Features
 Current Features
 Past Features





Feature Story - August 2005

Robert Kingery Expressway
$430M Redo Addresses Safety, Mobility, Road Quality

by Pamela Dittmer McKuen

The four-year Robert Kingery Expressway reconstruction is on track for an early 2007 finish.

The 50-year-old expressway, which is supporting traffic seven times what it was designed to handle, is undergoing a massive transformation.

advertisement

The $430 million project will improve public safety, traffic mobility and road conditions, and it will have a nationwide impact.

The Kingery (Interstate 80/Interstate 94), which runs east and west from the Tri-State Tollway (Interstate 294) to the Indiana border, bears portions of pavement that were laid in the 1950s. About 160,000 vehicles travel this route daily, one-quarter of them large trucks. By 2020, the average daily traffic count is projected to grow to 192,000 vehicles per day.

"They had no way to predict the weight and volume of the truck traffic this road carries now," said Mike Wiater, an Illinois Department of Transportation project engineer who is supervising the job. "This has become one of the major east-west links through the country."

Project Has 'SPUDIs'

Begun in 2003, the project stretches 6.6 mi. and includes lane additions; resurfacing; bridge replacement and enhancement; two reconstructed interchanges, known as SPUDIs, an acronym for single-point urban diamond interchanges; local access-road improvements; retaining walls to support new embankments; sound barriers; and new high-mast tower lighting and surveillance equipment.

It also includes about a mile of the Bishop Ford Freeway (I-94 north of I-80) and a mile of Illinois 394 south of I-80.

Among the specifics:

  • Kingery reconstruction and widening.

  • Reconstructed interchange at I-94/Illinois 394, where flyover ramps replace loop ramps.

  • Reconstructed Torrence Avenue (Route 83) interchange.

  • Widening I-94/IL-394 from U.S. Highway 6 (159th Street) to Thornton-Lansing Road.
    When finished, the Kingery will be widened from three to four lanes, plus additional lanes that take ramps. In places, it will be 14 or more lanes across.

    Overall, we're increasing the capacity and increasing the safety of the roadway through the design," said IDOT spokesman Mike Claffey.

    We'll be giving drivers more time to cut across lanes. That is going to make things a lot safer as well as getting drivers through there more quickly. When you cut down on accidents, you also cut down on congestion.

    The two flyovers, which connect eastbound Kingery to northbound Bishop Ford and southbound Bishop Ford to eastbound Kingery, are "a real engineering marvel and cover a lot of ground," Claffey added.

    That '70s Reconstruction

    No substantial work has been done to the highway since the 1970s, and since then, construction methods and technology have changed greatly. For example, the new roads will be built using a 12-in. aggregate subgrade, 6-in. stabilized subbase of bituminous material and 14 in. of continuously reinforced concrete.

    In comparison, "what we're taking out of the existing roadway is 8 or 9 in. of unreinforced concrete with 4 to 6 in. of asphalt overlay," Wiater said.

    Doing the work are hundreds of contractors and subcontractors, several of whom formed joint ventures. Among them is the Lorig/Lindahl/Herlihy Joint Venture, made up of Lorig Construction Co. of Des Plaines, Lindahl Bros. of Des Plaines and Herlihy Mid-Continent Co. of Romeoville.

    "It is a large project and we felt that one contractor wouldn't be able to handle it all," said Pete Element, a Herlihy project manager. "For example, when there were four jobs that were let at one time, in order to bid on all four, we set up the joint venture."

    The rough division of labor within that venture is: Lorig and Herlihy on roads and bridges and Lindahl on earthwork. But those roles are somewhat fluid, depending on the contract. And not all contracts have been awarded yet.

    Keeping Traffic Moving

    Contractors who in another setting might be competitors have become team members in this larger effort, and they must work together to keep traffic moving.

    "Any project or combination of projects of this magnitude is complicated, and scheduling is challenging," said Tim Riemersma, a senior project manager for Lorig.

    "The interface of contracts is critical so that one contract does not cause another contract to fall behind schedule."

    Lane closures - when to close which ones, when and for how long - are an exercise in extreme logistics.

    On the Bishop Ford section, which has three lanes in each direction, one lane in each direction is closed on a rotating basis while being rebuilt. The Illinois 394 section has been taken down to one lane in each direction.

    "On the Kingery itself, we're committed to not closing existing lanes of traffic, so we're maintaining three lanes east of I-94," Wiater said. "It stays the same number, but sometimes we're jogging traffic onto shoulders or making lanes narrower than before but we're maintaining three lanes."

    When other lane closures are necessary, such as in sections where bridgework is going on overhead, they are done during nonpeak hours.

    "Pretty much, any night there is going to be a lane closure somewhere along the project," Wiater added.

    Weekly coordination meetings are essential for smooth interaction between contractors and minimal disruption to the public. As needed, various contractors have and will be working nights and weekends.

    "We spend a large amount of time coordinating," Wiater said. "When contractors come in here requesting lane closures, we try to sort them out and try to combine them so we don't have conflicts."

    Next Flurry of Activity

    The project's most recent milestone was the opening of the reconstructed Thornton-Lansing Road Bridge over IL-394 in time for the Memorial Day weekend. The bridge had been closed since work began in September.

    "It was originally two lanes and now it's two lanes," Wiater said.

    The next big flurry of activity will occur late this fall when several portions of the project are finished closely together. Notable among them are the Torrence interchange and most of the roadwork, Wiater said.

    "Our goal is to get finished on time within budget and to have no accidents to our workers or the motoring public," Element said. There have been no major accidents since the project began.
  •  

     Click here for more Features >>


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved