| Chicago Transit Authority Planning
Puts Red Line on Right Track by Elaine
Schmidt It's never easy working on a commuter rail line in an
urban environment, particularly when a portion of it runs down the middle of a
busy interstate highway.
Such is life on the Chicago Transit Authority's Dan Ryan Red Line rehabilitation
project, a $294 million upgrade of the busiest of the CTA's seven lines. The job
began in March 2004 and is slated for completion in autumn 2006.
Work was
divided into three phases:
Phase one, which was recently completed,
involved replacing crossover track, installing a temporary signal system to support
existing and upcoming track and beginning 9.1 mi. of contact rail replacements
from Cermak Road to 95th Street.
Phase two, which began in August
2004 and will be finished in October 2005, includes constructing two substations,
upgrading two existing ones and demolishing another. Also involved are installing
a new bidirectional signal system, finishing replacement of the contact rail and
installing fiber-optic cable.
Phase three from August 2005 to autumn
2006 will involve renovating stations, including elevator installations, at 47th
and 69th streets; refurbishing platform canopies at eight stations; and bus bridgework,
including a mid-bridge canopy, at 47th Street.Coordination
Is Key The Illinois Department of Transportation is rehabilitating the Dan
Ryan Expressway at the same time, and the construction schedules between it and
the CTA project were carefully coordinated, said John McCue, Chicago-area manager
for Kiewit/Reyes Joint Venture, general contractor of the CTA project.
The
interstate and Red Line trains, which run 24 hours every day of the year, could
not be taken out of service during the project. There was no site for laydown
and staging, no logical access to the work area and only tiny windows of time
between trains in which to accomplish the work.
"We made it a little
easier by coming up with an alternate way of doing the work," McCue said.
"We built a run-around track on the shoulder of the Dan Ryan."
Susan
Plassmeyer, CTA vice president for engineering and facilities maintenance, said,
"We really had to work with the contractors and think outside the box to
come up with the plan of moving the construction zone by one lane on each side
of the tracks. It meant the difference between having an open zone or a place
with trains constantly running through it."
Getting various agencies
onboard and interstate traffic moved over to accommodate the closed shoulder was
an enormous task, but the run-arounds worked well and created an area in which
crews could work safely.
Several storage yards were set up nearby, and
as much material as possible was prefabricated in the yards so that it could be
delivered to the site and set in place immediately, McCue said.
Two small
tamping machines were brought in off the shoulder and set in place on the tracks.
Two different gradations of crushed limestone were laid as bedding before the
tracks could go in place.
"There was also a lot of coordination with
workers from Aldridge/Mass Joint Venture because they had the lion's share of
the underground electrical conduit and duct banks," McCue said. "They
had to work right along with us.
For every manhour we spent, they spent
almost an equal number."
Safety
Comes First Getting equipment and materials to the site raised one of the
project's biggest safety concerns.
"The run-arounds allowed us to
keep services reliable for our customers, but the safety implications were huge,"
Plassmeyer said.
McCue added: "We viewed traffic as a huge risk. We
had strict rules on how workers would access the site, how trucks would pull in
and out of freeway traffic and we had a no-tolerance policy."
Concrete
barriers with extensions were put in place to protect the CTA trains and workers
from interstate traffic.
"Trucks would pull onto the shoulder and
into protection even when unloading," McCue said. Our personnel could access
the site through the station."
The tracks also presented some safety
concerns, which were addressed with each person who came onto the site.
"We
do an individual, one-day training session for any worker who will be working
on our right-of-way," Plassmeyer said. The session provides certification
that must be renewed periodically.
"I have been through the certification
twice and I think my certification comes up again at the end of the year,"
Plassmeyer added. "All of the management team goes through it, as do employees
that work in the restricted zones and all CTA rail employees."
When
the last run-around was taken out of service in November, no accidents that would
affect workers had occurred.
"The Dan Ryan traffic will still be a
constant challenge" during the remainder of the project, McCue said. He added
that one of the upcoming issues will be routing passengers around construction
zones while work begins in the stations.
There will be "a unique plan
for each station," he said.
One of a Kind The
Dan Ryan Red Line rehabilitation project had no models around the country for
learning.
Plassmeyer said communication is one of the major factors in
keeping the project safe and also bringing it in on time and on budget.
"Our
organization has changed over the last few years," she added. "We are
very open with information and encourage contractors to look at the documents
and key information we have put on the Web. We include a background on the CTA
and our priorities in terms of how we look at our customers and the fact that
we want to serve them well."
|