Wisconsin
Pipeline
Line Goes Through Town and Country
by Elaine Schmidt
The $41 million Port Washington Lateral pipeline project,
an underground gas supply pipe, will forever change the harbor
area of Port Washington, Wis.
When the pipeline goes into service in December, it will supply
the Port Washington Generating Station, which has relied on
coal to generate electricity for seven decades. The first
phase of plant construction began in 2003 and will be followed
by a second phase in 2005.
The work removes an eyesore, a coal pile from Port Washington's
harbor area, and allows We Energies, the trade name for Wisconsin
Electric Power and Wisconsin Gas, to remove the second of
two towering smokesstacks from the plant.
It has not been an easy job. Burying a 17-mi. run of pipe
- 14 mi. of 24-in. pipe and 3 mi. of 20-in. pipe - stretching
from Jackson, Wis., to the shore of Lake Michigan required
plenty of preplanning and delicate handling.
Division of Work
The pipeline construction began in May.
"There were really two parts to the project," said
Joseph Versnel, president of New Berlin-based Arby Construction,
the prime contractor for the entire lateral installation of
the pipeline. "A rural piece was laid primarily out in
agricultural areas, and the more urban lay beside city streets
in Port Washington."
To get the pipeline laid efficiently, Arby performed the urban
portion of the project and subcontracted the rural portion
to H.C. Price of Dallas.
"H.C. Price is more of an intrastate pipeline contractor,"
Versnel said. He added that the rural sections of the pipeline
could be laid in a streamlined, assembly-line type of operation,
while the urban work required more of a delicate, contained
operation.
"The challenges on the urban portion of the project were
making sure we had proper traffic control and minimizing disruption
to the areas we were affecting," Versnel said.
Crews worked at opposite ends of the project, connecting the
two segments where the pipe size changes from 24 in. to 20
in.
This joint operation required communication.
"We had an overall project manager's morning meeting
every day with us and Price and We Energies," Versnel
said. "Everyone kept abreast of where everyone else was
working and what the issues were."
On the urban side of the pipeline, issues included traffic
control, minimization of disruption to area businesses and
the problems of working in a tight, urban environment.
Some Fragile Terrain
The rural portion of the project, on which crews had the
luxury of working in an assembly-line fashion, presented an
entirely different set of challenges, including a significant
amount of wetland under which the pipe had to be laid.
"We Energies worked with the Wisconsin Department of
Natural Resources to establish construction procedures for
every tract of land that was designated a wetland," Versnel
said. "Sometimes we had to bore underneath it and sometimes
we allowed to do open cuts, to cut right through it."
Boring beneath the wetlands, and beneath Interstate 43, required
six horizontal drills, one of which was 3,000 ft. long.
The biggest concern in boring beneath the wetlands and the
highway was the possibility of "frac-outs" - a release
of material to the surface.
"In a frac-out, seepage comes to the surface and looks
like a mud pile extending out," said Mark Haas, project
manager for We Energies. He said that the seepage is bentonite
clay, the nontoxic substance used to clean out the hole. But
it can be a mess and can cause a problem in the wetlands and
on the highway if it is not cleaned up immediately.
"We were very cautious and had cleanup crews with vacuum
trucks standing by to address is right away," Haas added.
Crews also used large wooden mats to protect the wetland areas
as they worked. Crews and machinery were restricted to the
mats, which distributed their weight over a large area and
protected the ground from damage.
Leaving No Footprints
Laying the pipeline is not the end of the project. A cleanup
phase returns the affected land by trench digging to the state
it was in before the project began.
"If we are crossing someone's front lawn we will lay
sod," Versnel said. "If we are crossing a county
road we have to replace the road. If we are crossing a farmer's
field, we have to put the topsoil back correctly."
Haas called it a "long process" and said the power
company had to file environmental impact and construction
impact statements with the state's Public Service Commission.
The process required testifying at hearings to explain the
reasons for doing the project. The DNR and Wisconsin Department
of Agriculture also had a voice in the early decisions and
planning.
Once the project had the green light, the next task was securing
easements for the project.
"We had to collect approximately 80 easements,"
Haas said. He added that We Energies had to take both temporary
and permanent easements to create a path for the pipeline.
"The permanent easement was 30 ft. wide," he said.
"We paralleled the high-tension transmission line corridor.
Our easement abutted their easement so that we were not creating
much more of a corridor than is already there." A temporary
easement of 45 to 75 ft. was required for the actual installation
of the pipeline.
Since the project serves to better the power infrastructure,
We Energies has the right of eminent domain. If an easement
settlement cannot be reached with property owners along the
path of the pipeline, the power company can take the landowner
to court to condemn the land in question.
"This whole process has to start about two years before
construction," Haas said.
Work on the project actually commenced in December 2001, when
STS Consultants Ltd. in Milwaukee began mapping several possible
pipeline routes.
Gerry Carlson, principal surveyor for STS, said the firm will
be on the job to the end, using a global positioning system
for each 40-ft. length of pipe once it is in the ground. The
firm then will prepare as-built drawings to provide pipe locations
for any future maintenance and repairs.
|