Children's Research Institute
Coordination and Mock-Ups Key in Lab Construction
by Elaine Schmidt The sleek exterior
of the Medical College of Wisconsin/Children's Research Institute Biomedical Research
Facility in Wauwatosa hides the complexity of the interior space where multiple
mechanical systems are being knitted together to serve labs and a vivarium.
|
The $94 million, 320,000-sq.-ft., four story project broke
ground in March 2005 and is slated for completion in December.
"The
mechanical coordination has been very critical," said Mike McNamee, senior
project executive in Milwaukee for general contractor Gilbane Building Co. of
Providence, R.I.
Lab construction is always complex, but this structure
contains a vivarium, a holding area for live research animals, which has added
significantly to the complexity of the MEP systems.
"This job is taking
layers and layers of ductwork and piping," said Ron Kwiatkowski, vice president
of design/build for the Grunau Co. of Milwaukee, the project's HVAC and plumbing
contractor and project manager on the new facility. "It surpasses anything
I have ever seen."
McNamee added that even though there is interstitial
space to work with, working with the minimum headroom requirements and the enormous
amount of ductwork has made the project difficult.
Kwiatkowski said that
the vivarium space requires stainless steel piping for an animal watering system;
complex exhaust and decontamination systems; and finely tuned systems to control
temperatures, humidity and air changes, all of which are critical to the animals
in the vivarium.
Coordination was such an essential element of getting
the systems in place that Gilbane required coordination personnel on site.
"We
insisted that the MEP and fire-protection contractors all have one onsite representative
doing coordination so that you are not running from office to office to coordinate
work," McNamee said. "They are all here onsite so you just walk next
door to get what you need."
Noting that the mechanical contractor
will usually take the lead in such coordination efforts, he said Grunau has six
or seven coordination and fabrication people onsite.
Fitting
in the Crews
With approximately 60 paired animal-holding rooms and procedure
rooms to build, and all the intricate systems to knit into the interstitial spaces,
the physical requirements of getting crews into the various spaces when they needed
to be there were also a large concern.
"We broke down the job into
pods of animal holding and procedure rooms," Kwiatkowski said. "A pod
is maybe eight or 10 rooms and we need roughly 500 hours to do a pod of maybe
60 ft. by 60 ft. So how many people can you put in there?"
The original
plan was to put four people in each pod, but they had to work on lifts to get
into the interstitial space. When it turned out that only three people would fit
comfortably in the pods, it became clear that it would take four to five weeks
to complete each pod.
Kwiatkowski added that he is planning to keep the
same personnel on all of the pod work, hoping to pick up some time once the learning
curve is out of the way.
'Critical' Mock-ups Although
mock-ups are commonly done of highly specialized spaces such as surgical suites,
laboratories and hospital patient rooms, the ones done on this project were critical.
Users of the new facility needed to try a room on for size and make any necessary
alterations before construction began.
"We did mock-ups of one animal-holding
room and one procedure room,"
Kwiatkowski said. In early December,
departments were still evaluating the elements of the rooms' design and layout,
tweaking details to make the rooms suit their needs.
Kwiatkowski said that
a few changes have been made, including moving air-distribution devices to allow
sprinkler heads to be placed in certain locations. "That's the point of building
the mock-up, to get these changes made before you start constructing the rooms,"
he said.
The structure's fourth floor is being shelled for future use as
lab space, which has required additional coordination and planning.
"We
are putting in under-floor piping for plumbing and waste systems, both sanitary
and acid waste, and stubbing it off on the fourth floor so that when that floor
is built out, we don't have to go into the third-floor ceilings and disrupt activities
down there,"
Kwiatkowski said. He added that the fourth floor is
also getting exhaust systems that anticipate possible use of that space for radiology. Busy
Campus The small site, which is bordered by existing buildings and one of
the busy medical campus' main thoroughfares, has presented its own set of construction
issues.
"We have had to coordinate deliveries closely because we have
hardly any laydown or storage area," McNamee said. "Deliveries have to be times
so that materials go straight from the trucks into the building." He said
that the presence of an existing vivarium in one of the nearby buildings has brought
up issues of noise control because sudden noises and-or vibrations can bother
the animals. "We can make some noise, just not vibrations," he added. The
vibration concerns had an impact on material handling, the demolition of an existing
parking garage and particularly in the construction of the foundation for the
new building. Drilling rather than driving piles solved the foundation issue,
and in other areas treading lightly with materials and demolitions has done the
trick. Even the process of bidding this job was out of the ordinary. "This
was not a traditional bid process," Kwiatkowski said. He said that an extensive
interview process was used, which resulted in Grunau being brought on early in
the planning stages of the project. "We said; don't just bring us on as an installer.
Make us part of the decision-making team," Kwiatkowski added. "We did a
lot of legwork up front to sell this to Gilbane and they saw that the drawings
were not going to be ready to bid on their schedule." Click
here for next Hospital Construction Feature >> |