|
Monolithic Church Complex
Crops Up in Birmingham by Candy McCampbell
The $16.5 million activity center project at Faith Chapel
Christian Center in Birmingham, Ala., is not like most other
church expansion projects.
This one requires the construction of six monolithic concrete
domes totaling 120,000 sq. ft. across 16 of the church's 140
acres. The additions are being built next to the church's
existing 87,000-sq.-ft. domed sanctuary, the largest single
dome in the country at the time of its construction three
years ago.
The new domes-three are 144 ft. and three are 164 ft. in diameter-will
house a children's play area, entertainment areas complete
with a pair of NBA-size basketball courts, a 12-lane bowling
alley and commercial kitchen and connecting lobby.
How to Build Domes
To build the domed roofs, construction manager Monumental
Contracting Services of Birmingham, Ala., and contractor South
Industries of Menan, Idaho, install a roofing membrane-called
an Airform-on top of the wall forms.
Polyurethane foam is then applied to the interior surface
of the membrane, which then acts as a base for attaching the
roof's reinforcing steel.
Work is under way on the fourth dome, which will be inflated
this month, said William Robertson, president of Monumental
Contracting Service.
"You have to have constant air pressure to keep it inflated,
and you have to inflate it 24 hours a day," Robertson
said. "The contractor has to monitor the intake and outflow
to keep the pressure even."
To access the air structure, the contractor must enter through
a double door airlock, which keeps the air-pressure inside
at a constant level. Steel reinforcing rebar is attached to
the foam using a specially engineered layout of hoop and vertical
steel rebar.
Shotcrete-a special spray mix of concrete-is applied in 1-in.
layers over the mats of reinforcing steel. Some areas of the
dome can be as much as 24 in. thick, he said. Drying time
varies, depending on the circumference of the dome, but usually
two layers can be applied each day.
Robertson said the side walls for each dome-built in the same
way with layers of shotcrete and steel mesh-range from 10
to 14 ft. high, depending on the building's use.
The monolithic layered-construction method required about
575 cu. yds. of concrete per dome, or 3,450 cu. yds. for the
project. Each dome also requires about 55 tons of steel, or
about 330 tons for the project.
Construction of a dome takes about two months from start to
finish,
Robertson said. The last one should be completed by June,
when interior finish work will start. The entire project is
scheduled for completion in December.
LPDJ Architects LLC of Salt Lake City is the architect for
the center.
"The uniqueness about this client is they are an all-cash
deal," Robertson said.
"There is no debt service."
Click here for next Feature Story >>
|