CTA Upgrades Transit
System Retools Telecom, Rail Line by
Craig Barner Improving telecommunications systemwide and service quality
on the Brown Line rail on the Northwest Side are resulting in major construction
projects on the Chicago Transit Authority system.
In September, a $31 million project was started to improve
the CTA's telecommunications.
Previous telecom upgrades have been completed.
Meantime,
the long-awaited, $530 million enhancement of the Brown Line system started in
February.
In addition to these, other CTA projects are nearing completion
or recently finished (see the accompanying Sidebarstory.)
Transit Telecom Improving
communication technology quality and security are key goals of the telecommunications
work, which is formally known as the CTA Systemwide Communications Upgrade Project.
Ray
Clark, senior project manager of Libertyville-based prime contractor Aldridge
Electric Inc., said the project includes the installation of fiber-optic cable
at some CTA rail stations and operations facilities and along some tracks.
About
300,000 to 400,000 lin. ft. of the cable--called optical carrier 192 line--is
being installed to carry voice, video and data.
The cable's capacity is
so vast that it could carry 9.95 thousand million bits of information per second.
"It
would fill up a computer with information in a second," said Tom McLinden,
vice president of business development for Aldridge. The CTA has multiple servers
to handle the data.
Robyn Ziegler, a spokeswoman for the CTA, said uses
include the enhanced video monitoring of stations by security cameras, upgraded
audio for announcements over the public-address system and improved transmission
of voice and data.
The project is affecting rails on the city's South Side
(Orange and Green lines), West Side (Blue Line Congress, Green Line Lake) and
North Side (Purple, Red, Yellow and O'Hare Blue).
The cable will be buried
about 3.5 to 4 ft. in the ground, supported along elevated structures or put in
existing subway tunnels.
"I would say the majority of it is in the
ground," Clark said. "People think of the CTA is elevated, but a lot
of it is at grade."
Scheduling and nimbleness have been used to minimize
the project's impact on commuters.
For example, train service shuts on
some lines, such as the Purple and Yellow, during the wee hours of the morning,
and crews can get work done during those periods.
Crews can also lay cable
while only a single track on a line is used in each direction to move trains.
Trains would be switched to the track that normally carries trains in the opposite
direction while the trains in the opposite direction wait.
The cable crews
will also piggyback on other crews that are performing maintenance.
For
instance, the Purple Line in Evanston was shut over a weekend in the winter so
an old bridge could be replaced, and cable was installed during the same weekend.
"We
went in with 45 to 50 people, and we put all our underground cable in over one
weekend," Clark said.
To ensure safety, construction employees are
required to take a one-day course covering working in a rail environment, and
no one is allowed onsite without his or her certification. Aldridge also conducted
in-house safety programs.
A major issue for the team is that the CTA's
existing telecommunications services, such as telephone and public address, be
maintained during construction.
Dual and temporary systems were installed
to maintain constant communication, Clark said.
"We'll set up temporary
communications, give all the phones temporary extensions, hook in to the new phones
while still maintaining the old and cross them over one at a time," he added.
Previous
telecom work included an $11 million project completed in 2003 for the installation
of cable on the Blue Line from O'Hare International Airport to Jackson Boulevard
in the Loop.
Also, telecommunication cable and other electrical systems
were installed for $90 million on the Red Line from the 98th Street yard to 22nd
Street as part of an overall $250 million project on the South Side. The installation
of electrical systems was completed in December, but the overall project is expected
to finish in September.
The Brown Out As
the telecom project continues, stations on the Brown Line are being upgraded in
part because of increased ridership.
Since 1979, the number of riders has
increased about 83 percent on the century-old line, according to the CTA, and
the 18-station system averages more than 66,000 passengers each weekday.
Most
stations accommodate six-car trains--other than the Merchandise Mart, Fullerton
and Belmont stops, which can handle eight cars--and a key goal is to extend 15
stations for the longer trains to improve passenger flow, said Sheila Gregory,
general manager of public affairs for the CTA. Because additional power is required
to operate eight-car trains, substations are being upgraded as part of the project.
The
rebuilt stations will provide better amenities than are currently available, including
wider entrances and exists, additional turnstiles and access for those with disabilities.
Also included will be things customers are only partly aware of--tactile
edging, windbreaks, canopies and improved lighting.
A major concern is
the limited space for work and the nearness of businesses and residences to the
line.
"Much of the work that requires street closures or obstructions
so materials and equipment can be staged will be done during nighttime working
hours or condensed into a 54-hour weekend," Gregory said.
Fifteen
stations will temporarily close at some point between now and 2009, when the entire
project will finish, on a staggered schedule for weeks or more so work can be
done.
For instance, the Kedzie and Rockwell stations closed on Feb. 20
for six months.
Work includes demolishing the station and platform, installing
platform precast foundations, steel framing, electrical, wood decking with tactile
strip and equipment, signage and barricades.
Some weekend closures of stations
are planned. Only the Belmont, Fullerton and Western stations will maintain regular
schedules during the project.
Chicago-based FHP Tectonics is the general
contractor for three bid packages: Belmont/Fullerton,Chicago/Armitage/
Sedgwick
and Kimball/Kedzie/Francisco/Rockwell/Western. The bid documents have been issued
for the Irving Park/
Damen/Addison and Montrose stations, but the Wellington/Diversey/Paulina/ Southport
and Brown Line telecommunication packages have not yet been bid. Sidebar
: Red Line Nearly Done; New Route Coming Two other major projects
are nearing completion or done on the Chicago Transit Authority:
The
$283 million upgrade of the Dan Ryan Red Line on the city's South Side is expected
to be complete in September, said Robyn Ziegler, a spokeswoman for the CTA.
The
project includes replacing crossover track, constructing and upgrading substations,
installing a bi-directional signal system and fiber-optic cable, renovating stations,
refurbishing platform canopies and other elements.
A $5.2 million project
involved the refurbishment of the Paulina Connector, a north-south track on Paulina
Street on the West Side between Congress Parkway and Lake Street that has recently
only been used to move trains from one line to another. The track has not been
used for commuter service for decades.
But in June, trains will use the
connector again for commuter service between the downtown Lake Street elevated
tracks to the northeast and the former Blue Line 54th/Cermak elevated track to
the southwest. (The CTA sponsored a contest and solicited ideas from Chicago-area
schoolchildren for a new name, and the Pink Line was the winner.)
The Paulina
Connector is the first element of the visionary Circle Line plan, a second loop
of commuter lines conceived to serve an area about six times greater than the
existing Loop, Ziegler said. The agency is seeking federal funding for the Circle
Line.
-C.B.
Click
here for next Mass Transit Construction Feature>> |