Features
 Current Features
 Past Features





Feature Story - March 2005

Cogeneration Project
Thinking Inside the Box in Wisconsin


by Elaine Schmidt

There's no way to fit a behemoth of a power cogeneration plant into a newly constructed building.

advertisement

And so you put the equipment in place and build the enclosing structure around it, which is the approach taken on the $180 million West Campus Cogeneration Facility under construction on the University of Wisconsin campus in Madison.

"If you build an office building, you build the shell and then bring the furniture in," said Don Peterson, project manager for Madison Gas and Electric. "But we couldn't do that here."

Crews began driving piles and pouring foundations in fall 2003 for the system of piles and pile caps connected by concrete grade beams that the facility sits on. The power generation equipment was set in place during winter 2004, and the plant is expected to be commercial in mid to late spring.

The process of setting equipment in place and building around it is not as simple as it sounds, given the size and weight of the power-generation equipment. With just one of the steam turbines weighing at 242,000 lbs., the equipment required special handling.

The large pieces of generating equipment were brought into downtown Madison via rail and loaded onto 120-ft.-long heavy-haul trucks. To avoid traffic and pedestrian snarls, the trucks were escorted to the site by police during overnight hours while the student population was on Christmas break.

A 300-ton crane was used to lift the equipment into place.

And because of the extreme weight loads, a temporary bridge had to be installed over the existing Willow Creek Bridge on the Observatory Drive delivery route.

Has Joint Ownership

The cogeneration facility, which is jointly owned by MGE and the state of Wisconsin, will have a capacity of 150 MW of electricity, 20,000 tons of chilled water and 500,000 lb./hr. of steam. It will provide heating and cooling for the university campus and electricity for customers of MGE.

Cogeneration is the simultaneous production of electricity and thermal energy.

The residual thermal energy generated in the process of producing electrical energy, which is wasted in most electrical generation facilities, is used in the production of steam heat.

"This is not really an unusual project, although it is unusual for Wisconsin," Peterson said. "There are some of these plants in other parts of the country."

He added that rising energy prices have increased interest in cogeneration.

Despite campus conservation measures that have saved enough electricity to power 2,500 homes and ongoing MGE programs to help customers reduce electric usage, Madison's population and business growth and a societal growth in technology use are creating increased power demand. In addition, new classroom and research structures on the campus are adding to the burden.

Overcoming Logistical Nightmares

Putting a plant in the middle of such a high-use area required careful logistical planning and sensitive design considerations.

"Normally a plant like this would be built out on a site away from a town or city and have no enclosure around it," said Jim Moravec of Potter Lawson Inc. of Madison, the plant's design consultant. He said that the units are normally intended to be freestanding, but the Madison enclosure was needed to allay concerns about noise from the plant disrupting the neighborhood as well as aesthetic concerns about the plant's visual impact.

There was one other problem: Building in the middle of downtown Madison meant there was no rural-site luxury of space. The plant sits on a 4.5-acre site.

"Probably one of the most challenging parts of the project is that we don't have any sizable laydown area," Peterson said. "So we have had to take just-in-time delivery on everything. In addition we have had the logistics of getting parts not only from Wisconsin but also from Austria, France, Texas, New York, Minnesota - basically from all over the world - and getting them there at the right time.

"We have to make sure nothing comes in a day or two early - or we have to store it - or a day or two late - or we have 300 guys standing around with nothing to do."

Making It Fit

The size of the facility, in proportion to the small site and neighboring structures and streets, was a big design issue. The building's height varies from spot to spot, with the cooling towers reaching to 117 ft., or about 12 stories.

It is located at Walnut Street and Herrick Drive, beside the Walnut Street Heating Plant and across from several university greenhouses.

"We worked with the engineers to create a palate of materials to break down the mass of the building and create a more friendly scale," Moravec said. "We had little flexibility in the size of the components of the facility, which were set by engineering constraints."

He said placement of the components on the site was determined by the shadows the components would cast.

"We did extensive, three-dimensional shadow studies for different times of the day and times of the year to determine the impact on the greenhouses across the street," he said. In the end, the shadow studies may have been unnecessary because the university has decided to build new greenhouses outside the shadow-impacted areas.

Moravec added that in addition to working with the project engineers, his firm worked with the university's architects and landscape groups to create a workable structure.

"The outside of the building is all precast ribbed panels or thin-set brick set into precast," Moravec said. The choice of thin-set brick was dictated by a combination of economics, no laydown space and the difficulty of erecting scaffolding on the site for traditional brickwork.

But the biggest task is installing the enormous amount of piping required for a plant. In all, the project has 94,608 lin. ft. of piping, some of it up 72 in. in diameter. That translates into almost 18 mi. of piping.

Conservation efforts on the project were not limited to the end goal of creating a high-efficiency energy plant. With the help of WasteCap Wisconsin, 717,000 lbs. of metal and 288,000 lbs. of concrete have been recycled from the site. Some of the refuse came from a pre-existing foundation onsite and some from the routine cleaning of concrete trucks.


 

 Click here for more Features >>


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved