|
Marquette Interchange Update
Two Years Down,
Two to Go in Milwaukee
by Elaine Schmidt
Anyone who has driven into downtown Milwaukee in the past
two years is aware that there is a construction project under
way on the Marquette Interchange, which connects interstates
94 and 43.
But they may not be aware of the enormity of the project.
|
"The Marquette Interchange project has been defined by
people with a national background in these kind of projects
as the most ambitious urban interchange construction ever
attempted, in terms of maintaining two lanes of traffic in
four directions and doing so while reconstructing the entire
interchange," said George Poirier, oversight manager
in the Madison, Wis., office of the Federal Highway Administration
The $810 million project began in 2004 and is slated for completion
in 2008.
It replaces one-lane system ramps connecting I-94 and I-43
with two-lane ramps, switches existing left-hand access ramps
with right-hand ramps, replaces existing pavement and roadbeds
with a perpetual-pavement recipe of asphalt over gravel and
replaces aging sewer lines that serve the roads.
Overall, 5.5 mi. will be rebuilt. A stone layer of 18 in.
of crush stone, 6 in. of 1.25-minus stone and 4 in. of open-graded
stone comprise the redone mainline. The asphalt on top will
be 13 in. thick.
The project includes the closure and reconstruction of 13
on/off ramps, with five more to be closed and replaced by
new ramps. Nine bridges will be demolished and eight of them
replaced.
Work includes the completed Clybourn Street Project adjacent
to I-94. The second phase, which is still under way and is
the project's longest stretch, is I-43 from Wells Street to
North Avenue. Other phases under way include the west leg,
south leg and the core contract.
Marquette has been overused since the day it went into service
in 1968. It has handled double the expected traffic, reaching
300,000 cars a day in the early 2000s.
Ahead of Schedule
Speaking at the two-year point in
the four-year project, Brian Manthey, communication director
on the Marquette Interchange project for the Wisconsin Department
of Transportation, said that two mild winters have allowed
certain segments of the project to get as much as five months
ahead of schedule.
"We are on track to hit certain milestones about five
months earlier than planned," he said. That means that
certain segments of roadway will open to the public ahead
of schedule, during the first week in January 2008 rather
than the first week in May.
Bumping those openings ahead of schedule means that crews
will be able start the next round of demolition and substructure
work ahead of schedule.
"Demo work, pile driving and placing footings can all
be done in winter weather," Manthey said. He added that
under the original schedule, that work would have taken much
of summer 2007 to complete.
But getting the demolition and substructure work completed
over the winter was based on the coming winter being "normal
or mild," he added.
Hitting a few milestones ahead of schedule does not necessarily
mean that the project will be completed ahead of schedule,
but, "It takes out a great deal of the risk that it will
go later than planned," Manthey said.
In addition to the mild winter, several factors helped keep
the enormous project on schedule and pushed portions of it
ahead of schedule.
Manthey gave teamwork credit to Marquette Constructors, the
company formed by Edward Kraemer & Sons Inc. of Plain,
Wis.; Lunda Construction Co. of Black River Falls, Wis.; and
Zenith Tech Inc. of Waukesha, Wis.
"WisDOT wondered if this would work," Manthey added.
"Could three companies that are normally fierce competitors
coming together and work as a team?"
After two years, the answer is yes.
For Tom Hessling, construction team leader for the Chicago-based
CTE Engineers, one of the key elements in the project's success
thus far has been the ability and willingness of individuals
and firms livings up to commitments they made.
"Marquette Constructors had secured in-state fabricators
and gotten commitments made by a lot of different industries,"
Hessling said. He cited PDM Bridge in Wausau and Eau Claire
and Spancrete Inc. in Green Bay among those fabricators, saying
that both companies were fabricating around the clock to meet
demands and had trucks performing a constant delivery process,
circling from plant to site and only stopping long enough
to load.
"For me it was playing a hand of poker and hoping we
had been dealt the right cards - and we had," he said.
"Everybody who had a hand in this project has been really
excited and energized about it. They have been really sympathetic
to what we are doing and have gone the extra mile to help
out."
Cost, Scheduling Tools Help
The use of new tools, such as Earned Value Analysis, a methodology
for tracking costs and scheduling and projecting that data
into the future, has also had a positive impact.
Dave Scott, the Marquette Interchange coordinator for the
Federal Highways Administration's Madison office, said, "WisDOT
put a full range of skill sets on the project full time so
that they have all the resources they need right there."
The full-time people included projects schedulers, engineers,
cost trackers and soils people.
Keeping the public apprised of changes and closures and providing
alternate route suggestions have been key elements in keeping
downtown open for business throughout construction.
Manthey cited recent figures indicating increased ticket sales
for several downtown-based organizations, including the Milwaukee
Bucks and the Milwaukee Symphony Orchestra, as one indication
that WisDOT's communication plans are working and keeping
downtown open for business.
Some Headaches
Worker and traffic safety records have been good on the project
thus far. Manthey credited the fact that no workers have suffered
major injuries with WisDOT's safety program and vigorous self-policing
by the various contractors. He added that keeping the public
apprised of construction progress and responding quickly to
traffic and signage issues have prevented any major traffic
accidents on the busy site.
But the project has not been without a few headaches.
Manthey pointed to the collapse of old, brick sewer inlet
during heavy September rains.
"Ironically, we were going to close that area in a few
weeks anyway," he said.
The collapse, which would likely have occurred without the
construction going on in the area, occurred on a Sunday night,
flooding the Brown Street area of I-43 to car rooftops.
He said that some of the construction workers and engineers,
"got out there, grabbed a backhoe and were able to guess
where to dig to open it up," he said. The moment it was
opened up, water began pouring down into the sewer. Crews
covered the hole with a plate and some asphalt, and all was
well by the time Monday morning traffic hit the area.
Manthey said that much of the work slated for the next two
years deals with structures for elevated portions of roadway,
including tying two new ramps into the existing I-94 "high-rise"
bridge that spans the river valley on the south side of downtown.
"Coordinating the building of all of the system ramps,
the spaghetti bowl as it's called, and keeping traffic moving
will be more complex than what we have been working on to
this point," Manthey said. "But everybody is confident
in the plan."
Click
here for Next Feature >>
|