O'Hare Hotel Market
New Hilton Rooms Just 'Inn' Time by
Paula Widholm In anticipation of a resurgence in the long-sluggish
hotel market surrounding Chicago's O'Hare International Airport, Raymond Management
Co. broke ground nearly a year ago on its nine-story, 253-room Hilton Garden Inn
Chicago-O'Hare Airport hotel in Des Plaines.
|
The hotel represents one of the largest Hilton Garden Inn properties to be
constructed within the United States.
The Madison-based owner/developer
had conceptualized bringing this hotel product to the O'Hare market four years
ago.
"We felt we had a product and an idea and were able to obtain
a site," said Jeffrey Raymond, president of Raymond Management. "We
closed two weeks after Sept. 11."
With the entire hotel industry hitting
a severe slump after the terrorist attacks, the project at 2930 S. River Rd. was
put on hold. It is now scheduled to be complete this summer.
Raymond isn't
the only owner showing confidence in the O'Hare hotel market.
The 362-suite
Renaissance Chicago O'Hare Hotel has been empty since its completion in early
2003, but its new owners plan to open in February. A 206-room La Quinta Inn &
Suites-O'Hare is also slated to open this fall.
He added that the Hilton
Garden Inn's amenities would attract small groups or two-day seminar events. Features
include 7,000 sq. ft of flexible meeting space with high-tech capabilities; 24-hour
complimentary business center; fitness center; indoor swimming pool; and full-service
restaurant. The property will also provide on-grade parking for 238 vehicles.
Preparing the Site The 3.25-acre
site contained a 40-year-old bowling alley and restaurant. Due to the age of the
former 32,000-sq.-ft. structure, an asbestos study was required, and the hazardous
material was found in the building's flooring, ceiling tiles, piping and insulation.
"The
asbestos had to be removed prior to doing any demolition," said Steve Miller,
project manager with Rosemont-based McShane Construction Corp., the project's
general contractor.
After the Elgin-based American Demolition Corp. removed
the asbestos, the structure's basement was excavated and removed, along with the
asphalt and all underground utilities.
"Because of the differences
in construction methods, the standards of materials used were of less quality
than now, so we were removing more material than typical," Miller added.
"We had to get rid of the foundations and start with a new site."
Specifically,
the underground utilities, storm and sanitary system were deteriorated, and the
water main was cracked. Some materials such as the brick and steel were recycled.
After
excavation, the site was raised approximately 3 ft. with fill material, which
was then compacted to a compression level to support the building.
The
nearby Des Plaines River also posed a challenge.
"Because we were
so close to the Des Plaines River, the water table is high above the slab of the
basement," Miller said.
Instead of digging well points, one section
of the basement was overexcavated to collect all the water, and then it was pumped
out.
McShane staged the site construction by first completing 80 percent
of the curbs, gutters and asphalt to store construction material. The new building
is also used for temporary storage.
The hotel has two basements, in its
northwest and northeast corners, totaling 4,000 sq. ft. Because both basements
abut closely to the property line, shotcrete was sprayed on the slope of the soil
to prevent it from caving in. The 20-ft.-deep basements will hold the HVAC equipment,
which will maximize the first-floor area for the lobby, dining, meeting space
and swimming pool.
Opting for
Precast Structural precast concrete was chosen over block construction in
anticipation of erecting the building during Chicago's harsh winter months, said
Gary Brink, owner and president of his namesake architectural firm in Madison.
Brink
said precast panels go up quickly on the site, but coordination is important when
they are being cast. "Everything has to be exact; there's no forgiveness
after it's cast," he added.
Raymond said the precast system saved
money considering today's high steel prices. The structural system is 95 percent
precast concrete planks with some supporting steel for the first floor only. The
precast plank floors were covered with gypcrete for leveling.
"Due
to the size requirements the Hilton Garden Inn has for rooms, and the site restrictions,
we cast the electrical into the precast wall panels, which saved room," Miller
said.
The 5/8-in. drywall is laminated directly to the concrete panels.
This speedy method allows workers to start on the finishes quicker and have an
entire floor ready.
The final phase of precast was being erected late in
the year on the ninth floor while the second floor had already had windows installed.
McShane plans to complete and turn over one floor at a time.
Unique
Design Elements Brink, whose firm is providing the architectural services,
said distinct architectural features include the pavilion and the entrance area
with vaulted ceilings. Hilton Garden Inns have a standard, stand-alone pavilion
lobby that is a one-story sloped roof structure that is not under the main footprint
of the hotel.
Each Hilton Garden Inn is unique to its site in terms of
style and design, while guest rooms reflect the hotel brand's standard. Guest
rooms feature carpet and painted walls, and restrooms have wall coverings and
granite vanity tops.
A hospitality center in a cabinet includes a microwave,
coffeemaker and refrigerator.
Since the hotel is under an O'Hare approach
runway, soundproofing was incorporated into the window and exterior wall design.
With
253 rooms, ample parking is essential. Since the site was not a rectangle, "we
went through a number of building iterations to maximize parking and provide a
good traffic flow," Brink said.
Also, a typical Hilton Garden Inn
has limited meeting space, but the O'Hare location needed space for banquets and
large meetings. "It required a different floor plate unique to this project,"
Brink said.
The exterior facade will be EIFS, an exterior dressing to the
structural precast to provide architectural interest. Miller said EIFS is a good
way to eliminate the architectural monotony of a multistory building without spending
twice the budget for a brick exterior.
"It's tough to get reveals
and corners, but with EIFS it's like Styrofoam with a finish coat, and we can
make it look like anything," he added.
|