| Speeding Ahead Illinois
Tollway Moves Quickly To Relieve Traffic Congestion
by Paula Widholm Stuck in traffic
is not where Chicago motorists want to be.
The Illinois State Toll Highway
Authority has responded and is into its second year of an aggressive $5.3 billion
Congestion-Relief Program. The 10-year capital program is front-loaded, with most
construction occurring in the first five years, generating $20 billion in economic
benefits and creating 252,000 jobs.
The program is designed to reduce travel times by:
Rebuilding/reconstructing 90 percent of the system.
Widening/adding
lanes to nearly half the system - 117 mi.
Converting 20 mainline toll
plazas to the barrier-free, nonstop, transponder-based Open Road Tolling system
by this year.
Extending Interstate 355 in western DuPage County 12.5
mi. south to Interstate 80.
In all, the Congestion-Relief Program is estimated
to save a minimum of 15 minutes from the average trip of 30 to 40 mi., according
to Jan Kemp, assistant press secretary of the Illinois Tollway.
The following
is a snapshot of three major Tollway projects under way - Open Road Tolling Conversion,
the I-355 South Extension and the rebuilding and widening of the South Tri-State
(Interstate 294).
Open Road Tolling Since
embarking on a systemwide conversion to Open Road Tolling in January 2005, motorists
can now zoom through ORT at nine mainline toll plazas.
The 11 remaining
mainline plazas are slated to be complete by the end of this year. ORT separates
transponder-based I-PASS users who pay electronically while traveling at normal
highway speed from cash payers who pull off to the right in toll plazas.
"Going
from an old barrier system of stop, pay and go to a completely open-road tolling
system has been done before, but we're doing it systemwide on 20 plazas all at
once, and that's a first (nationwide)," said J.D. Stokes, deputy program
manager for ORT implementation.
Jeff Dailey, chief engineer for the Illinois
Tollway, calls the rapid conversion "short-term pain for long-term gain.
We're giving the traveling public a shorter amount of pain on the freeway for
an easier way in the future."
"The more expeditiously you can
convert from older system to ORT the better," Stokes said. "Dragging
it out doesn't work well. The public can say 'this construction is something we
didn't like, but we appreciate that you're getting it done.'"
To get
the project on the fast track, design and construction phases overlapped.
"We
went out to bid when the design stage was about 80 percent complete," Stokes
said. "There was enough to build, but we didn't have final answers on specifications
for technology and functionality."
This approach, as well as working
through the winter, shaved 12 to 18 months off the schedule.
Stokes said
work zones were created for traffic control, and "we'd wait several days
to see how the traffic flowed before actually tearing out the pavement."
For
example, at one toll conversion, there was a 10-mi. backup after creating work
zones, but the backup dropped to 3 mi. after workers made specialized signs, painted
thicker, wider striping to help motorists know where lanes were going and gave
up some workspace to add an additional cash lane.
"The real challenge
has been maintaining the schedule within budget," Stokes said.
"Getting
it within budget involved value engineering and partnering with the contractor.
We're marrying technology, new buildings and roadway work."
After
ripping out the old cash booths and roadwork, the contractor is installing a continuous
reinforced concrete roadway. Expansion joints are cut into the pavement for the
expanding and contracting weather.
Vehicle detection systems are in the
pavement and the toll collection equipment is tucked into tubes on the canopy
overhead.
"We're the first to do ORT systemwide and statewide,"
Dailey said. "We have the highest I-PASS rates in the nation, with more than
75 percent total average during peak hours."
I-355
South Extension As of midsummer, the project to lengthen Interstate 355
by 12.5 mi. to I-80 is moving at freeway speed, and construction of the 1.3-mi.,
six-lane Des Plaines Valley Bridge, one of the project's highlights, has begun.
The
bridge is being built over the environmentally protected Des Plaines River Valley,
and environmental concerns halted the project 10 years ago.
As part of
a resolution between the Tollway, the U.S. Fish and Wildlife Service and the U.S.
Army Corps of Engineers, the habitats in the Des Plaines River Valley will be
protected and 35 acres of wetlands will be created.
Specifically, contractors
are being careful not to disturb the habitat of the Hines Emerald Dragonfly.
"To
protect their habitat, we took precautions not to impact their larva states where
they burrow into the ground," said Tom Valaitis, senior project manager of
Woodridge-based V3 Cos., the construction manager. "Their gestation period
is five years long, so we can't excavate in the areas where there are burrowed
holes.
"Some fenced off areas are literally underneath the bridge.
The bridge was also designed to make sure it was tall enough so the flight of
the dragonfly would be below the bottom of the bridge."
The bridge
is a precast, post-tensioned, spliced-bulb-T, concrete-beam design.
"It's
construction that's more typical in the Southwest and West Coast," Valaitis
said.
"Bridge beams are fabricated offsite, trucked to the site and
erected on piers and temporary shoring towers."
The beams are spliced
together and steel strands are slipped through the beams and post-tensioned to
make the beam continuous from pier to pier. The temporary shoring towers are removed
before the deck is cast and additional post-tensioning is done on the beams before
the bridge is opened to traffic.
The bridge rises about 80 ft. to 100 ft.
above the Des Plaines River Valley and has 34 piers with four columns per pier.
The 35 spans range in length from 145 to 275 ft. The $125 million bridge contract
is constructed using the design-build method, which saved $8 million.
The
$730 million project consists of 16 construction contracts. The extension includes
interchanges at I-55 and I-80. Four other interchanges will service local roads.
The new tollway is slated to open by the end of 2007.
The designs from
the mid-90s were updated for new standards and analyzed for cost efficiencies.
"Originally, the project had to spoil a couple million cu. yds. of dirt,"
the Tollway's Dailey said.
In the redesign, 9 million cu. yds. of earth
was moved and used to build up the approach to bridges, raise the profile of the
roadway about 10 ft. in one area and create berms for landscaping and sound control.
Higher
anticipated traffic volumes also called for updating intersections to provide
more vehicle capacity.
The new tollway is a 12-in.-thick, jointed-concrete
pavement designed for 20 years. For 3 mi. it's a six-lane road, and for 9 mi.
it's a four-lane road.
However, the entire strip can be easily expanded
to six lanes by striping out the shoulders and putting in an asphalt shoulder.
Dailey estimated the project is using 176,000 cu. yds. of concrete.
South
Tri-State Reconstruction Eight mi. of the 17.5-mi. reconstruction of the
South Tri-State Tollway is under way. A new lane is being added in each direction.
To
complete $275 million worth of work in a 20-month time period, the project kept
running through the winter, said Michael Hannemann, vice president of Chicago-based
McDonough Associates, the construction manager. "Major components - bridge
decks and pavements - were performed in January," he added.
This first
phase is slated to be complete by fall 2007.
"This portion of the
Tollway has a tremendous amount of truck traffic, some of the highest counts in
the country," Hannemann said.
He said maintaining three lanes of traffic
required an extreme amount of crossover lanes and counterflow lanes.
The
project also required a lot of rock removal because it crossed and was adjacent
to the Thornton Quarry. "A lot of delicate blasting techniques were used
by the contractor to remove rock to leave it in a stable state," Hannemann
said.
For the project, 45,000 cu. yds. of concrete was used for the pavement,
shoulders and ramps. The quarry bridge is being reconstructed 300 ft. above the
quarry floor.
"It's a 30-year continuous-reinforced concrete pavement
suitable for heavy truck traffic volume," Dailey said. "It should be
60 or 70 years until we have to reconstruct it again."
The Tollway
opted for the design-build method for the noise walls, retaining walls and bridges.
"We used a different project delivery method to expedite it and get it out
on the street," Dailey said.
Phase two, which is 12 mi. of reconstruction
of I-294 from I-80 to 95th Street, will include widening to four lanes in each
direction. It is scheduled to start this year with a 2009 completion. However,
costs have come in $100 million over estimates, which will require redesigning,
repackaging and value engineering, Dailey said.
"Over the last three
years, there's been a 30 percent increase in material costs," Dailey added.
"Also, there's a saturation of the market. Contractors aren't as hungry for
work, with the Dan Ryan reconstruction and the O'Hare Modernization and our own
work."
The Tollway has $1.7 billion committed to spend over the next
year and a half, with $1.4 billion of that just in construction work.
"We're
scheduled to encumber another $1 billion in engineering and construction work,"
Daley said. "By the end of this year, about $2.4 billion will be encumbered
out of the $5.3 billion Congestion-Relief Program."
Click
here for Next Feature >>
|