|
Trump Update
Tower Making Its Climb
Toward Chicago's Skyline
by Craig Barner
A rarity for a construction project is happening just west
of Michigan Avenue in Chicago.
Pedestrians are watching, not scurrying past, the building
activity at 401 N. Wabash Ave. on the North Bank of the Chicago
River.
On a recent day, visitors from Europe were standing on the
opposite bank and asking questions. "I wonder how tall
it is going to be?" one asked.
|
Office workers and other passersby slowed their pace to watch.
Tourists on a boat trip were pointing.
The object of their interest was the $850 million Trump International
Tower & Hotel, which is making its climb toward Chicago's
skyline.
The importance of the parallelogram-shaped tower goes beyond
its lofty price tag.
When the 1,360-ft.-tall tower is completed in April 2009,
it will be the second tallest in Chicago and nationwide after
the 1,450-ft.-tall Sears Tower. The Trump, which will be 92
stories, will be the tallest building constructed in North
America since the 108-story Sears was completed in 1974.
Trump will be the 14th tallest in the world assuming each
of the eight towers under way in Asia and the Middle East
taller than it are built according to plan, according to Geri
Kery, operations manager of the Council on Tall Buildings
and Urban Habitat, an international association headquartered
in Chicago.
In mid-August, Trump had reached the 14th floor where a health
club will be located, said Tim Snyder, construction manager
in Chicago for the New York-based The Trump Organization,
the developer. The 1,000-car parking garage, which is on levels
3 to 12, is done, except for a helix-shaped ramp.
Tere Proctor, director of sales in Chicago for The Trump Organization,
said 76 percent of the tower's 758 units-472 condominiums
and 286 hotel-condominiums-are sold.
The condominium-hotel is on floors 16 through 27, with units
ranging between 526 and 2,245 sq. ft. and prices between $850,000
and $3.3 million. The condominiums will be located on levels
29 through 89 and range from 580-sq.-ft. studios to 14,000-sq.-ft.
penthouses. Prices range between $563,000 and $9 million.
Building amenities include the 60,000-sq.-ft. health club,
restaurants, retail, ballroom and meeting rooms. A 1.2-acre
park will surround the base, and the park's three tiers will
face a walkway on the river.
Recently, Midwest Construction visited the site where details
emerged about some of the above-ground construction issues
and structural engineering.
Concrete Details
Concrete is an important project element early on in part
because it forms the building's structural support.
Snyder said that about 150 of the 200 people on the job in
mid-August were employees of Chicago-based James McHugh Construction
Co., the concrete contractor.
Numerous details keep the crews busy.
For instance, the floor-slab thickness of the completed garage
is 14 in., said Brett Szabo, senior project manager of concrete
for McHugh. The depth will be 9 in. for a typical residential
floor and 18 to 20 in. for a transfer level.
Supporting the garage are 30 6-ft.-diameter concrete columns,
and 47 thinner concrete columns will support the residential
portion.
Transfer levels are needed because setbacks at levels 16,
29 and 51 require column pressure to be transferred from some
lines to adjacent lines, said Bob Sinn, associate partner
with Chicago-based Skidmore, Owings & Merrill LLC, the
architect and structural engineer. The transfer levels, which
also hold mechanical equipment, are on 15, 28, 50 and 90.
Usually, mammoth outrigger beams that are typically 17-ft.,
6-in. deep and 5-ft., 6-in. wide are on each transfer level.
They provide lateral stability against the city's winds.
"The outriggers don't occur on the typical floors like
parking and residential," Sinn said. "They're in
the mechanical floors so they're out of the way."
The outrigger beams extend from the perimeter columns to the
197-ft.-long, 49-ft.-wide central core, also concrete. The
core, which is composed of four I-shaped walls and one C-shaped
wall, will hold the elevators and stairs.
More important, it provides additional lateral stability.
Since the building started coming out of the ground, approximately
60,000 cu. yds. of concrete have been poured.
"A typical 30- to 40-story condominium in Chicago runs
about 20,000 to 25,000 cu. yds.," Szabo added. "So
(the Trump) is about two typical condos, but we're only up
to the (Trump's) 14th floor."
A seven-day pour cycle was the norm early in the project,
but in mid-August, a large amount of time was expected for
the 15th to be formed, because it is a transfer level.
"A couple months are needed to get them (transfer floors)
built," Szabo added.
About 300 trucks full of concrete are received every week
because the material is so important to the project.
Mixing a Mat
About 20 different concrete mixes are being used on the project.
The care taken with the 10-ft.-thick mat slab shows how important
concrete recipes are.
The building has four below-grade levels, and the 200-ft.-long,
60-ft.-wide slab, which is below Lower Level Four, was poured
over a 22-hour period between Sept. 30 and Oct. 1, 2005. The
slab serves as a juncture between the below-ground caissons
and the above-grade core.
The mix was composed of self-consolidating concrete that features
specialty additives and low-water content, Snyder said.
Key benefits include strength and less labor during the pour.
Because of the chemistry, the material is poured without having
to be vibrated. And, as the name implies, the concrete has
a high slump rate.
"That concrete is so sticky and dry because it has so
little water and so much cement and other additives that within
15 to 20 minutes of striking it off, it goes hard," Snyder
said. The pour was done with only six laborers, but with a
conventional concrete, three times the amount would have been
needed.
More important, the concrete's temperature and strength were
carefully monitored to ensure strength and solidity.
The concrete was poured on a day not greater than 80 degrees
F to try to control the concrete's heat gain, and 36 temperature
probes had been attached to rebar cages inserted in the mat
for monitoring.
"We didn't want it to reach temperatures internally greater
than 150 degrees F," Snyder added.
Readings were taken every minute for each of the 36 points
and downloaded onto a computer so a curve could be plotted.
Within 24 hours, the temperatures spiked at 150 degrees because
of hydration but receded over weeks. After 10 days, the concrete
averaged around 120 to 125 degrees.
Similarly, six full-depth cores were made in the mat to measure
the concrete's strength. The concrete was poured at 10,000
psi. It measured at 7,000 psi after seven days due to heat
gain but averaged 13,000 psi after cooling.
"It was a 56-day design mix, but we were reaching design
strength in less than 28 days," Snyder added.
SIDEBAR 1
A Stiff Trump
The stiffness of the concrete was specified on the Trump
International Tower & Hotel in Chicago.
Bob Sinn, associate partner of Chicago-based Skidmore, Owings
& Merrill LLC, the architect and structural engineer,
said the "modulus of elasticity" was specified for
the columns, walls and other concrete elements on the project.
"It's pretty unheard of," he added. "Most concrete
suppliers know about strength tests of concrete. Modulus of
elasticity is a different animal for them."
Ensuring the stiffness is important so that the eventual residents
do not perceive sway in the building after it is completed.
Other elements to ensure stability include a concrete core
and the placement of mammoth outrigger beams on some floors.
Because the modulus of elasticity was specified, mechanical
means to counteract a tall building's natural sway, like auxiliary
dampening devices, were avoided.
"We're using the stiffness of concrete to control the
motion instead," Sinn added.
The building is expected to reach the 20th to 22nd floor by
the end of the year, said Tim Snyder, construction manager
in Chicago for the New York-based The Trump Organization,
the developer. Topping-out is expected in June 2008 and completion
in April 2009.
SIDEBAR 2
A Way Safe Project
Several elements were incorporated in the Trump International
Tower & Hotel in Chicago to ensure safety.
The owner, 401 N. Wabash Venture LLC, is paying for insurance
with an owner's controlled insurance policy.
Two full-time safety managers staff the project, one with
the owner and one with the construction manager on the project,
the Chicago office of New York-based Bovis Lend Lease Inc.
Tim Snyder, construction manager in Chicago of the New York-based
The Trump Organization, the developer, said their responsibilities
include performing safety audits, monitoring construction
and training laborers.
Fundamentals are stressed. For instance, controlled access
zones permit only laborers trained in fall protection to work
near the slab edges of floors.
"There is a monitor there-a nonworking individual who
monitors the activity in the controlled access zone-to make
sure somebody isn't backing up close to the edge," Snyder
said.
A safety office is located onsite, and full-time paramedics
are onsite every day.
Click
here for Next Feature >>
|