Microbial Sciences Building
Complexities Mount on Wisconsin Lab Project
by Elaine Schmidt Installing the
systems required in modern laboratory buildings are frequently a complex issue.
|
The intricacies of the $120 million Microbial Sciences Building
at the University of Wisconsin at Madison go beyond exhaust hoods.
For
instance, the six-story structure had to be shoehorned around the campus' historic
Hiram Smith Hall and built over a working electrical substation.
The facility
had to meet post-Sept. 11 security requirements.
And, an open environment
was required so ideas could be exchanged and people could interact in the academic
programs the building will house. These include bacteriology, medical microbiology
and food microbiology.
Because of these programs, the building will include
a crystal growth chamber, vivarium and research kitchen.
The 330,000-gross-sq.-ft.
structure broke ground in December 2004 and is scheduled for completion in May
2007. Portions of the structure should be ready for lab installation by spring.
A
seventh-story mechanicals penthouse will top the facility, and four underground
parking levels will contain about 150 spaces.
The university has big hopes
for the building. It is intended to keep the school competitive and attract top-drawer
faculty and students capable of pulling in research grants.
Underground Surprises
Peter Heaslett, engineer and project manager with
the university, said site issues included an area of poor soils and accommodating
the structures and activities on and around the area.
"We encountered
some soft soils to the north of the existing substation and had to redesign some
footings and drill some extra caissons on that side," added Jerry Wheaton,
project manager for lead contractor C.D. Smith Construction of Fond du Lac.
Spread
footings had been planned for the affected area of the structure, but the unplanned
redesign called for drilled caissons, which were being used in other areas of
the building that required deep footings.
Heaslett said the redesign and
addition of caissons cost time and money because the soil in that small area was
"moving, with a lot of water coming through from a sand layer." Crews
are still working to make up the time.
An electrical substation, which
provides power to approximately 25 percent of the campus, was located in E.B.
Fred Hall, the building that stood on the site when the project began. The substation
had to remain functional throughout the demolition of E.B. Fred, as well as throughout
the construction of the new building.
The upper levels of E.B. Fred were
torn off first and then the rest of the structure demolished to leave the substation
intact and running. A roofing membrane was put over the substation and enclosed
in a mostly underground bunker.
All went well until the roofing membrane
started leaking.
"A little water got into the substation and caused
a small failure of one of the electrical components," Heaslett said. Redundancy
in the substation kept the power on, while crews quickly repaired the membrane.
Historic Hiram Building
The construction team also
worried about the historic Hiram Smith building during excavation and foundation
work.
With the new structure wrapping around two sides of Hiram Smith and
an old crack in its foundation, the historic structure had to be monitored closely
to be sure there was no settlement.
Heaslett said the old structure "held
up very well," but there was a lateral water break.
"Water started
seeping through the shoring and weakening the soil," he added.
Scott
Kramer, partner with Plunkett Raysich Architects in Milwaukee, said there was
a potential for collapse, "but the contractor was onsite and dealt with it
quickly."
Heaslett said crews had to "shore up the shoring"
with dirt at first and then with soil nails.
Additional site issues include
a $25 million utility project going across part of the Microbial Science Building's
construction fence.
"A central campus utility project is bringing
a whole host of utilities through that part of the campus, so streets are torn
up all around us," Heaslett said.
The amount of construction going
on in a limited area of the busy campus has resulted in traffic backups. Demands
on Design
The microbial building had to accommodate some conflicting demands
on its design.
"Security is a very big deal since Sept. 11,"
Kramer said. "All security regulations for laboratory facilities have changed
and keep changing on a monthly basis. It's hard to keep up with the regulations."
He
has worked closely with the university's security department to meet regulations,
but the faculty had different desires for the building.
"I think it's
disappointing for researchers who are coming from an era of no security and students
just walking into their labs, that there are all these barriers to keep the students
away," Kramer said.
Working with faculty members >> from all
three departments, Plunkett Raysich architects came up with a series of neighborhoods
that will define and unite the three departments that will share the building.
They also designed several atria that will provide neutral space where people
can interact outside the labs.
The labs themselves are designed for flexibility
and can be expanded when a project needs more space and/or staff.
"One
of the other challenges we had is that this was one of the first major buildings
in the state designed under the new IBC (International Building Code) adopted
in 2002," Kramer said. "Trying to deal with atrium space and the code
was untested territory."
He added about a dozen firms consulted on
the project to handle some of the building's specific requirements such as smoke
control systems for the atria.
Thermodynamic modeling was used to show
how the atria would react in the event of a fire. The computerized models showed
such things as fire at different temperatures, the smoke spread the fire would
create, how quickly the smoke cleared and how long it took the average person
to evacuate.
Working on the university campus has presented an unforeseen
advantage in the way of two interactive Web cams on the site. The cameras are
accessible and moveable from offsite computers via the Web.
Web cams that
the university's Heaslett has used in the past have been static, but the interactive
cameras have occasionally allowed him to take a look at things on the site and
answer questions without leaving his desk.
Heaslett added that another
advantage on this project, which was bid by the university to multiple prime contractors
rather than to a general and subs, has been a high level of cooperation between
the among contractors on the site.
Click
here for next University Construction Feature >> |