Features
 Current Features
 Past Features





Feature Story - August 2005

Little Calumet Leg
$171 Million Job Ends 'Deep Tunnel' 1st Phase

by Craig Barner

The $171.2 million Little Calumet Leg Tunnel is expected to be complete in March, and it will mark the end of the first phase of the Chicago area's $3.1 billion Deep Tunnel project.

advertisement

The Deep Tunnel's first phase is made up of 109.4 mi. of tunnels under Cook County, and tunneling began in 1975, said Joe Sobanski, chief engineer of the Metropolitan Water Reclamation District of Greater Chicago, the city agency overseeing the project. The construction of the prototypes goes back to 1967.

Greg Hauser, project manager with the South Holland-based Jay Dee Contractors Inc./Affholder Inc. Joint Venture, the general contractor on the 7.9-mi.-long Little Calumet Leg, said, "We could do our testing and start-up before the end of the year."

Other tunnels completed in the first phase are already in service.

The second phase of the Deep Tunnel, which is formally known as the Tunnel and Reservoir Plan, will focus on the construction of three reservoirs, the Thornton and McCook basins under way, and the already complete O'Hare reservoir.

All three reservoirs are expected to be done in 2019 when the TARP project as a whole will be finished. The TARP system will offer pollution and flood-control benefits for Chicago and 51 Cook County suburbs.

Part of Calumet System

The Little Calumet Leg is part of the Calumet System, one of four systems that make up TARP.

It is composed of the reservoir in Thornton; four main tunnels including the Little Calumet Leg and auxiliaries that collect overflows from combined sewers that carry storm water and raw sewage in the same pipe; and a treatment plant at 130th Street in Chicago.

The tunnel, which runs from Lansing near the Indiana state line northwest to Dixmoor near Interstate 57, will provide pollution control and overflow abatement for all or parts of eight south suburban communities.

The Little Calumet Leg will offer relief for the Little Calumet River, which was inundated with overflows from combined sanitary and storm sewers during heavy rains. The project will prevent 2 billion gallons of combined raw sewage and 1.5 billion lbs. of polluting organic material from being discharged into the waterway each year, according to projections from the water reclamation district.

Several structures make up the Little Calumet Leg:

The system of combined sewers constructed generations ago will flush effluent to "hundreds" of vertical connecting structures, Hauser said. They will channel the sewage to soft-ground horizontal exit tunnels ranging between 36 in. and 120 in. diameter. A regulating structure with a sluice gate controls the system via radio signals or hard wiring.

When the sluice gates are up, the exit tunnels empty into the Little Calumet Leg's 10 concrete-lined drop shafts that range between 7 ft., 2 in. and 30 ft. in diameter. The sewage will plunge more than 100 ft. into a chamber - often referred to as a "boot" - that marks the starting points of the tunnel journey.

The 16-ft.-diameter, concrete-lined main tunnel is sloped so gravity can be used to flush the sewage. The tunnel ends are 160 ft. deep, and the middle is 210 ft. deep.

A connection to be built will link the Little Calumet Leg to the previously constructed Indiana Avenue Tunnel, a passageway that is about 300 ft. below ground. The 30-ft.-diameter tunnel leads to a pumping station that channels sewage to the 130th Street treatment plant.

Making the Connection

Making the connection between the Little Calumet Leg and the existing Indiana Avenue tunnels is the last major element to be done, and a plan is being reviewed.

A potential problem is that the Indiana tunnel, which is in service, could fill with effluent after the connection between it and the Little Calumet tunnel above it is opened, Hauser said. The flood could then back up into the Little Calumet tunnel.

As a result, the plan calls for diverting flow and installing a bulkhead in the Indiana Avenue tunnel that will take about 30 ft. out of service and prevent flows from pushing into the Little Calumet Leg.

"It (the bulkhead) would prevent us being flooded out every time the Deep Tunnel fills," Hauser said. "It then prevents work stoppages and prevents us from having to clean up and get back in there."

An existing drop shaft with access to the Indiana tunnel would allow equipment to be brought in. The work would include saw cutting the existing concrete lining, socketing the 10-ft.-thick concrete bulkhead to the limestone and exploding the remaining 30 ft. between the Indiana Avenue and Little Calumet Leg tunnels.

"The rock is very hard at that location," Hauser added. "The microtunnel machine won't break it up."

Major Work

Several major elements have gone into the Little Calumet Leg project, and they included the following:

  • The shafts were opened with explosive emulsion, the main tunnel was mined with a tunnel-boring machine and the near-surface tunnels were created with soft-ground TBMs.

  • The shafts and tunnel were lined with concrete, usually reinforced with rebar, and about 140,000 cu. yds. of concrete was required. In addition to the 10 drop shafts, one access shaft was made, Hauser said.

  • Concrete with strength of 10,000 to 12,000 psi was installed at the bottom of the drop shafts to resist the impact of water dropped from about 100 ft. By comparison, the other concrete used on the project for lining was usually about 4,000 psi.

  • Ninety-eight surface structures were opened with backhoes, and these allowed the connecting structures to be formed between existing sewers and the soft-ground tunnels that feed the drop shafts. The surface structures were also needed to install the regulating structures. Some sewer segments were taken out and replaced with about 6 mi. of new sewer.

  • Rock cut for the main tunnel was brought to a shaft with a continuous conveyor and removed from the ground with a vertical conveyor. Mud for the tunnels and shafts in the soft ground was removed with a train on rails, brought to a surface structure and lifted out with a crane.

    Coordination was required on the project because the partnership was a line-item joint venture, Hauser said. For example, Chesterfield, Mo.-based Affholder Inc. was responsible for the mining, and Livonia, Mich.-based Jay Dee Contractors oversaw the soft-ground work.

    "Once we started making connections, the issues of ventilation, access and power supply came up," he added. "We had to sort that out just to keep the dollars straight so both of us could do our work."

  •  

     Click here for more Features >>


     


    Sponsors

    © 2008 The McGraw-Hill Companies, Inc.
    All Rights Reserved