|
O'Hare International Airport
High-Flying Curtain Wall Taking Wing on Terminals
by Craig Barner
Curtain wall that represents a first-ever installation in
the United States will form terminal facades at Chicago's
O'Hare International Airport as part of a $319 million upgrade.
|
Art Andros, director of development for the Chicago Department
of Aviation, said that the curtain wall will have no mullions
between the glazing. Glass will sit atop glass, and only the
seams will form the horizontal and vertical lines.
Two-ft.-wide metal plates with rods that extend about 1 ft.
from glazing joints will carry the curtain wall's gravity
load, said Tom Chambers, principal architect with Chicago-based
Murphy/Jahn, the project designer. Silicone in the glazing
will keep the plates hidden.
Besides the seam lines, the only visible element will be vertical
cables, which are attached to the glazing's inside face with
brackets. The cables will provide bracing against winds.
The curtain wall will be attached to a column-supported canopy
also being erected as part of the project. The metal canopy
will cantilever over the two inner traffic lanes of the departures
area.
Chicago-based Walsh Construction Co. is the general contractor.
Architect Helmut Jahn worked with structural engineer Werner
Sobek of Germany on the design. "I am told that this
is the first time they have done a cantilever with a canopy
and curtain wall," Andros added.
Germany's Josef Gartner GmbH manufactured the 40-ft.-tall
curtain wall with tinted glass. Testing was done, also in
Germany, to ensure the system could withstand the elements.
A mockup was built, and one trial included subjecting the
structure to 70-mph wind with water propelled from a jet engine.
An independent agency observed the test procedures and recorded
the results to ensure the system meets requirements.
Chambers said that despite the similarity, the curtain wall
is different than the "net wall" that forms the
lobby of the UBS Tower, a much-lauded office completed in
2001 at One N. Wacker Drive in Chicago. The difference is
that the net wall, which is also a first-of-its-kind American
installation, has visible cables horizontally, in addition
to vertically, and a visible gasket in the glazing joints.
|
Project Practicality
Functionality is driving the O'Hare work - formally known
as the Facade and Circulation Enhancement, or Face, project
- especially the need to create more check-in space.
With the exception of Terminal 3's expansion in the mid-1980s,
the check-in and baggage claim facilities of terminals 2 and
3 are virtually unchanged since they were constructed 40 years
ago, even though they now serve several times the number of
passengers.
Under the project's first bid package, the existing curtain
wall and vestibules were demolished on terminals 2 and 3,
and the terminals will be expanded 20 ft. toward the roadway.
This will increase the check-in lobby's width by more than
a third and the clear area in front of the check-in by more
than 50 percent.
The new space will be used for new circulation elements -
glass elevators, glass escalators and stairs - and check counters
more spacious than the existing ones.
"We wanted to keep it open to enhance passenger orientation
so passengers can see where they're going, especially in regard
to [the lower level] passenger tunnels," Chambers said.
"Before, they had no visual connection between the tunnel
level and check-in, and now you'll be able to see all the
way up."
Thirty-five columns that are 23 ft. in front of the existing
curtain wall and spaced 70 ft. apart are being erected. The
metal canopy will be about 2,000 lin. ft. long, and it will
cantilever 42 ft., 6 in.
Face's second bid package, which has not been awarded, covers
the canopy erection for Terminal 1 and the interior renovations
of terminals 2 and 3. The work will include the installation
of new ceilings, signage, lighting, terrazzo tile and rental-car
areas.
Unlike its neighbors, Terminal 1 will not be expanded.
Two tenant projects involving United and American airlines
will occur while the second bid package is under way. "They
are going to be doing a lot of little pieces - curb front,
lobby technology and other things - to bring them up to date,"
Andros said.
A preliminary project element that is already complete involved
the installation of new beams that support the roadway separating
the upper and lower levels and the roadway itself. The change
was needed to beef up these elements to handle the Face cranes.
"[The work] needed to be done anyway," Andros said.
"It was up there for 30 to 40 years."
Face construction started in May 2003, and work is expected
to run until March 2007. The project will act as a run-up
to the airport's $14.8 billion expansion.
"O'Hare is the gateway to our city," Andros added.
"Our customers have to come into a nice-looking terminal."
Dealing with Obstacles
The columns and canopies are being installed bit by bit to
make sure the schedule is met.
Excavation teams encountered old tunnels and utility lines
that were not in drawings, and some foundation types were
changed, Andros said. Micropiles are holding the columns where
there are obstructions, and caissons support the remaining
columns.
"So instead of stopping and waiting for the micropiles
to be done and continue like soldiers going down the terminals,
we jumped ahead," he said. Activity on Terminal 2 was
put off for awhile, and the teams moved to Terminal 3.
The caissons were set 55 ft. below grade on bedrock, and the
eight to 12 micropiles for each column line were seated 10
ft. below the bedrock. The drilling was done on the grade-level
road.
Alerting Passengers
Coordination was key so that the project impact on the 190,000
travelers who use O'Hare every day was kept to a minimum.
Most of the work takes place between 8 p.m. and 5 a.m., said
John Cornell, senior project manager with Walsh Construction
Co.
"We never know when we will have a full day's work,"
he added. "It could be raining in Tennessee, and that
could delay flights here or have flights sent here."
Flexibility was needed because the daily go-ahead to set the
steel varied depending on traffic.
Staging areas were located on Mannheim, Montrose and Bessie
Coleman Drive to allow materials to be delivered quickly.
Some columns were partly assembled in the yards.
The public awareness campaign included putting project information
on the Internet, passing out fliers to taxicab and limousine
drivers and posting road construction alerts on orange signs
outside the airport as far as Cumberland Avenue on the Kennedy
Expressway.
Useful Source
Find out more about the project at O'Hare International
Airport by visiting www.flychicago.com/FACE
on the Internet.
|