Millennium
Park Infrastructure
Park's Construction Hurdles More Than Skin Deep
by Jeffrey Steele
Visitors who marvel at the beauty of Millennium Park cannot
see what is below.
But contractors who were part of the Herculean effort to
construct the park's below-grade infrastructure certainly
know what is there.
Rising from track level below and supported by many of the
more than 900 caissons beneath the park are concrete piers
resembling highway bridge piers. Resting on these piers are
specially designed, double-T precast concrete beams that fit
together like an enormous jigsaw puzzle. Each beam is 6 ft.
wide and 3 ft. deep.
"They're similar to beams found in many parking structures,
but these are much more heavy duty," said Karl Hanson,
assistant chief structural engineer at Chicago's McDonough
Associates, the designer of the below-park structure.
A parking structure, for example, is designed
for 50-lb.-per-sq.-ft. loads, but these beams can carry approximately
600 lbs. per sq. ft., he added.
"They can hold up about 4 ft. of earth,
a truck and trees," Hanson said. "So that's a lot
to ask. That's a heavy-duty loading."
The genius of using double-T beams was in
their ability to eliminate concrete form work at the park
level, he added.
"The beams are the working surface
for the park itself," Hanson said. "Once they were
down, workers could drive the cranes on top, walk around and
handle material."
It took a great deal of preliminary planning
before the early construction could begin, said Mike Shymanski,
architect and urban planner with McDonough Associates. The
firm worked out the interface between the city, Metra rail
line and the Metropolitan Pier and Exposition Authority, as
well as CDOT and the Art Institute, Shymanski said.
The busway - a dedicated lane beneath Millennium
Park to be used by buses ferrying convention-goers from riverside
hotels to McCormick Place - was an integral feature of the
interface. McDonough Associates plotted the alignment of the
busway from Randolph Street to 26th Street and between Metra
and city-controlled properties.
"The other thing was to provide future
expansion for Metra," Shymanski said. "In the project,
we provided two new tracks used by the South Shore. And there's
capacity for three additional tracks and two additional platforms.
We also had to engineer the track work and the overhead traction
power for the electric trains, and we had to develop a current
and future track plan."
A Supportive Garage
To build Millennium Park, the old Grant Park North Garage,
which was originally built in 1953, was demolished down to
the piles and rebuilt, said Ed Uhlir, project design director
for Millennium Park.
"They created a foundation that transfers loads more
uniformly to the pile structures," Uhlir said. "We
added an additional structure to hold up the peristyle, the
ice rink and the Park Grill. We added micropiles in the lowest
levels of the garage to support the Anish Kapoor sculpture.
"We also added to the floor-to-floor height on the top
level of the garage, so we had to raise the elevation on the
east side of Michigan Avenue by about 1.5 ft. If you're walking
west to east across Michigan Avenue, you're actually walking
uphill."
The garage also figures in the drainage of the park, as well
as the support of the Kapoor. A below-grade retaining wall
about one-third of the way into the park from the west separates
the garage from the Metra tracks to the east. It also travels
directly below the middle of the Kapoor, helping to support
its weight, said Mike Hanneman, vice president of McDonough
Associates.
Water draining from the western one-third of the park west
of this retaining wall/dividing line flows into the Michigan
Avenue drainage system. The eastern two-thirds of the park,
or everything east of the Kapoor, drains through the Metra
track area and the Millennium Park garage into a sewer built
in the middle of the busway.
"The piping was fairly large," Hanneman said. "It
was tricky because it's only a few feet above the level of
Lake Michigan. It's tricky in the sense you're discharging
into the river at a certain elevation, which is close to the
actual elevation of the lake. So the whole drainage system
had to be designed with that in mind."
Above-Grade Park Topography
Hanson said a waterproofing system was placed on the "working
surface: deck formed by the double-T beams. On boulevard and
sidewalk areas, cast-in-place concrete surfaces were laid
in.
Most of the remainder of the park was then blanketed with
2.7 billion lbs. of soil, but because of loading limits on
the structure below, no area of the park could feature elevations
of more than 4 ft. of soil.
That problem was partially addressed beneath the park.
"The interesting thing was the concept of the park itself
had to be carried down into the structure," Hanneman
said. "If there were vertical curves or contours in the
park, that contributed to the irregular design features in
that the structure below had to match the surface with the
support mechanism."
He said that meant below-grade columns were longer below
higher levels of the park and shorter below lower levels,
which created higher and lower elevations in the park surface.
But in some areas, such as the Lurie Garden, changes in the
elevation of the concrete surface of the park weren't enough.
The solution came in the form of lightweight poly-foam fill.
"The designer wanted to have all these contours, but
we were restricted by the amount of soil we could use,"
Uhlir said. "The deck underneath had a slight slope for
drainage but not the major elevation changes desired for the
garden. We used big white blocks of poly fill."
He said the fill provided a lightweight means of achieving
varying elevations without using heavier materials. Sand or
soil would have been too weighty to meet specified load limits.
The park boasts almost 700 trees and eight to 10 species.
"These are spectacular trees, some with 10-in. trunks,"
Uhlir said. "They came from all over. A lot came from
the Midwest, but some from as far away as New Jersey and Maryland.
We planted hybrid elm trees along Michigan Avenue that are
resistant to Dutch elm disease."
These were intended to mimic the historic "double row"
of American elms along Michigan Avenue planted in 1917. Some
of the elms remain in Grant Park, most near Buckingham Fountain.
As he looks back on the project, Hanson said the major hurdle
was the construction timetable.
"We were under the gun to do this really quick,"
he added. "It was like building a Wild West town. Just
throw it up. We were under a lot of pressure."
|