|
St. Luke's Medical Center Cardiac Center and Patient Tower
Project
of The Year: Health Care
St. Luke's Medical Center saw increasing demands in surgery,
intensive care and medical/surgical beds.
The Milwaukee hospital sought an innovative design for the
addition of its $180 million Cardiac Center and Patient Tower.
St. Luke's worked with the design team to evaluate several
options to maintain patient convenience and staff efficiency
on an already congested campus.
The decision was made to build a 12-story facility above an
existing six-story parking structure located in the heart
of the campus.
A Hospital on Stilts
Once the location had been established, project engineers
devised unique coordination, design and problem-solving strategies
to accommodate building the structure above the parking garage
while meeting the hospital's need for both the garage and
hospital to remain fully operational throughout construction.
Dubbed "the hospital on stilts," the tower sits
on columns spaced much further apart than a typical building,
thus allowing for uninterrupted traffic flow in the garage
below. The potential for transfer of vibrations to the tower
was eliminated by preventing the columns from having any contact
with the garage.
The tower's foundations were constructed on the roof of the
garage, rather than at ground level, due to both campus congestion
and the need to preserve the existing garage.
The parking structure, which had to remain open to the public
throughout construction, was shored and a 65-ton crawler crane
was disassembled on the ground and then reassembled on the
garage roof to punch 6-ft.-diameter caissons through the existing
structure and 100 ft. below ground into bedrock.
A second crane worked from the ground level outside the garage
to assist the caisson drilling.
Significant loads were carried by the truss system because
of the long spans between the columns.
Trusses from Europe
The design called for trusses that were 32 ft. deep. Each
truss weighed up to 1 ton per ft. and required some sections
so large that they were not available in the United States.
As a result, they were imported from Europe.
The trusses were erected using a piece-by-piece method of
assembly with a tower crane. Truss connections were designed
using plates up to 2 in. thick and, in some locations, more
than 500 bolts per joint.
The materials fit together to form what was termed the "tabletop"
supporting the tower above. The space between trusses provided
a convenient location to house the building's mechanical systems.
The stilt design allows for the addition of floors below the
tower in the future when the existing parking structure is
removed.
Accommodating Medical Operations
Reduction of vibrations caused by large reciprocating air-handling
systems was key due to the location of a highly sensitive
surgery level directly above the tabletop.
Also due to vibration concerns, the steel-encased, concrete
columns that support the tower are up to 5 ft. in diameter
and 90 ft. tall and are independent from the parking structure
below.
Complete structural models were created to simulate the building's
vibration characteristics and identify whether any deficiencies
were present in the structure.
As construction proceeded, vibrations were monitored and the
model ultimately confirmed that the sensitive surgery floor
did perform within acceptable limits.
A building enclosure mock-up was built and tested for structural
and thermal elements.
In addition, a unique program of enclosure quality management
was developed and implemented. This ensured that the building
enclosure was constructed to incorporate the information learned
from the mock-up testing and the enclosure components were
installed according to specifications.
Strict internal air quality requirements were established.
HVAC ductwork, water and gas piping all came to the site capped
so that no ends were exposed. Air handlers and other equipment
remained factory sealed until installation to eliminate the
possibility for dust and mold issues.
The jury said, "What a project! They went to Europe for
the trusses. The staging was complex. The architecture is
beautiful. And they did it all over an existing parking facility."
|