|
Indianapolis Public Schools
$832 Million Program
Moves into New Phase
by Pamela Dittmer McKuen
The mammoth capital improvement program of the Indianapolis
Public Schools is a little ahead and a little behind, but
pretty much on track. When finished, it will have taken more
than a decade and about $832 million, and all 79 schools will
see new academic life.
|
"We're in an overlap of phases," said Debra Kunce
of Indianapolis-based Schmidt Associates Inc., an architectural
firm serving as the project's program manager. "We're
on the downside of phase one and the upside of phase two."
IPS serves 38,000 pupils in kindergarten through high school.
Phase one, which began in 2002, created 28 advanced science
labs in 23 middle and high schools to help prepare students
for new state testing standards. The five traditional high
schools, which serve grades nine through 12, also were renovated
to include such enhancements as infrastructure upgrades, accessibility
for those with disabilities, air conditioning and telecommunications
systems.
At the elementary level, six new schools were built. Two of
them, Wendell Phillips and James Russell Lowell, were closed
20-some years ago when desegregation reigned. They were sold
and reacquired by the district, although by then the buildings
had fallen into extreme disrepair. The schools were replaced
with new ones and reopened last fall.
Despite all the construction, classes went on as usual, said
Steve Young, the school district's chief of facilities management.
"In the high schools, students stayed in buildings and
moved around as we did different portions of the building,"
he said. "In the elementary schools, each of them was
built on the same site so the students stayed in the existing
building while we built next to it. Then they moved in and
we tore down the existing building."
Not disrupting students took some logistical science. Most
of the elementary schools stood on two- or three-acre sites
in developed neighborhoods with barely enough room for the
building, a small parking lot and maybe a playground. At five
of the sites, the district acquired small amounts of adjacent
land. Even so, quarters were tight.
The solutions depended on the site. In some cases, the construction
teams did remote staging or brought in materials only as needed.
In others, they leased nearby land or bartered services in
exchange for parking.
$250 Million First Phase
The cost of the first phase, $250 million, was funded by a
bond initiative supported by property taxes. The rough breakdown
for construction costs was $25 million per high school, $11
million per elementary school and $300,000 per science lab.
As the work wound down, various economies enabled the district
to air-condition one elementary and one middle school ahead
of schedule.
"That's money that won't have to be bonded in the future,"
Kunce said.
Phase two began in early 2006 with a budget of $200 million
coming from a second bond initiative. Six middle schools are
seeing renovation and infrastructure improvements, and most
are being transformed for new or expanded uses.
For example, Thomas Carr Howe Academy and George Washington
Community School will enroll students in Seventh through 12th
grades.
Crispus Attucks is converting to a medical magnet school for
students in sixth through 12th grades who wish to enter the
healing professions. Shortridge Middle School is converting
to a government and law magnet school for grades six through
12.
The second phase also renovates and expands three historic
elementary schools: Christian Park, George W. Julian and Joseph
J. Bingham. Christian Park is on the National Register of
Historic Places.
"That one had an addition in the 1950s and we are tearing
it off," Young said.
"It wasn't built very well. It's not as stable as the
original building, which was built in the early 1900s."
The new additions are designed to complement the historic
nature of the existing buildings, he added.
One more project is at Arsenal Technical High School, where
the music and cafeteria building and a gymnasium will undergo
renovation. The classroom buildings were renovated during
phase one.
The construction for phase two, scheduled for completion in
2009, will cost about $20 million per middle school, $11 million
per elementary school and $6 million for Arsenal Tech. Contracts
have begun to be awarded.
"Because we have such a large school district and so
many schools, we have attempted to create a sequence that
impacts the most students initially and the greatest geographic
area," Young said. "For example, the high schools
impact the whole district. Now we're focusing on the second
level of widespread distribution, the middle schools, but
we are not able to do all the middle schools at one time."
Throughout the school system, environmental and accessibility
improvements are major issues, Young said.
"When we started, very few of our buildings were air-conditioned,"
he said.
"A lot of our buildings were inaccessible. They didn't
have elevators. They had four or five levels with only stairs
to get up and down. The older elementary schools are three-level
buildings and the only restrooms were in the basement.
That's the way they built them."
Increasing Phase Count
Since its inception in the late 1990s, the original two-phase
program has undergone a few modifications.
Among the reasons: a change in school board leadership, strong
and growing sensitivities to property tax impacts and the
establishment of 17 charter schools that contributed to a
loss of a couple thousand pupils.
As a result, the program was broken into three phases and
the timeline for completion was extended. The budget for phase
3, which will renovate the remaining 55 or so elementary schools,
has yet to be determined. A fourth phase is possible.
"I expect that with delays and additional considerations,
we'll go a little longer than a 10-year plan," Kunce said.
"These decisions have to be very deliberate."
Maximizing the precious tax dollars requires constant scrutiny,
Young said.
Among the fiscal management techniques the district employs
are the set-aside of contingency funds and two-tier bid requests
listing base and alternate items.
In a few instances, when bids exceeded the budget, the design
team was sent back to the drawing board. And Young's extensive
maintenance staff gets tapped for ideas and suggestions.
"We've been very aggressive in establishing budgets and requiring
our professionals to meet those budgets," he said. "We feel
it is absolutely essential that we not have to ask the community
to pay for more than what we committed to get things done."
Providing construction management on the various projects
are multiple firms and joint ventures. One is Indianapolis-based
Shiel Sexton Construction Co., which filled this role at two
schools during the first phase and is doing the same for Shortridge.
A unique aspect of the program is the advanced age of many
of the schools, said senior project manager Randy Waren.
"It's a special challenge to know exactly what existing conditions
are and how they are going to be impacted with new construction,"
he said. "It takes a lot of preplanning and going through
attics and basements and crawl spaces to see what's there.
There are always surprises."
At Brookside Elementary School, one of the new construction
projects, a couple of large painted murals were saved and
reinstalled in the new building, said Don Jungst, vice president
of construction manager Smoot Construction in Indianapolis.
"They came in and cut the wall out with the mural and stabilized
it to be transported," he added. "It was put in a frame and
we put it in a pocket in a new wall. IPS did an extensive
amount of salvaging of unique items and integrating them into
new structures."
For phase two, Smoot is charged with managing the construction
of Julian.
Despite the work that is yet to be done, rewards are all ready
evident. "We know we're making an impact," Kunce said. "We're
seeing some scores go up. We're seeing people fixing up their
houses adjacent to the school. We're seeing communities come
back together and more fully utilize their schools-one neighborhood
at a time."
Click here for next Feature Story >>
|