|
Overture Center for the Arts Phase
One
Project of the Year: Cultural
The Overture Center for the Arts in Madison, Wis., is a multi-venue
center for the performing and visual arts located in downtown
Madison.
The project encompasses an entire city block in the heart
of the town's central business district. Unique features include
a modern dome atop the restored Yost's facade, which is visible
from many vantage points in the downtown area.
In the rotunda, light emitting diodes are mounted below each
balcony and are positioned to send a glow of interior light
toward the dome. Each light can produce as many as 20,000
different colors in various sequences for specific events
of seasonal presentations.
In addition, the exterior of the massive glass curtain wall
of the Overture Hall lobby are reportedly the largest glass
panels in any building in the world. At 19 ft. by 9 ft., the
91 individual panes weigh 2,379 lbs. each.
The Madison Symphony Orchestra organ, which has 4,040 pipes
and weighs 30 tons, plus its 120-ton chamber, is said to be
the heaviest moveable object in any theater in the world.
|
New and Old
The project, which is a mix of new construction and renovation
of existing arts facilities in the Madison Civic Center, required
demolition of a number of businesses, included the Bank One
Building.
Demolition had to be carefully coordinated to allow the Civic
Center to remain in operation throughout the duration of construction.
Crews were also required to work around a building in the
middle of the block, which housed a restaurant, until condemnation
and court proceedings were completed.
Throughout the entire project, construction crews were required
to build to a zero lot line condition with only the sidewalk
and one traffic lane closed on two sides of the job site.
Staging and storage areas were also limited and continue to
be so as phase two of the Overture Center project progresses.
The project collected for recycling 74 percent of building
materials during demolition, donating as much deconstructed
material as possible to local nonprofit groups. In total,
5,395 tons of fixtures, stone, metal concrete, carpeting and
ceiling tiles were recycled or reused.
In addition, an extensive effort was made to preserve the
Indiana limestone from a building that was torn down in the
construction process. About 650 stones, weighing 60 tons,
were numbered and saved to be used in a future downtown construction
project.
Some stones were more than 6 ft. in length and weighed more
than 800 lbs.
On-site recycling containers for wood, plastic, concrete,
metals and blueprints ensured that more than 50 half the construction
waste was kept out of local landfills.
'Green' Building
The building was chosen as one of the leading projects in
the state for sustainable design by the Wisconsin Green Building
Alliance.
When new materials were selected and procured, every effort
was made to do so in an environmentally conscious and responsible
way.
For instance, wood panels covering the ceilings and walls
were selected from a forest certified for its sustainability
and conservation efforts. English figured sycamore, used in
paneling throughout Overture Hall, comes mostly from two large
logs forested in Germany following sustainable methods.
Overture Center is the first major building project in Madison
to use green concrete, a mixture that uses less energy to
produce and is stronger and easier to work with than regular
concrete. When both construction phases are completed, Overture
Center will exceed energy code requirements for building envelope
and mechanical systems design.
Overture Center was built on a fast-track scale, which required
construction to begin with uncoordinated, incomplete design
development drawings.
During phase one of the project's design evolution, the project
management team went through 15.3 tons of recycled drawings
alone.
Two major elements of the project - the installation of the
127-ton glass curtain wall system and the task of making 197
tons of pipe organ and orchestra enclosure moveable - are
believed to have never been done before anywhere.
The constrained site and limited staging area meant that major
pieces of material, such as the steel trusses that span Overture
Hall, had to be assembled at different locations and brought
in separately.
The jury said, "Overture Hall is spectacular. There were
a lot of unique things they did on the project, such as the
recycling of construction waste. The navigation they did in
the tight site was also well done."
|