|
Indianapolis Public Schools
Team Aces School Test While Students Watch, Learn
by Jeffrey Steele
The construction teams building new schools on the sites
of existing schools for the Indianapolis Public Schools system
are working while classes remain in session.
|
The task has required working in extremely tight sites, said
Randy Waren, project manager on Eleanor Skillen School 34
for the Indianapolis-based joint venture of Shiel Sexton Co.
Inc. and Corbitt & Sons Co. The site of School 34 is bordered
by narrow city streets on three sides and by Interstate 65
on the other. In addition, it features shallow setbacks from
sidewalks and streets.
"The project left very small amounts of area to be utilized
for construction staging, and that required as-needed deliveries,"
Waren added. "The other challenge was all deliveries
had to be coordinated around the start of school and dismissal
of school. The streets are tight for buses, even without any
additional construction traffic.
"And special additional logistical planning was done
for any especially large deliveries or crane movements to
set the steel and mechanical equipment."
For instance, the route to be used for the delivery of the
chiller was planned long before the delivery, and streets
were walked and measured to ensure trucks could deliver to
the site, Waren said.
The tight sites also impacted contractor parking. At one school
project, construction workers parked at a nearby church, and
at others, they parked on adjacent side streets.
Ray Kramp, vice president of Smoot Construction LLC in Indianapolis,
mentioned the same kind of obstacles for the construction
of James Whitcomb Riley School 43.
"We had limited parking for the faculty, limited space
for bus unloading, limited space for construction staging,"
he said. "It's a phased construction, and once the new
building is up, we'll raze the old one, and then build the
kindergarten addition on the site of the old building."
Beneath the site of the old building, Smoot will add utility
infrastructure for the new school, including a storm water
retention system composed of underground pipes.
Learning plans were created that allowed pupils to learn from
the construction projects. At School 34, for instance, pupils
worked with the architects and contractors to create a wall
mosaic of materials from both old and new schools that will
appear in the new
Elements of $832M Plan
Construction of School 34, School 43 and Brookside Elementary
School 54 is part of a much larger project, said Debra Kunce,
program manager for Indianapolis-based Schmidt Associates
Inc.
The architecture firm serves as program manager for the entire
school construction project and is responsible for $250 million
worth of work on 36 IPS schools in phase one of the project.
This phase is part of a 10-year plan to improve all 79 of
the system's schools at a budget of $832 million, Kunce said.
Schools 34 and 43 are under construction and are slated to
open in spring 2005. Construction will begin on School 54
in the spring, with a slated completion date during the school
year of 2006-07. All three schools are replacing old schools
bearing the same names built during the period from 1910 to
1912.
The three schools are each budgeted at about $11 million in
hard construction costs. School 34 was designed by Fort Wayne-based
Schenkel Shultz. School 43 was designed by Indianapolis-based
Blackburn Architects, and School 54 was designed by San Francisco-based
URS Corp. and will be construction managed by Smoot.
Each is based on the same program, accommodating 600 pupils
and featuring kindergarten through fifth grade.
However, the program is adapted to the individual school sites,
Kunce said.
"These buildings are intended to be community-based schools,
with rooms in each one dedicated for use for community meetings,"
she added. "There will also be offices for Indianapolis
parks and the YMCA, so they can run after-school programs."
The new schools are the first IPS facilities to be built in
10 to 15 years, Kunce said.
Two additional schools starting construction in the spring
will not replace existing schools. James Russell Lowell School
51 in the Martindale-Brightwood neighborhood and Wendell Phillips
School 63 in the Haughville neighborhood will serve communities
that due to a desegregation order that sent students to other
communities, have not had IPS schools in at least 20 years,
Kunce said.
Sites Averaged 2.5 Acres
To accommodate construction, additional land was acquired
where possible.
That was necessary because the sites for Schools 34, 43 and
54 averaged just 2.5 acres.
But the added land won't be enough to build the entire new
school without demolishing the old one in every case. For
example, School 34 is being constructed in two phases on its
2.8-acre site, Waren said.
Approximately 80 percent of the new building will be complete
in the spring, and pupils and teachers will move in at that
time. Then the old building will be torn down, and the new
school will be completed on the site of the former school.
Safety of pupils, teachers and staff was a primary concern.
In addition to suspending material deliveries during the times
when pupils arrive at and leave school, contractors ensured
construction areas are fenced off at all times, Kunce said.
Hallmarks of the new schools' construction have included highly
durable materials and abundant use of windows. The IPS builds
its schools to last at least 50 years, Kunce said.
For that reason, "materials of permanence" such
as terrazzo corridor floors, concrete masonry unit walls and
brick masonry exteriors were chosen.
Durability was also behind the decision not to place mechanical
equipment on rooftops, where it would likely sustain damage
from the elements.
Natural light was another priority. "We have a significant
amount of windows in the classrooms to ensure natural light
in students' regular learning environments," Kunce said.
"Even our dining rooms and media centers have windows."
Attention to current and future budgets led to analyzing a
number of potential mechanical systems to determine which
was most economical in initial cost and day-to-day operating
costs.
"In school systems, you pay for energy out of the same
fund that pays teachers," Kunce said. "If we can
save $40,000 a year on energy costs, we can put another teacher
in the classroom. It really does make a difference."
The new schools will also feature air conditioning, which
isn't the case at all IPS facilities. A study last year showed
IPS pupils in air-conditioned schools scored an average of
eight points higher on standardized tests than those at schools
without it.
"We know adding air conditioning to these buildings will
help the students of IPS," Kunce said.
|