| Gold Medal of Construction
Olympic Effort Needed
To Erect Mega-Projects
by Craig Barner
If Chicago lands the Olympics in 2016, the city will see
a level of construction worthy of a Greco-Roman wrestler.
With this issue, Midwest Construction presents its own effort
of grappling with a enormous task: the Top-20
Completions of 2007.
Top Projects Completed 1
MetroLink Extension
Cost: $669 Million
MetroLink's extension project involved 8 mi of new light-rail
line that connects the inner-ring suburbs of St. Louis.
Dozens of utilities immediately in the track's path were relocated.
This translated into more than 900 utility relocations that
support water, sewer, electricity, gas and cable television.
The corridor along Forest Park Parkway-which the extension
follows for just less than half of its path-is the oldest
utility corridor in St. Louis. In some places, the aging utilities
were so brittle that the use of heavy excavation equipment
would likely have severely damaged them.
Hydrovac excavation-removing surrounding earth by spraying
it with water, then removing it with a vacuum-was used in
sensitive areas to avoid severing critical lines.
Other work included installation of track, overhead catenary
systems and signals. The last portion of the project comprised
stations and landscaping.
Connecting Communities
The MetroLink Cross County project is the latest of several
projects that have incrementally extended the 38-mi. MetroLink
line serving the St. Louis metropolitan region.
The extension connects to the existing line at Forest Park
and travels in a dog-leg configuration through seven communities:
the city of St. Louis, University City, Clayton, Richmond
Heights, Brentwood, Maplewood and Shrewsbury.
The extension follows Forest Park Parkway west until it reaches
Clayton, then it takes over the former Terminal Railroad freight
line where it travels south.
The original 17-mi. line from Lambert-St. Louis International
Airport to East St. Louis, Ill., was built in 1993. A 17-mi.
addition from East St. Louis to Belleville, Ill., was constructed
in 2001, and there was a 4-mi. extension from Belleville to
Scott Air Force Base in 2003.
The current extension is the first in Missouri since the original
system was built.
Some work was done near exiting MetroLink line. The start
of the extension ties in at Forest Park, where crews have
had to work around train arrivals every few minutes while
performing partial demolition of the existing station, building
retaining walls for new tracks and constructing a new center
platform at the existing station.
Another challenging section of the project is the "Facilities
2" contract: 1.32 miles of cut-and-cover tunnel construction
and two below-grade stations. For tunnel construction, crews
shored up the sides of the route and then excavated to 45
ft below grade, removing approximately 350,000 cu yds of material.
Top Projects Completed 2
New Prentice Women's Hospital
Cost: $550 Million
The 950,000-sq-ft New Prentice Women's Hospital was completed
at Superior Street and Fairbanks Avenue in the Streeterville
campus of Northwestern Memorial Hospital in Chicago.
The 257-bed facility will accommodate 13,500 births annually
and include 32 labor and delivery rooms; four cesarean section
rooms; and seven prep/holding/recovery rooms.
There are 134 obstetric beds for postpartum and antepartum
care; 144 normal newborn bassinets; 86 special care nursery
beds; 36-bed women's care unit with 28 beds for gynecology/gynecological
oncology patients; surgical unit with 10 operating rooms;
and 30 prep/holding/recovery rooms.
New Prentice houses the largest comprehensive breast center
in the Midwest, including breast imaging, breast surgery evaluation
and radiation oncology.
Inpatient and outpatient diagnostic services will include
ultrasound, genetic counseling, chest X-ray, CT scan, MRI,
fluoroscopy and phlebotomy.
Artwork representative of woman and their diversity hangs
throughout the facility.
A Building with a Curve
Prentice features a number of design elements to give it a
feminine architectural style.
The building's east facade offers a gentle curve that leads
to a glass-and-metal corner at Chicago and Fairbanks avenues,
providing views of a park and Lake Michigan. The building
also has a translucent glass top.
A three-story glass atrium allows prospective patients to
see inside. The public base is for evaluation and triage,
so prospective patients do not go to elevators.
After evaluation, expectant mothers have a discrete entrance
to patient elevators that lead to labor delivery rooms set
close to recovery/postpartum rooms.
In addition to designing for the patient, the family-oriented,
three-story base considers the public. The second-floor cafeteria
is visible from the first floor so visitors do not get lost.
Patient rooms line the perimeter of the upper floors. Outpatient
areas are spa-like with the colors, textures, lighting and
fabrics that are used for a relaxed, noninstitutional setting.
Departments and services are placed close to each other to
improve patient flow.
More than 60 user groups from Northwestern staff met repeatedly
throughout design to provide assistance.
Many medical systems were ordered at the last possible moment
to ensure the latest technology.
Top Projects Completed 3
Metra New Start Upgrades
Cost: $508 Million
Three of the Metra commuter rail system's 12 lines recently
saw improvements.
These comprised the 52-mi North Central Service to Antioch,
the 36-mi Union Pacific West to Geneva and the 33-mi SouthWest
Service to Orland Park. Each terminates in the Loop.
Federal Transit Administration New Start funding was approved
in 2001. State and local sources also provided financial support.
Increasing demand and the expanding boundaries of the Chicago
metropolitan were the project drivers.
As part of the project, the SWS was extended about 12 mi to
Manhattan, and the UPW was lengthened 8 mi to Elburn. The
NCS did not get longer but received additional track.
The SWS expanded from 16 to 30 weekday trains, and the NCS
grew from 10 to 22 weekday trains. The buys UPW did not grow
beyond the existing 59 weekday trains.
Ridership is expected to surge in part because of the improved
service. The SWS is projected to go from 6,843 weekday boardings
to 18,500 boardings by 2008, and the NCS is expected to increase
from 4,500 boardings to 12,200 boardings.
The projects touched areas that are experiencing significant
population growth and economic development and are projected
to keep growing well.
Additional Track, New Stations
Each service runs on track shared with freight trains. Second
or third track that is parallel to existing lines was added
for improved efficiency.
The UPW received third track between Geneva and Elburn. Thirteen
mi of second track was added to the NCS and 3 mi to the SWS
lines. Some freight trains exceed a mile in length, and the
additional capacity allowed for a passing line.
The projects should relieve parking and pedestrian congestion
at the stations. Stations or platforms were added, expanded
or upgraded.
The railroads themselves-Canadian National/Wisconsin Central;
Norfolk Southern, Union Pacific-did the mainline trackwork.
This included setting ties, limestone ballast and subballast
and rails.
On the UPW extension, for instance, the laborious trackwork
included setting an estimated 63,000 concrete ties.
The intricate trackwork process was carefully orchestrated
to ensure that it was done properly. This included laying
multiple layers ballast, laying track and aligning the track.
Top Projects Completed 4
Interstate 74 Reconstruction
Cost: $499 Million
The reconstruction of Interstate 74 in Peoria is reportedly
the largest road reconstruction project ever in downstate
Illinois.
Despite its name, I-74 precedes the interstate system. It
was originally constructed to improve traffic flow between
Peoria and sister city East Peoria and represents an important
economic lifeline in Central Illinois.
I-74's age and increasing traffic were the key factors driving
the redo.
About 30,000 vehicles traveled the highway every day when
it was originally opened in 1959, and the figure had doubled
due to Peoria's growth.
The pavement had become worn from the heavy use, and motorists'
safety was increasingly at risk. In fact, 13 of 22 areas of
I-74 exceed the statewide average accident rate in a state
with a metropolis like Chicago
About 45 lane mi were removed and replaced between Peoria
and East Peoria, twin cities across the Illinois River from
each other. The new interstate lanes are composed of 11.5
in. of continuously reinforced concrete.
Bridges Also Redone
The massive scope of the project required 42 bridges that
cross the expressway to be rebuilt and in some cases widened
due to an increase in motorists using alternate routes to
avoid the mainline construction area.
The Murray Baker Bridge, which carries I-74 traffic across
the Illinois River, was shut for improvements for six months.
Traffic was shifted to the south, where the Bob Michel Bridge
and two others are located, or to the north to use the McClugage
Bridge.
A substantial amount of utility relocations-sewer, telecommunications,
electrical, natural gas, water-were done.
Perhaps the most complicated was the installation of a 78-in.
storm sewer.
Water collection went up because the amount of road space
increased. The lane number in each direction on the interstate
rose from two to three, and some city streets and bridges
were widened.
The sewer installation resulted in the relocation of hundreds
of individual utility lines.
Related project elements included the widening of Sterling
Avenue on the project's north from four to six lanes because
it feeds two shopping malls. Spalding Avenue, an important
downtown street near OSF Saint Francis Medical Center, was
also widened.
Other upgrades include limestone facing on abutments to make
them more pleasant looking than their predecessors.
Top Projects Completed 5
Robert Kingery Expressway
Cost: $430 Million
The 50-year-old Robert Kingery Expressway was handling traffic
seven times greater that what it was designed to handle.
As a result, the thoroughfare (Interstate 80/Interstate 94)
was reconstructed to improve safety and traffic mobility.
The Kingery runs east-west between the Tri-State Tollway (Interstate
294) and the Indiana line. About 160,000 vehicles travel the
route daily, one-quarter of them large trucks. By 2020, the
average daily traffic count is projected to grow to about
192,000 vehicles a day.
Almost 7 mi. Rebuilt
The project stretched 6.6 mi and included lane additions,
resurfacing, bridge replacement and enhancement; two reconstructed
interchanges, known as SPUDIs, an acronym for single-point
urban diamond interchanges; local-access-road improvements;
retaining walls; sound barriers; and new high-mast towers
lighting and surveillance equipment.
Some work was done on the Bishop Ford Freeway (I-94 north
of I-80) and a mile of Illinois 394 south of I-80.
Among the specifics:
Kingery reconstruction and widening.
Reconstructed interchange at I-94/Illinois 394 where flyover
ramps replace loop ramps.
Reconstructed Torrence Avenue (Route 83) interchange.
Widening I-94/IL-394 from U.S. Highay 6 (159th Street) to
Thornton-Lansing Road.
Two flyovers to connect east-bound Kingery to the northbound
Bishop
Ford and the southbound Bishop Ford to eastbound Kingery.
The completed Kingery will be widened from three to four lanes,
plus additional lanes that take ramps.
The reconstructed road will feature 12-in. aggregate subgrade,
6-in. stabilized subbase of bituminous material and 14 in.
of continuously reinforced concrete.
In comparison, the previous surface was 8 or 9 in. of unreinforced
concrete with 4 to 6 in. of asphalt overlay.
Weekly coordination meetings were held for smooth interaction
among the contractors and minimal disruption to the public.
Some contractors worked nights and weekends to keep construction
moving forward.
Top Projects Completed 6
Bayshore Town Center
Cost: $300 Million
Bayshore Mall in Glendale, Wis., was originally built in
1958 and reconstructed in the 1970s.
The new Bayshore Town Center emerged from construction in
time for the 2006 Christmas season as a retail/dining/entertainment
destination.
The indoor mall ruled the shopping world until the mid-1990s,
when New Urbanist thinking led to open-air malls called "lifestyle
centers" or "town centers." With these centers,
developers strive to create the feel and function of a small-town
Main Street.
Part of this latest trend in mall construction is the idea
of a mall being a destination for more than just shopping.
Development Has 'Streets'
Bayshore has large buildings, including a reworked incarnation
of the existing mall and several parking structures that surround
several open-air "town" streets and a "town
square," complete with a fountain.
Issues included a tight, 47-acre site, 22-month schedule,
proximity to a residential neighborhood and the fact that
the mall had to remain open through construction.
Keeping the mall open was an enormous task. On the south end
of the existing structure, half of the building had to be
demolished while half of it remained operational. A corridor
in the center of the old structure was the dividing line between
what stayed and what went.
Crews turned that former corridor into a tunnel-like, interior
walkway that protected shoppers and connected the south-end
stores to the rest of the mall.
At night, after patrons and employees were gone from the mall,
construction crews would remove the floor of the tunnel walkway
and pour new foundations and perform utility work. All equipment
had to be cleared from the space and the floor set back in
place in time for the mall to open for business the following
morning.
A residential neighborhood immediately east of the Bayshore
site presented additional concerns.
Hunzinger went with a quiet, auger-cast system in which an
auger drills down to the required depth. Concrete is then
poured through the auger, the auger is removed and the concrete
settles down into place.
In addition to keeping parking areas open for mall patrons,
foot traffic was also an issue.
Shoppers would try and get by fencing systems to walk through
the construction and get to another part of the mall. A lot
of security was needed to protect the public from itself.
Top Projects Completed 7
Dan Ryan Red Line Reconstruction
Cost: $294 Million
It was not easy working on a commuter rail line in an urban
environment, particularly when a portion of it is running
down the middle of a busy interstate highway.
Such was life on the Chicago Transit Authority's Dan Ryan
Red Line rehabilitation project. Work was divided into three
phases:
Phase one involved replacing crossover track, installing
a temporary signal system to support existing and upcoming
track and beginning 9.1 mi. of contact rail replacements from
Cermak Road to 95th Street.
Phase two included constructing two substations, upgrading
two existing ones and demolishing another. Also involved are
installing a new bidirectional signal system, finishing replacement
of the contact rail and installing fiber-optic cable.
Phase three involved renovating stations, including elevator
installations, at 47th and 69th streets; refurbishing platform
canopies at eight stations; and bus bridgework, including
a mid-bridge canopy, at 47th Street.
Coordination Was Key
The Illinois Department of Transportation rehabilitated the
Dan Ryan Expressway at the same time, and the construction
schedules between it and the CTA project were carefully coordinated.
The interstate and Red Line trains, which run 24 hours every
day of the year, could not be taken out of service during
the project. There was no site for laydown and staging, no
logical access to the work area and only tiny windows of time
between trains in which to accomplish the work. Run-around
track was built on the shoulder of the Dan Ryan.
Getting various agencies onboard and interstate traffic moved
over to accommodate the closed shoulder was an enormous task,
but the run-arounds created an area in which crews could work
safely.
Several storage yards were set up nearby, and as much material
as possible was prefabricated in the yards so that it could
be delivered to the site and set in place immediately, McCue
said.
Two small tamping machines were brought in off the shoulder
and set in place on the tracks. Two different gradations of
crushed limestone were laid as bedding before the tracks could
go in place.
Getting equipment and materials to the site raised one of
the project's biggest safety concerns.
Concrete barriers with extensions were put in place to protect
the CTA trains and workers from interstate traffic.
Top Projects Completed 8
French Lick Springs Resort &
Casino
Cost: $282 Million
Indiana's French Lick is returning to its former grandeur
as a celebrated resort area but with modern flair.
The project encompasses the hotel, golf courses and golf school,
restaurants, spa and convention center. The project also includes
sister West Baden Springs Resort nearby.
The hotels, which were built at the turn of the 20th Century,
were restored and renovated. Other work includes building
an 80,000-sq-ft casino; 110,000-sq-ft convention center; and
800-car parking garage. The Donald Ross golf course, which
dates to 1920, was also restored to its original design.
The history of Southern Indiana's Orange County dates to the
mid-1800s when a couple of enterprising physicians capitalized
on nearby mineral springs whose waters were said to have medicinal
benefits. Over the decades, hotels were built with increasing
luxury, and they drew prominent patrons from around the country,
such as President Franklin Roosevelt.
By the 1970s, financial difficulties, ownership changes and
deterioration had set in. In 2005 Blue Sky Casino LLC took
over as the new, energized owner.
It is a joint venture of Lauth Resorts & Casino LLC, an
affiliate of Lauth Group Inc. in Indianapolis, and Orange
County Holdings Inc., formed by Cook Group Inc. in Bloomington,
Ind.
A Beaux Arts Beauty
The 440-room French Lick Hotel, designed in the ornate architectural
style, had not seen serious attention inside or out since
the late 1970s. The plans include replacing bathrooms, enlarging
guest rooms and adding a $2 million sprinkler system.
Time-consuming and detailed restoration of the public areas
included replicating plaster ornamentation and restoring aged
gold leaf. Tens of thousands of tiny floor tiles are being
chiseled out and replaced.
A surprise was discovered after the immense lobby columns
were stripped of 10 layers of paint. Underneath was scagliola,
a thin plaster made from dyed silk and polished to a marble-like
sheen. Only a handful of people know how to repair it.
The hotel suspended operations during construction, but its
employees, who number in the hundreds, were paid wages and
benefits until being called back.
About $4.5 million was spent to sustain them.
The new buildings complement the existing architecture and
also integrate the resources of the area.
Design elements such as belt courses and radius windows are
adaptations from the hotel. Native Indiana limestone trims
and precast concrete panels are a tribute to local industry:
Limestone from nearby Benford, Ind., is known throughout the
world.
Top Projects Completed 9
Schaumburg Convention Center and
Hotel
Cost: $249 Million
A negative site was turned into a positive setting for the
Schaumburg Convention Center and Hotel.
The facility in the suburb 25 mi northwest of Chicago is located
in a low-lying floodplain northeast of the juncture of Meacham
Road and the Northwest Tollway. Three major facilities will
comprise the complex: the convention center on the site's
south, the Marriott Renaissance Hotel in the center and a
performing arts center-an element not yet started-on the north.
Excavated ponds were incorporated into the design plans, and
they provide water retention and some drainage.
More important, the design aim of the ponds and accompanying
landscaping in front of the hotel is to give visitors the
impression that they are entering a resort.
Amplifying the theme of a grand entry is an extraordinary
aesthetic element in circular shape called the "embrace."
The bottom of the 550-ft-diameter feature is 15 ft. above
ground and is made of two column-supported, 8-ft-tall, 2-ft-deep
arcs, one north of the hotel entrance and the other south
of the entrance. Between the arcs are entry and exit roads,
in addition to the ponds and landscaping. The embrace allows
the water and prairie-style, landscaped site to become an
outdoor room.
Another key aesthetic element is an elliptical porte-cochere
shelter that will protect guests and vehicles from the elements.
The porte-cochere and embrace are circular, while the convention
center and hotel are rectangular, thus providing contrast
and composition.
The high style continues inside the Marriott hotel, where
guests will encounter upscale touches and finishes. For instance,
the lobby houses a pair of curved grand staircases that provide
a dramatic first impression.
Seeking Village Funds
The complex about five minutes' drive north of the Woodfield
Shopping Center is being built partly to help increase village
revenue and drive business.
Schaumburg does not levee property taxes but rather relies
on assessments against hotels, sales, food and similar things
to fund operations.
The 350,000-sq-ft convention center holds a 100,000-sq-ft
exhibit hall that can be divided into separate halls.
The convention center connects to the 15-story, 500-room hotel.
The complex has a 1,700-space surface parking lot.
Top Projects Completed 10
Lower Meramec River Wastewater Treatment
Plant
Cost: $230 Million
When the Metropolitan St. Louis Sewer District was formed
in 1954, it was charged with the responsibility of consolidating
more than 70 formerly independent wastewater districts.
More than 50 years later, the MSSD is continuing those efforts
with the Lower Meramec River Wastewater Treatment Plant southwest
of St. Louis.
The plant is replacing two existing open lagoon treatment
plants, the Meramec and Baumgartner facilities. The plant
will divert treated water, which currently flows to the Meramec,
into the Mississippi. The project required miles of tunnels
through rock and wetlands.
Being a Good Neighbor
The area around the plant has seen tremendous development
in recent years, creating thousands of new neighbors. Concerns
about odor affecting nearby residents, including pupils at
a grade school, led to a design that would keep sewage underground
or otherwise enclosed on the plant site, rather than running
through open channels.
Noise and traffic were also concerns. During preparation of
the 203-acre site, crews created a new access entrance to
help alleviate strain on local roads.
The site lies within a floodplain, so crews brought in about
850,000 cu yd of engineered structural fill to elevate the
footprint of the new plant. An additional 370,000 cu yd of
fill was added to another area where future expansions will
take place.
The main components of the plant include a three-story process
building, a secondary treatment building, two primary clarifiers,
two trickling filters and two secondary clarifiers. The main
process plant is designed in brick and glass with a steel
structure.
Sewage will flow through the 90-ft-diameter primary clarifiers
to the 150-ft-diameter secondary clarifiers and the covered
120-ft-diameter trickling filters.
The flow moves through a series of pipes with diameters up
to 64 in. via an underground gallery that connects the structures.
The process plant itself is set on pilings that run an average
of 90 ft into rock.
A 1.5-mi outfall sewer was built, which routes a 78-in.-diameter
reinforced concrete pipe to the Mississippi. The sewer route,
which reached as deep as 20 ft and went through wetlands,
was open-cut, backfilled and restored. Mitigation included
nearly 11 acres of wetlands planting.
Discharge is into the Mississippi because the Meramec is one
of the most pristine and well-used rivers in Missouri.
Top Projects Completed 11
Sherman Plaza
Cost: $193 Million
The 28-story Sherman Plaza residential and retail development
has added height to the skyline in north suburban Evanston.
The tower would have been the city's tallest, but early design
changes took it just inches below the Chase Building. As it
stands, it is the city's tallest residential building.
About a decade ago, city planners saw that the 30-year-old,
600-space public garage on the Sherman Avenue site needed
work. Engineers said it should be torn down and rebuilt, leading
to question about what else should be built, and Sherman Plaza
was cobbled together. It is believed to be the highest-dollar
mixed-use project in Evanston history.
Anchoring the project is the condominium tower, The Residences
at Sherman Plaza, which houses 253 lofts, penthouses and condominiums.
The units range in size from 900 sq. ft. to 4,000 sq. ft.
The tower connects to 152,000 sq. ft. of retail space on two
levels and a 1,585-space public parking garage, creating an
L-shaped footprint. All together, Sherman Plaza encompasses
nearly a city block.
Construction of Sherman Plaza began in December 2004. There
was no basement to excavate, but the caissons required drilling
about 70 ft.
Underground were numerous and costly obstructions due to poor
ground conditions and deep foundations of previous buildings
on the site. "Potholing," which is making trial
bores, helped locate obstructions near grade, but for deeper
ones, crews had to widen their holes or try harder to get
through.
In one case, the rock was impenetrable despite numerous attempts.
Finally the decision was made to drill two additional caissons
about 10 ft. on either side of the rock and to lay a bridge
beam across them so that the column support could be put in
as planned.
Seeking Human Scale
The enormity of the project, from a design standpoint, is
visually scaled to human size.
Although basically a single, poured-in-place concrete building,
the various areas of use stand at differing heights and sport
differing facades. The first six floors and the entire retail
center are clad in brick. The three penthouse floors, 23 through
25, are tiered like a wedding cake and ribboned with high-performance,
floor-to-ceiling windows. They are crowned with a three-story
mechanical penthouse. The silo-like garage elevator is encased
in glass.
Rooftop gardens on the third, fifth and seventh floors are
decked with trees, shrubs, grass and flowers and provide nearly
half an acre of outdoor respite.
Top Projects Completed 12
Community Hospital North
Cost: $170 Million
Community Hospital North in Indianapolis completed an 850,000-sq-ft
building expansion and renovation project to meet growing
demand for services.
The project involved three new structures-a six-story patient
tower, six-story parking garage and five-story medical office
building. It also included some renovations of existing buildings.
Over the last four years at Community Hospital North, admissions
increased by nearly 7%. Emergency visits have grown by almost
9.5%, and births have risen by more than 4%. The hospital
averages more than 1,000 daily patients.
The project more than doubled the size of the hospital, adding
282 private patient rooms, with space for 48 more rooms in
the future. Linked to the hospital will be the professional
office building and the 1,000-space parking garage. The structures
are connected in a circular fashion.
The exterior has a circular feel, rather than the more typical
square appearance of hospitals. The skin will also provide
a high-tech look because of the geometry of the forms inside
and out and materials that include curtain wall and metal.
Some of exterior is brick to match the existing hospital.
The parking garage, which is also curved, is covered with
stainless steel.
Most o the new structure was built on top of an existing surface
parking lot, which was taken out before construction started
in third-quarter 2004.
The Art of Design
The project's centerpiece is the new patient tower. A large,
sunlit gallery serves as the main entrance, and the entrance
is referred to as a gallery because it is designed to look
and feel like an art gallery. Patients and visitors can peruse
art, and the hospital has commissioned 30 original art pieces,
both paintings and sculpture, from local artists.
Inside the main tower are two atria with skylights that are
40-ft square.
Also inside the main building is a set of elevators that provide
access to the upper levels, which house 48 private medical/surgical
suites and three floors of new space for mothers and babies.
Upper floors include 60 labor, delivery, recovery and postpartum
rooms, allowing new mothers to remain in one place throughout
their stay.
The main building features private registration and billing
areas. Every surgical patient has a private room before surgery
and for recovery. Advanced technology was included throughout,
including wireless Internet, electronic medical records, digital
imaging and computers near patients' rooms for staff members.
Top Projects Completed 13
Winnebago County Justice Center
Cost: $150 Million
The existing jail and justice facilities in Rockford, Ill.,
were aging and overcrowded, so work started on the replacement
Winnebago County Justice Center.
The biggest issue was the sequencing of the jail buildings'
monolithic, pan-slab concrete structure, says John Hammer,
senior project manager with the Chicago office of New York-based
Bovis Lend Lease Inc., the contractor.
This involved setting 609 precast modular, double-stacked
jails. The jail's monolithic concrete structure was erected
in six clockwise phased pours per level, and the precast concrete
modular cells were set within the concrete structure erection
sequencing.
Levels three and four have double-stacked precast modular
cell units, and Level Two has a single stack arrangement.
Detailed scheduling of the sequencing was key to the success
of the project, Hammer says.
The three-story court with lower level has four courtrooms.
The four-story jail with lower level service facility has
loading docks, kitchen, laundry, and under-structure parking.
The court and jail are connected with a three-hour-rated wall
separating the independent structures. A link connects a power
plant and jail and also services the court.
The jail is monolithic pan-slab concrete, and the court is
steel framed with concrete floors on metal deck, Hammer says.
Both the court and jail are enclosed with architectural precast.
Saving Local Church
A downtown location at the corner of Winnebago and State streets
was selected to ease fears about eh status of the city's second-oldest
Roman Catholic Church, St. Mary Oratory. Fifty-two parcels
of land were purchased to create the 12-acre site to avoid
threatening the future of the church.
In addition to the 1,212-bed jail, the 600,000-sq-ft facility
holds the offices of the county sheriff, state's attorney,
public defender and court service departments.
The project also included an underground tunnel to connect
it to the nearby Public Safety Building and underground parking.
Top Projects Completed 14
The Regatta
Cost: $140 Million
The 44-story Regatta condominium tower in Chicago is part
of the 16-highrise Lakeshore East development immediately
adjacent to Lake Shore Drive.
The 690,000-sq.-ft. Regatta will have 321 condominium units.
The location allows views of Lake Michigan and the Loop.
The building was designed with some distinctive architectural
features to make it stand out among the large number of residential
structures-a key strategy in the high-end condominium market.
For instance, variety was introduced into the project's appearance
through a number of methods.
Curtain wall dresses the main facade, but a substantial amount
of masonry makes up the east and west facades.
An aesthetic element resembling a sail rises about 20 to 30
ft. from the building top and will be backlit. The spandrel
glass element, which will hide mechanical equipment, reinforces
the building's nautical theme.
Small Structure Nearby
Plans also call for a 12-story structure, dubbed the "Bustle
Building," to connect to the main building so that the
project's size is not overwhelming. It also gives a different
view for homeowners who do not want to live in a big tower.
A green space will be atop the Bustle and in a plaza to serve
the entire Lakeshore East development.
Space inside the main structure and Bustle will provide 360
parking spaces.
Amenities include a swimming pool with locker rooms on the
second floor, a media room where movies can be viewed and
a community room with fireplace.
The first level will have about 8,000 sq. ft. of retail space,
and an aim is to lease a portion to a restaurant.
Sitework was an issue in the project's early going, because,
in part, Lake Shore Drive and boat slips had once been located
nearby.
Because of the accumulation of debris, transfer beams were
installed to shift pressure from the obstructions, Bullard
said.
The project was close to Wacker Drive, so crews had to be
careful not to interfere with existing caissons and columns.
Top Projects Completed 15
St. John's Mercy Heart Hospital
Cost: $140 Million
The 350,000-sq.-ft., nine-level St. John's Mercy Heart Hospital
is connected to existing facilities on the St. John's campus
and will incorporate a number of uses.
In addition to cardiac care, these include pediatric and adult
emergency areas and a kitchen. Several doctors have leased
space.
Two of the heart hospital building's nine floors are below
grade. The lowest level will include emergency-department
office space along with the kitchen, which will serve not
just the heart hospital but also many St. John's patients
elsewhere on campus. One floor up will be five operating rooms,
25 prep/hold/recovery rooms, four catheterization labs and
an endovascular room.
The new emergency department is housed in the first floor
above ground and replaces the existing St. John's Mercy emergency
department.
On the second floor, tenant space will include more catheterization
labs.
Floors three through five include the heart hospital's patient
rooms, with 32 private rooms on each floor. The sixth floor
is to include a rehab gym area, children's heart area and
noninvasive cardio suite. Leased tenant space will fill the
top floor.
Concrete provides the building's structure, with steel used
in the penthouse.
The new heart hospital is clad in precast and brick.
Site Also Developed
The overall project also includes a fair amount of site development.
For example, the relocation of the emergency department required
construction of a helicopter pad.
The St. John's Mercy Heart Hospital project has brought plenty
of challenges relating to mechanical, electrical and plumbing
installation.
Joining the usual plumbing, ductwork, electrical and fire-protection
systems in the interstitial space are lines supplying oxygen,
nitrous oxide and vacuum.
The heart hospital also required more than its share of communications
cabling because images and medical records are to be collected,
stored and shared digitally. That means, among other things,
computers and network connections in all patient rooms.
St. John's Mercy Heart Hospital will put a premium on patient
and visitor comfort.
It has a hotel feel, with stone walls in the lobby, terrazzo
floors and cherry wood paneling. Some of those elements work
their way into the rest of the hospital.
In addition, the patient areas were designed to be hotel-like
with a more restful setting. The patient floors each have
a center hallway for the noisiest, high-traffic uses, plus
two carpeted outer hallways that provide access to the patient
rooms.
Top Projects Completed 16
Translational and Biomedical Research
Center
Cost: $138 Million
Two heads proved better than one when the Medical College
of Wisconsin and the Children's Research Center joined forces
to create the 310,000-sq-ft Translational and Biomedical Research
Center on the grounds of the Milwaukee Regional Medical Center.
The structure features three floors of laboratory space and
two floors of vivarium space. The project broke ground in
January 2005 and was completed in December 2006.
The structure was designed to accommodate approximately 80
researchers and physicians. It contains space devoted to molecular
critical care; developmental vascular biology; pediatric surgery;
the Children's Kidney Disease Research Program; the Individualized
Medicine Institute; pathological/vascular anomalies; and clinical
pharmacology, pharmacogenetics and teratology.
It will also house major research programs, such as The Cancer
Center; Biotechnology and Bioengineering Center; Center for
Biopreparedness and Infectious Diseases; and Structural Biology.
Dealing with Complexity
Adam Jelen, senior project manager for Gilbane Building Co.,
the contractor, said there were many project issues. These
included a fast-track schedule, research space complexity,
dual ownership, site restrictions and utility relocations
as some of the project's most significant challenges.
The structure was located above an existing utilities corridor
that included a steam tunnel, 30-in., chilled water mains,
electrical utility duct bank, a water main and sewer mains.
In addition, the research spaces required extremely complex
HVAC systems, including layers of ductwork and piping. Mockups
were used to choreograph construction of these areas.
The entire project had to be completed while treading lightly
and monitoring sound and vibration levels to avoid disrupting
ongoing research in adjacent buildings.
"What made the project a success is the dynamic, integrated
approach by all team members, including early contractor procurement,
upfront, detailed coordination and fabrication," Jelen
said.
Top Projects Completed 17
Westin North Shore
Cost: $131 Million
The four-star, 411-room Westin North Shore tops out at 15
stories and anchors a complex that will include retail and
restaurant space, a bank and parking on a 21-acre site at
the southeast corner of Lake-Cook Road and Milwaukee Avenue.
At 180 ft., it's the tallest building in Wheeling and just
slightly higher than the area's next largest building - Riverwalk
Office Plaza directly across Lake-Cook Road in Buffalo Grove.
The 15-story hotel will target small- to midsized corporate
meetings and banquets and features large guest rooms and the
latest wireless technology.
Other favorable conditions include proximity to office parks
and suburban headquarter businesses.
The hotel features a grand ballroom that can accommodate 1,200
guests for a banquet or 1,500 people in stadium-style seating.
In addition, there will be 40,000 sq. ft. of meeting space.
The hotel's signature restaurant is slated to be a Japanese
steakhouse.
There will be three restaurants in the hotel, three on parcels
in front and inline retail shops near the hotel along Milwaukee
Avenue.
Rooms will feature standard Westin finishes with higher-end
finishes in the 30 suites. The building exceeds Westin's standards.
For instance, Westin's standard room height is 8.4 ft., but
this building features a 9-ft. height.
Tweaking Original Plans
Three years ago, Mid-America began assembling the site's four
properties, which included a horse stable, vacant investment
land, used car lot and Wonder/Hostess outlet. The site had
a small amount of environmental issues that were cleaned up.
The Village Board approved the proposal in spring 2004.
An 18-story, 225-ft.-tall hotel was originally proposed, but
the initial plan exceeded the Federal Aviation Administration's
height restrictions-the project is near Palwaukee Municipal
Airport.
This required the floor plans to be redesigned, going from
441 rooms to the final number.
With the site close to the Des Plaines River, the construction
team decided to use a 5-ft.-thick steel and concrete matt
foundation instead of deep piles.
Also, since the building's height was reduced, it wasn't as
heavy and was therefore more conducive to a matt foundation,
which enabled construction to move quickly.
Top Projects Completed 18
Metropolis Shopping Center
Cost: $127 Million
Urban character distinguishes Premier Properties USA Inc.'s
lifestyle center in Plainfield, Ind., from others.
The buildings are not themed in a way that would make them
dated. The facility is open air tying in with an upscale downtown
atmosphere.
Materials include metal panels, cast stone, brick, EFIS and
glass. In addition to a variety of scales, the buildings are
also taller than most outdoor lifestyle centers.
Two of the buildings have a second floor for the mall's offices,
as well as 35,000 sq. ft. marketed for office use.
Lights, Sound, Action
A lot of that energetic spirit stems from the center's Futura
Park Plaza where choreographers synchronized light-emitting-diode,
color-changing lighting; music; and special effects with 30-ft.-high
jets of water.
The LED images appear on pylons and on transparent wire mesh
screens mounted on light framework several feet in front of
the retail storefronts.
Patterned concrete block, urban landscaping and 28- to 38-ft.-tall
steel towers housing lights and speakers surround the fountain.
Metropolis includes upscale retailers unique to Indianapolis'
west side, including Ann Taylor Loft, Finish Line, Victoria's
Secret, Lane Bryant, Kirkland's, Ulta, DSW, Jos. A. Banks,
Coldwater Creek, Pacific Sunwear, Vera Bradley and Yankee
Candle. The center's best-in-class restaurants include Stone
Creek Dining Company and Claddagh's Irish Pub.
In total, Metropolis encompasses 12 buildings within 650,000
sq. ft., including anchors JCPenney, an 18-screen Rave Theatre
and a two-level Dick's Sporting Goods.
Phase one included the central plaza, 150,000 sq. ft. of specialty
retail space, 70,000 sq. ft. of office space, the movie theater
and the sporting goods store on 75 acres. The four-building
second phase completed Metropolis.
Across the street, Premier offers more pragmatic shopping
at Plainfield Commons, which includes Target, Kohl's and Wal-Mart.
Sometime in the next two years, Premier plans to expand the
big-box center on a 70-acre site. Plainfield Commons 4 will
include 228,000 sq. ft. within nine buildings.
Top Projects Completed 19
Microbial Sciences Building
Cost: $122 Million
Installing the systems required in modern laboratory buildings
are frequently a complex issue.
The intricacies of the 330,000-sq-ft Microbial Sciences Building
at the University of Wisconsin at Madison went beyond exhaust
hoods.
The six-story structure was shoehorned around the campus'
historic Hiram Smith Hall and built over a working electrical
substation.
The facility had to meet post-Sept. 11 security requirements.
And, a design featuring an open environment was required so
ideas could be exchanged and people could interact in the
academic programs the building houses. These include bacteriology,
medical microbiology and food microbiology. Because of these
programs, the building houses a crystal growth chamber, vivarium
and research kitchen.
|
The university has big hopes for the building. It is intended
to keep the school competitive and attract top-drawer faculty
and students capable of puling in research grants.
Dealing with Soils
Site issues included an area of poor soils and accommodating
the structures and activities around the area.
Spread footings had been planned for the affected area of
the structure, but the unplanned redesign called for drilled
caissons, which were used in other areas that required deep
footings.
An electrical substation, which provides power to about 25%
of the campus, was located in E.B. Fred Hall, the building
that stood on the site when the project began. The substation
remained functional throughout the demolition of E.B. Fred
and throughout the new construction.
The upper levels of E.B. Fred were torn off first and then
the rest of the structure demolished to leave the substation
intact and running. A roofing membrane was put over the substation
and enclosed in a mostly underground bunker.
The team was worried about the historic Hiram Smith building
during excavation and foundation work.
With the new structure wrapping around two sides of Hiram
Smith and an old crack in its foundation, the historic structure
had to be monitored closely to be sure there was no settlement.
An additional site issue included a $25 million utility project
going across part of the Microbial Science Building's construction
fence.
Top Projects Completed 20
University Club Tower
Cost: $119 Million
The University Club Tower in Milwaukee will overlook the
Milwaukee Art Museum and Lake Michigan.
The building will house 38 floors of residential space with
mechanical penthouse and will contain 57 units.
The units, two per floor with elevators that open directly
into each unit, range from 2,984 sq ft to 4,043 sq ft. Some
buyers have elected to purchase an entire floor.
The exterior of the tower, which will be distinctive for its
height and glass crown, is designed to fit in with the other
structures in the neighborhood.
The building's skin will be glittering white, complimenting
the white-winged Santiago Calatrava-designed Milwaukee Art
Museum Addition it overlooks and the stately Cudahy Tower
residential building to the south. Built in 1909 and 1929,
Cudahy is constructed of marble, glazed brick and terra cotta
- all gleaming white.
The University Club's amenities include expansive views of
the city skyline, security features, a cooled room for grocery
transport, 325-sq-ft terraces and 17,000-sq-ft private garden.
A coordination issue involved the cabinetry from Italy for
the condo pantries.
A 20-week lead time was needed to get the millwork and casework
onsite.
Some unexpected poor soil conditions set the team back nearly
12 weeks to redesign the caisson system. The soil consisted
of loose clay and some ash from foundries from long ago.
Originally, there was a belt caisson system that had to be
changed to a straight-shaft system. The team also went from
70 ft deep to more than 90 ft deep.
Click here for 20
Top Projects Started>>
|