Features
 Current Features
 Past Features





Feature Story - March 2006
Power and Energy Construction
Port Washington Update
Coal Plants Demolished; Gas Blocks Under Way

by Elaine Schmidt

Wisconsin's $7 billion Power the Future initiative is changing the face of the lakefront of Port Washington, Wis.

advertisement

Between 1932 and 2004, the Port Washington Power Plant received about 18,000 tons of eastern coal during each month of the shipping season. On June 19, 2004, the plant took its last delivery. Its two enormous smokestacks served as beacons for mariners on Lake Michigan for more than 70 years.

But advances in power generation have rendered the old plant obsolete, and it is being replaced by two 545-MW, natural-gas-fueled generating units on the same site.

The first unit went into service on July 16 and the second one is under construction.

"This project consists of two combined-cycle units," said Doug Weegin, project manager for Milwaukee-based We Energies, the primary utility subsidiary of holding company Wisconsin Energy Crop., also in Milwaukee. The second unit will consist of two combustion turbine generators, two heat-recovery steam generators and a steam turbine generator.

The overall cost of the Port Washington project is estimated to cost about $650 million. The balance of Power the Future funding is being spent at the Oak Creek power plant south of Milwaukee and transmission upgrades.

In addition to the environmental benefits of switching to natural gas, the upgrades are necessary because of the potential for a power shortage in the state.

Deconstructing a Power Block

The old must go out before the new comes in. The last coal units of the 70-year-old plant have been retired and were being demolished through January. The demolition process is more a matter of deconstruction, rather than traditional demolition.

The first step was removal of any salvageable equipment, followed by the removal of oil and other substances used in operations, Weegin said.

With the old plant out of the way, early construction work on the natural gas units is beginning.

Power Déjà vu

"This [second gas] unit is going to replicate the first one," said Chuck Taylor, project manager for in the Princeton, N.J., office of Boise-based Washington Group International, the company providing engineering, procurement and construction services. Replication stands to be a tremendous advantage for the project.

"We plan on being a lot more efficient on the second phase of the project because of lessons learned on the first phase," Taylor added. "We put a formal program in place to learn from that project."

The program entailed extensive interviews with people who worked on the construction of the first gas unit.

"We looked at what we could do better and what we had done right, so that we could do those things again," Taylor said. The program identified upwards of 200 items that were cost savings and should be continued, or that should be changed in order to keep costs down.

One such item that will be continued on the second unit is the practice of receiving cable precut and bundled by the suppliers. The cable links one piece of equipment to another.

"On the first unit the vendor precut and bundled the cable, instead of us having it delivered bulk and having to cut it in the field," Taylor said. "There was some risk in having it precut, because if there were any design changes, it might not have fit and we could have lost money."

Continuity in the workforce will also be a plus on the second unit.

"We have made a concerted effort to retain or bring back people who were involved in the first unit," Taylor said.

Another advantage is the fact that there will be a working model close at hand to answer any questions that might arise in the field.

"We have the best model in the world right next door," Taylor said. "We Energies is working with us so that we can go next door and look at it while it's running if we need to."

Site Concerns

But having the working model right next door poses some logistical problems as well.
The second unit is wedged between the newly constructed first unit, a stretch of Lake Michigan shoreline and a part of the old coal plant that was preserved for historical reasons.

There is just one access point to the site by road, which will present delivery concerns throughout construction. But the proximity to the lake will end up being an advantage.

"We will use the lake to bring in the boilers," Taylor said. "They will bring the ship right up into the harbor and offload the boilers with a large crane."

He said that it would take at least a week to set up the crane needed for those lifts, and that off-loading the huge boilers would be "something to see."

The other big challenge is getting as much work done before the 2006-07 winter sets in.

"Our goal is to focus on underground piping and electrical installation first and to get all the foundations in by September and October of this year," Taylor said. "That leads us to be able to set the major equipment and about 50 percent of the structural steel in fall and early winter of '06."

The plant is scheduled to go online on May 2, 2008.


Click here for next Power and Energy Construction Feature >>

 

 

 Click here for more Features >>


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved