| A 40-Story Tower Law
Firm's Needs Rush Dearborn Street Office by
Craig Barner Law firm Sidley Austin Brown & Wood LLP needed a
lot of room fast.
And those considerable office space needs are driving
the $220 million 1 S. Dearborn St. office project in the Central Loop.
|
The firm with more
than 500 lawyers in Chicago had been looking at several properties for awhile
as it mulled whether to retain its lease in the Bank One Plaza, said Brad Soderwall,
project manager in Chicago for Houston-based Hines Interests LP, the project developer.
Sidley Austin had rented space in Bank One for 30 years.
"They were
looking out 20 years, and they needed the room to grow," he added.
Sidley
Austin had already rented space in a second building because of expansion and
was considering a lease on a third site if the Bank One Plaza was retained as
the head office.
"The only way to grow and stay in [the Bank One]
building would have meant there would have been a long period - four to five years
- of moving in the building, renovating space and moving back in," he said.
"There's a lot of time and effort involved in shifting people around in a
building."
The Dearborn Street land that previously held surface parking
and a bank was available directly across the street from the Bank One Plaza, and
Hines negotiated an option from the previous landowner to acquire the property
provided an anchor tenant could be found.
Sidley Austin wanted a floor
plate of at least 25,000 sq. ft. to accommodate future growth.
The 1 S.
Dearborn property could accommodate the large floor space if the building was
a rectangle that extended from the property line on the north along Madison Street
to the property line on the south on an alley, said Jim DeStefano, CEO of Chicago-based
architectural firm DeStefano and Partners Ltd., which was known as DeStefano Keating
Partners Ltd. while the design was under way.
At 26,500 sq. ft., the floor
plate met Sidley Austin's requirement, and the firm agreed to the project. The
land was purchased, and Sidley Austin signed a lease in May 2003 for 63 percent
of the 830,000-sq.-ft., 40-story tower.
The building will hold retail on
the first floor, support space on the second level, 160 parking spaces on levels
three through six, the offices on floors seven through 38 and penthouse space
at the top.
One other office tenant, Elite Business Centers, has been signed,
and leases are being negotiated for the three retail spaces, Soderwall said. They
likely will go to a financial institution, restaurant and store.
A
Quick Timetable Ground was broken in November 2003.
"From that
point, everyone was focused on the date the building had to be up and running,"
Soderwall said. Sidley Austin's lease in the Bank One Plaza will expire at the
end of this year.
DeStefano was commissioned in March 2003 and jumped into
the project immediately to make sure the timetable was met.
"We had
to go through all the entitlements, plan development, zoning, building permits
and have the building complete for [Sidley Austin's] move-in in September 2005,"
DeStefano said. "That's 30 months from start to finish."
Key
decisions were made to accelerate the project's progress.
A conceptual
team from Hines' Houston headquarters had already produced a set of drawings that
were ready when the project was bid, Soderwall said.
"[The conceptual
team] is up on the latest steel and drywall prices - everything you need to know
for budgets," he added.
The nearly 6,500 tons of structural steel
that frame the tower were ordered well in advance of erection time.
Steel
erection has been done all but three or four holidays since June, when the building
started to come out of the ground, said Dan Cronin, project manager with Turner
Construction Co. in Chicago, the general contractor.
About 10 days have
been lost due to rain, excessive wind or temperatures below zero degrees Fahrenheit.
"The weather has been brutal," but Sundays were used to make up the
lost time, Cronin added.
The parking was put above grade to save time.
Removing all previous obstructions below grade would have consumed a considerable
amount of time.
The foundations of several previous buildings - including
the Chicago Tribune and the famed McVicker's Theatre - and other obstructions
"covered" the site, said Bob Halvorson, president of Chicago-based Halvorson
Kaye Structural Engineers. The McVicker, which predated the Great Chicago Fire
of 1871 and was rebuilt, was on the site's east half and demolished in 1983 to
become surface parking. The Tribune left the northwest corner in the 1920s, and
the last building on the spot was a bank.
Obstructions included old caissons,
steel beams, concrete slabs, bank vault and even a coal tunnel that was plugged
and bulkheaded as part of the current project.
"We had to avoid the
old caissons, and that gets challenging when you're working off 100-year-old drawings,"
Cronin added.
Six steel-reinforced concrete transfer beams were installed
below grade, including one that is 60 ft. long. Obstructions that were not removed
are directly below some column lines, and the beams shift pressure to new caissons.
Belled
and rock caissons were installed, Halvorson said. Rock caissons were selected
for their sturdiness for areas where the soil appeared to be disturbed from previous
foundations.
Making a Visual Treat Aesthetic
elements were incorporated into the building.
The site's context was taken
into account, DeStefano said. Architect C.F. Murphy Associates' imposing 60-story
Bank One Plaza is to the west, and Skidmore, Owings & Merrill LLC's beautiful
19-story Inland Steel Building is on the south.
A 15,000-sq.-ft. plaza
sets back 1 S. Dearborn from the Bank One Plaza and allows pedestrians to see
the Inland Steel Building's north facade.
"The [1 S. Dearborn] plaza
is also an extension of a series of plazas along Dearborn Street, starting with
the federal center, the Bank One Plaza and the Daley Center Plaza," DeStefano
added. Another plaza adds open space to the street and keeps it pedestrian oriented
and people friendly.
In addition, backlit sky windows will be seen on the
One S. Dearborn's east and west facades near the tower's top. The west portal
is aligned with the main entry.
The curtain wall was extended straight
up on the east and west facades about 35 to 40 ft. above the highest occupied
floor to screen the mechanical systems. They provide the design flair that a flat
top would not.
Black granite clads the building base, and about 5,000 silver-gray
curtain-wall panels dress most of the building, Cronin said
A delay on
the fabrication of the curtain-wall panels caused some nerves to fray.
The
paint sample that had been approved looked different after it was sprayed on aluminum,
Cronin said.
"It was difficult to get a mix to match the paint sample,
more difficult than it sounds," he said. "I got way educated in metallic
paint, electrostatic painting and even sprayers."
A sample came in
that was found acceptable, but the time had to be made up.
The panels
were fabricated at plants in Florida and Connecticut, rather than at one plant.
Inside,
2-in.-thick cast glass frames two ends of the lobby, and white and gray marble
dresses the remainder.
|