| Gold Medal of Construction
Olympic Effort Needed
To Erect Mega-Projects
by Craig Barner
If Chicago lands the Olympics in 2016, the city will see
a level of construction worthy of a Greco-Roman wrestler.
With this issue, Midwest Construction presents its own effort
of grappling with a enormous task: the Top
Projects Started of 2007.
Top Projects Started 1
Chicago Spire*
Cost: $1.2 billion**
It will be the tallest building in North America, the tallest
residential building in the world and bear the design flourishes
of Santiago Calatrava.
The Chicago Spire residential tower will rise 2,000 ft., hold
3 million sq ft of space and total 150 floors, says Kim Metcalfe,
senior vice president of Weber Shandwick Worldwide in Chicago
and spokesperson for Shelbourne Development Group Inc., the
Dublin-based developer.
The project features a twirling appearance sometimes compared
to a plume of smoke, drill bit or swirling cloak. The project
itself has undergone a number of twists.
|
The project proposal was initiated in 2005 by local developer
The Fordham Co. Fordham had originally commissioned Calatrava
and had the option to buy the 2.2-acre property near the intersection
of the Chicago River and Lake Michigan.
But Fordham fell short on financing, and Ireland's Garrett
Kelleher stepped in to keep the project going. Kelleher had
previously worked as a painting contractor and developer in
Chicago, working here between 1986 and 1996, when he returned
to Ireland.
Detailing the Spire
The project details have changed numerous times, but several
facts have been confirmed.
The building will hold 1,200 condominiums that range in size
from 600 to 8,000 sq ft, Metcalfe says. Hotel rooms, which
had previously been announced, have been taken out from plans.
The building will feature a composite structure - steel and
concrete - with a 360-degree rotation.
More than 1,300 parking spaces will be below ground in a six-and-a-half
story hole.
Despite the name, the tower will not be topped with a spire,
Metcalfe says.
The top will be illuminated.
The building's base will hold a four-story, transparent lobby
with five stories of amenity space for the residents, including
spa, fitness area and brasserie. The condo units start on
the 10th floor.
Access to the spire will come from ramps built on Lake Shore
Drive, Metcalfe says. Traffic will exit on a ramp, go underneath
the drive to Lower Lake Shore and arrive at the spire entrance.
Plans call for the building to attain LEED Gold Certification,
Metcalfe says.
Rainwater will be recycled for car washes, river water will
be used for cooling and "ornithologically correct glass"
will be incorporated in the building to help spare the birds
who fly through the area.
*The Chicago Spire was approved by
the Chicago Plan Commission in mid-April when the June issue
of Midwest Construction was closing. Financing is still a
question mark. The magazine decided to include the project
in Top Projects based on discussions with the developer's
spokespeople, who said construction would proceed in spring
2007.
**The cost given in 2006. The developer
has declined to confirm the cost estimate.
Top Projects Started 2
Mandarin Oriental Hotel
Cost: $750 Million
The Mandarin Oriental Hotel in Chicago's East Loop will achieve
lofty height of 62 stories.
Before that loftiness can be erected, the site for the mixed-use
residential property has to be prepared.
For instance, a tunnel carrying water from the Chicago River
to the Prudential Building is being moved, says Tim Harder,
senior vice president of Bovis Lend Lease, the contractor.
The water is used to provide cooling, rather than chillers.
In mid-April, the tunnel was being relocated so that it does
not conflict with the belled caissons to be laid.
A freight tunnel with a bulkhead is located on a corner of
the site, and it will need to be avoided during caisson and
sheeting work.
Lower Stetson Avenue will be lowered 4 ft so the proper head
clearance for trucks delivering materials can be attained.
"There is quite of bit of finesse work to get around
the obstructions," Harder adds.
Above ground, a number of deep beams will be used to provide
the wide spans for the ballroom.
Boulevard Towers to the west will have to be accommodated.
Normally, tenants access Boulevard from Lower South Water
Street, which will be unavailable during construction, Harder
says. As a result, a concrete tunnel from Middle Stetson Avenue
will be constructed to provide access.
More than 500 Units
The mixed-use residential building will hold 252 hotel rooms,
103 hotel-residences and 162 condominiums. Overall it will
hold 1.4 million sq ft of space.
In addition to the ball room, amenities include the Mandarin's
world-renowned spa and fitness center.
The building will feature a number of aesthetic design features.
These include the horizontally oriented bustle at the building
base; a 70-ft-tall lantern at the top illuminated at night;
and an indentation sometimes referred to as the "zipper"
along the building's north facade.
The concrete-supported building will be framed in aluminum
curtain wall, Harder says.
The project for which constructed started in March is expected
to last through 2010.
Top Projects Started 3
Interstate 64 Reconstruction
Cost: $535 Million
A 10.5-mi.-long segment of Interstate 64 in St. Louis will
be reconstructed, the Missouri Department of Transportation
announced.
I-64 is the first design-build project that the legislature
in Jefferson City has authorized in transportation. Because
of the project's complexity, Missouri officials sought the
best design ideas to maximize funding.
As a result, Missouri highway specifications were not required
in proposals.
Standards from other state agencies could be proposed provided
they had previously received the approval of the American
Association of State Highway Transportation Officials or the
U.S. Department of Transportation's Federal Highway Administration,
both based in Washington, D.C.
The Gateway proposal calls for a concrete pavement with 45-year
design life that is expected to need a single maintenance
application in 25 years.
An Aging Highway
The project on the east-west thoroughfare covers I-64 between
Kingshighway Boulevard on the east in the city and Spoede
Road in St. Louis County on the west.
Construction started in spring 2007, and lanes are expected
to reopen on Dec. 31, 2009, though contract completion is
anticipated on July 31, 2010.
In addition to the rebuilt pavement, bridges and each of the
12 interchanges will be reconstructed. One lane will be added
in each direction.
Reconstruction is necessary because I-64, which was originally
built piecemeal as U.S. Route 40 between the 1930s and 1960s,
can no longer handle today's traffic volume without significant
delay. The segment, which handles an average of 170,000 vehicles
daily, was designed for a maximum speed of only 45 mph.
Motorist safety is also a concern due in part to the tight
clover-leaf ramps from previous design eras. Some ramps are
signed as low as 15 mph.
Twenty-four existing bridges will be rebuilt because they
are deteriorating. In addition, five new ramps at the I-64/Interstate
170 interchange will also be constructed.
The segment from project's western end to its midway point
will be shut completely in 2008. The following year, the segment
from midway point to the eastern end will be closed in full.
Plans have been made to accommodate motorists. For example,
lanes have been narrowed to 11 ft. from 12 ft. and shoulder
space reduced on Interstate 70 on the north and Interstate
44 on the south.
Top Projects Started 4
Aqua
Cost: $474 Million
A distinctive aesthetic design feature of 86-story Aqua mixed-use
residential tower in Chicago will be the building's undulating
waves of concrete.
The appearance of ripples will be achieved via the edge of
every balcony, says Steve Wiley, chief estimator of Chicago-based
James McHugh Construction Co., the contractor.
"Each edge or perimeter of every balcony is unique and
different from the one above or below it," he says. "It
will look like there was a fire in the building that randomly
burned the patterns going up the face of the building."
Designers are working with glass and reflectivity to accentuate
the appearance of wave shapes.
Given the unorthodox design feature, the typical issues of
construction are being carefully thought through.
For instance, finding the best location and connecting the
hoist will be challenging because of the varying geometry
of the balcony edges.
The undulating design feature, however, will not have a bearing
on the structure.
"It's a simple, rectangular structure, and the only thing
'moving' are the balcony edges themselves," Wiley says.
One Big Building
The 2.2 million-sq-ft building on Columbus Drive will hold
968 housing units-474 rental apartments, 264 condominiums,
225 hotel rooms and nine park houses.
Because of its size, Wiley says the building will require
31 rock caissons-footings socketed about 6 ft into the bedroom
beneath Chicago. The project also calls for 223 traditional
belled caissons.
In addition, the structure will rest on a 6-ft-thick concrete
mat slab.
Due to the complexity of the project, elements that include
the structure, mechanical system, electrical system and fire
protection are being done design-build, Wiley says.
A podium will hold 1,300 parking spaces. The podium's lid
will hold many of the building's amenities-running track,
walking path, fire pits, whirlpools, lap pool and volleyball
court. The building will hold two ballrooms.
Construction activity started in February and is expected
to last until February 2010, Wiley says.
Top Projects Started 5
Block 37
Cost: $450 million
Block 37 is the 2.75-acre plot in Chicago's Loop between
the Richard J. Daley Center and the former Marshall Field's,
now Macy's.
The spot has been vacant since the 1989, when it was razed
for redevelopment. A number of development plans were put
together but fell through. Indeed, Maryland's Mills Corp.
was the original developer of the existing project, but its
plans were purchased by Palatine's Joseph Freed & Associates
LLC and Chicago's Golub & Co.
Plans call for stores, offices, restaurants, apartments and
an underground Chicago Transit Authority station.
The CTA station will provide express trains to O'Hare International
Airport and Midway Airport.
A unique element is that passengers for upcoming flights from
the two airports might be able to check their bags at Block
37. Trains will reportedly have luggage racks and wider seats
than standard trains, but tickets could be $10, rather than
the $2 regular fare.
Retail and Entertainment
The base will hold retail and entertainment at the base, including
the on-air station for local CBS affiliate WBBM-TV Channel
2.
Channel 2 is expected to move in a 100,000-sq-ft space at
the corner of Washington and Dearborn streets in 2008 near
the city's famed Pablo Picasso sculpture. The station will
operate an on-air studio and have electronic billboards displaying
24-hour news headlines.
Some retail tenants have been announced: Banana Republic,
Gibson's Steakhouse and Lucky Strike Lanes bowling alley.
Morningstar, an investment research firm, will anchor the
16-story, 440,000-sq-ft. office portion of the project.
Plans also call for two residential towers, one holding 365
condominiums and the other holding 420 apartments.
Top Projects Started 6
353 N. Clark St.
Cost: $440 Million
Demand for upscale, Class-A office space in Chicago is resulting
in the 353 N. Clark St. project in the River North area.
In mid-April, the 46-story tower was 66% pre-leased, says
Rux Currin, senior vice president of Chicago-based Mesirow
Financial, the developer.
Mesirow will also be a tenant and depart its long-time home
across the street at 350 North.
Another major tenant is Jenner & Block LLP, a Chicago-based
law firm.
Other office and retail tenants are being pursued.
The 1.2-million-sq-ft building will hold offices, retail and
220 parking spaces in two below-grade levels, Currin says.
The office entrance will be on Upper Carroll Court and the
retail entrance on Kinzie Street - appropriately so because
of the increasing amount of retail on Kinzie.
"The site slopes 12 to 13 ft, so it gives us an opportunity
to separate the entrances for office and retail," Currin
says.
The steel-framed building will be dressed in curtain wall.
Construction began in November, and occupancies will start
at the end of 2009. Mesirow will move in 2010.
Top Projects Started 7
Nestle USA
Cost: $359 Million
A Nestle beverage plant was just what the Indiana city of
Anderson needed to help it deal with some 2,000 job cuts promised
at two longtime automotive employers.
The Nestle USA beverage division, based in California, announced
in July 2006 its plans to build the facility that will employ
more than 300 people making an average of nearly $20 an hour.
Nestle cited growing demand for Nesquik Ready-to-Drink and
Coffee-Mate Liquid, which the new facility is to manufacture
and distribute. The products have been made by Nestle suppliers,
but their in-house manufacturer was lured to Anderson by nearly
$8 million in state incentives plus local tax abatements,
bonds and incentives valued at approximately $46 million.
Ground was broken Aug. 15, said Rob Sparks, Anderson deputy
mayor and chairman of the city's Board of Works.
Nearly 1 Million Sq Ft
The 880,000-sq-ft facility-located on a 190-acre site along
Interstate 69-will include a sterile manufacturing environment
along with onsite computerized warehousing. Manufacturing
dry runs could happen in the fourth quarter of 2007, with
plant startup set for the first quarter of 2008.
Using tax-increment financing, the city has arranged site
preparation including a new electric substation, a rail spur,
upgraded sewer capacity and improved site drainage.
"We were fortunate enough to land it and get them in
a position to turn dirt in a short amount of time," Sparks
says.
Though the site is on the edge of an existing business park,
"it incorporates additional acreage that had not been
developed," he says. "We're cutting a new drainage
ditch, and it'll help open up several hundred more acres for
development."
The Stellar Group, based in Jacksonville, Fla., is the project's
general contractor. The company is providing design-build
services for the liquid-processing facility, including site
evaluation, architecture, engineering and construction management.
Stellar has previously worked with Nestle on several facilities
elsewhere.
Top Projects Started 8
Saint Joseph Regional Medical Center
at Edison Lakes
Cost: $355 Million
In early March, the foundation was poured for the Saint Joseph
Regional Medical Center at Edison Lakes in Mishawaka, Ind.
Preparing the 93-acre site began in October 2006. The 633,000-sq-ft
hospital is slated to open in fall 2009. It will provide 254
private inpatient rooms and baths with hotel-style ambiance
in two towers that are anchored by a diagnostic and treatment
platform. Multiple-story medical office buildings will also
connect to the hospital.
The new hospital replaces an aging facility in downtown South
Bend as well as St. Joseph's Mishawaka facilities.
"It will serve all of our patients in our regional market,"
says Sarah Hoshaw, strategic project manager for Saint Joseph.
"We were handling more than 1 million sq ft of old, inefficient
space. Now we're going down to a 633,000-sq-ft facility that's
more efficient. We'll be able to service as many or more patients."
The efficient design includes a two-story diagnostic and treatment
center that will include the emergency department, imaging,
diagnostics, surgery, catheterization lab and interventional
cardiology and conferencing areas.
Seeking Adjacencies
The adjacency of the medical departments improves the flow
of care for patients, their physicians and all caregivers,
Hoshaw says.
Patient comfort and satisfaction was also a driver of the
design.
"All storm water is retained in onsite retention ponds
that are placed around the site to provide a natural healing
atmosphere," Hoshaw says.
Half of the patients will have a view of these ponds and the
other half will overlook a grassy meadow area. Walking paths
also weave through outdoor area.
"The design was centered first and foremost on the patient
and secondly on the service atmosphere," Hoshaw says.
A business center as well as a concierge service will be available
for patients and visiting family members. "Any visitor
will be able to use laptops to provide a more comfortable
atmosphere than typical," Hoshaw says.
Also, families of neonatal infants or pediatric patients will
be able to stay overnight in designated visitor rooms.
The project's community participation plan is to achieve 6%
minority business enterprise participation and 6% women business
enterprise participation.
About 375,000 cu yds of soil was excavated and 24,000 cu yds
of concrete was poured for the foundation. The project will
use 5,000 tons of structural steel, 13 acres of tile, carpeting
and resilient floor coverings, 2 acres of glass, 2.3 million
sq ft of drywall and 1.1 million lbs. of duct work.
Top Projects Started 9
Sherman Hospital Replacement Campus
Cost: $310 Million
An onsite 15-acre geothermal lake could save the new Sherman
Hospital Replacement Campus in Elgin, Ill., up to 30% in energy
costs annually.
Designed on a rolling farmland site, the single-patient rooms
also overlook this man-made lake providing a healing environment
amid the nature setting.
"It's a sustainable form of energy," says Peter
Schlossman, senior associate principal, Loebl Schlossman &
Hackl. "We're reducing the need to use fossil fuels to
heat and cool the building."
This geothermal technology is a first for an Illinois hospital
and one of the largest in the world. Sherman was awarded a
$400,000 grant from the Illinois Clean Energy Community Foundation
for Environmental Leadership.
255-Bed Hospital
The project includes building a 255-bed, 650,000-sq.-ft. facility
and a 100,000-sq.-ft. medical office building. Construction
began in summer 2006 and the estimated completion is November
2009.
The campus relocates Sherman Hospital to this 154-acre greenfield
site on the west side of Elgin on Randall Road just off the
expressway, which also improves access and visibility.
"This new hospital gives them all the updated equipment
and layout needs that are in demand in Elgin," Schlossman
says. "The existing hospital has been an assemblage of
different wings added on over the years and it's landlocked
and there's no more real estate to purchase in that area."
Horizontal bands of brick and glass curtain wall form the
exterior façade of the seven-story hospital. Registration
and waiting areas will be on the first-floor of a circular
glass atrium. Visitor conference rooms, the kitchen and dining
facility as well as an outdoor patio are at lake level. A
six-floor in-patient bed tower will rise above this dining
area.
A four-story medical office building will also be wedged between
the in-patient tower and the emergency department.
An adjacent single-story building will house the cancer center
and administration.
The integrated design allows each component of the hospital-bed
units, diagnostic and treatment space, medical offices, and
parking-to expand individually over time to provide maximum
flexibility.
Top Projects Started 10
Blue Cross Blue Shield Illinois
Cost: $270 Million
The headquarters building of Blue Cross Blue Shield Illinois
in Chicago is sprouting an extension.
The 32-story building in the city's East Loop is getting an
additional 25 stories, according to Chicago-based Goettsch
Partners, the architect on the project.
The extension is needed because of growing space needs at
Blue Cross.
Completing Original Plans
The office tower was started in 1995 and completed in 1997
with plans for expanding vertically. With the initial building
nearing capacity, the decision was made to move forward with
the second phase.
Chicago-based Health Care Service Corp., which operates the
Blue Cross and Blue Shield insurance plans in Illinois, New
Mexico, Oklahoma and Texas, realized in the early 1990s that
growth had forced it to relocate from leased space four times
in a 25-year period.
As a result, the company set out to build a facility that
would accommodate immediate space requirements and expectations
for continued growth.
When finished in 2010, the 57-story, 2.3 million-sq.-ft. building
will accommodate 8,000 workers, up from 4,200 currently.
The expansion will increase the size of the tower to 2.2 million
sq ft, up from the 1.4-million-sq-ft existing tower.
HCSC will not occupy all 57 floors. About half of the new
space will be leased to other tenants.
Top Projects Started 11
Potawatomi Bingo Casino
Cost: $240 Million
A three-pronged, $240 million expansion project at the Potawatomi
Bingo Casino expansion is Milwaukee's Menomonee River Valley
is more than doubling the casino itself, creating a additional
parking structure and connecting the existing parking structure
to the city's James E. Groppi Unity Bridge (still known locally
at the 16th Street Viaduct) via a connecting bridge.
The three-story casino portion of the project broke ground
in August 2006, adding more than 500,000 sq ft to the existing
256,000 sq ft casino. It will house gaming space in a Native
American theme, restaurants, entertainment spaces and back-of-house
space. The lower level will hold valet parking for about 350
cars.
Dealing with Water
Water issues on the valley floor have presented challenges
from the project's start.
"The lower level of the expansion, the valet parking,
is about 10 ft below grade," says Wayne Groeschel, project
manager in the Milwaukee office of the Providence, R.I.-based
construction manager, Gilbane Building Co. "The river
is about two blocks over and the water table is about five
or six feet down."
Groeschel says the water issues required a perimeter of sheet
piling and a dewatering system during construction. In addition,
1,800 pipe piles were driven before any foundation work could
begin due to soil he says is, "not very conducive to
holding up a building."
The high water table also impacted the building's foundation,
requiring a suspenders-and-a-belt approach to waterproofing.
A waterproof membrane was installed to protect the lower level,
and a waterproofing compound was added to the foundation's
concrete mixture.
A precast parking garage, sized to accommodate approximately
1,800 cars, got under way in October 2006. It is schedule
for completion in December 2007.
The project's connecting bridge project broke ground in September
2006 and will be completed in June 2007.
Top Projects Started 12
300 N. LaSalle St.
Cost: $230 Million
The 300 N. LaSalle St. office tower will be located on the
north bank of the Main Branch of the Chicago River.
The office tower will stretch 60 floors and encompass 1.3
million gross sq. ft. of space, says Brad Johnson, project
executive in Chicago with Bethesda, Md.-based Clark Construction
Group, the contractor.
The anchor tenant is Chicago-based law firm Kirkland &
Ellis LLP, in addition to other tenants. Other uses will include
three levels of below-grade parking, retail and restaurants.
Tenants will have access to the river's edge and a public
garden. The space will feature landscaped terraces, seating
and a cafe.
Inside the building, steel with concrete core will support
the structure, Johnson says. Unitized aluminum curtain wall
cladding with stainless steel accents will dress the structure.
Construction activity started in July, and the project is
expected to be complete in December 2008.
Project Issues
The team is facing a number of issues early on the project,
including earth retention and closeness to the river. Steel
sheeting with a core retention system of H-piles and lagging
was used for the earth retention.
Because of the waterfront site, there is limited access. "However,
we're trying to turn it into a posstive by investigating using
barges for some of the materials we're bring to the site,"
Johnson adds.
Restrictions due to nearby residential is limit the number
of hours work can be done between 8 a.m. and 8 p.m.
The floors will be repetitious from a structural standpoint,
so"you can get into a groove like a marathon runner,"
Johnson says.
The building is designed to achieve LEED certification from
the U.S. Green Building Council.
Top Projects Started 13
SSM St. Chare Health Center
Cost: $224 Million
As St. Louis grows, so grows the SSM St. Clare Health Center
in Kirkwood.
A new hospital, located on a former golf course about 4 mi
from the existing, 1940s facility, will meet the needs of
a one-bedroom community that has become part of the suburban
St. Louis area in recent years.
The new facility broke ground in June 2006 and is slated for
completion in early 2009. According to Tom Miller, communications
manager for SSM Health Care St. Louis, it will create a healing
environment that accommodates the latest in medical technology.
"From the very onset of design, we have been focused
on some innovative design principles," Miller says. "We
have used design learning labs to engage employees to come
in and design the patient rooms-the functionality of those
rooms."
Inviting for Patients, Family
Subtle details will include carpeted hallways to reduce noise
and create a warm, hotel-like environment; patient controls
for lights and temperature in rooms; and ample, inviting space
for family members and other visitors.
The hospital's design reflects SSM's move away from a traditional,
institutional facility.
The hospital will be divided into four distinct zones: inpatient,
emergency, outpatient and surgical/specialty services. Each
of the zones will be marked by an exterior architectural feature
that will serve as a guide to the entrance for that particular
zone. Each of the four zones will be organized around a "town
square" of dining, retail and other amenities.
Within the inpatient zone, the concept of "acute adaptability"
is being employed to make each room adaptable for the varying
care needs that might arise during a patient's stay. This
eliminates the need to shift a patient from unit to unit within
the hospital.
The hospital will also feature such cutting-edge details as
bedside registration, all digital electronics and wireless
access to images, X-rays and scanner and electronic ID bracelets.
The idea of creating a hotel-like, noninstitutional environment
extends to the facility's food service as well. Patients will
be able to determine the time their meals are delivered and
will be able to order home-style meals that will be delivered
within a half-hour of ordering.
"This hospital will unique from anything we have seen
in this region," Miller says.
Top Projects Started 14
Pointe Blue
Cost: $220 Million
Racine, Wis., is reaching for the skies with a three-tower
condo project on the Lake Michigan waterfront, dubbed Pointe
Blue.
The project will create 320 condo units in high- and mid-rise
towers, along with 125 low-rise units mixing waterfront villas
and townhouses. First occupancy is scheduled for the fourth
quarter of 2008, with final completion in May 2012.
In addition to the 445 condominium units, ranging in price
from $220,000 to $970,000, 100 apartment units are also planned.
Scott Fergus, president of developer KeyBridge Development
Group of Waukesha, says site preparation began in February
2007.
According to Fergus, putting up 1.5 million sq. ft. of buildings
requires overlapping construction phases and employment of
two construction management firms. Tri-North Builders of Madison
will manage the low-rise units, and KBS Construction will
manage the towers.
Rejuvenating the Soil
Remediation will likely be the project's biggest issue, Fergus
says. The 20-acre site housed several businesses in its history,
including a manufacturing company.
"There is benzene in the soil, petroleum and a variety
of chemicals," he says.
The remediation plan for the site has been approved by the
Wisconsin Department of Natural resources.
"We will cap the site with a geo membrane, and three
feet of clay and sand," Fergus says. "From there
we will bring in top soil and build."
Many of the structures will be slab-on-grade construction
due to the water table issues presented by the project's close
proximity to Lake Michigan and the Root River.
Pointe Blue will be a mixed-use, lifestyle development, featuring
125,000 sq ft of retail for specialty grocers, coffee shops,
a video store and other retailers.
Fifty boating slips will also be including in the development
as will pedestrian and bike paths and renovation of several
historic structures.
In April 30 percent of the condo units had been reserved.
Top Projects Started 15
Greater Lafayette Health Services
Hospital
Cost: $192 Million
Excavation and site clearing began late last year to make
way for the Greater Lafayette Health Services Hospital on
the east side of Lafayette, Ind. It will replace two older
facilities, Home Hospital and St. Elizabeth Medical Center,
and is scheduled to be complete in April 2009.
The consolidation will improve efficiency and staff productivity,
and will cost less than updating the two existing hospitals,
according to Terry Wilson, president and CEO of GLHS.
Built on a 103-acre site, the hospital has 150 private patient
rooms with 16 observation rooms, including acute care and
women's health and neonatal intensive care unit. Also included
are nine operating rooms, 27 emergency room beds, two catheterization
labs and radiology rooms. The imaging area includes two rooms
each for general radiology, radio fluoroscopy rooms, CT and
nuclear medicine. It also includes one MRI and one interventional
radiology room.
The 430,000-sq.-ft. campus includes three 75,000-sq.-ft. medical
office buildings, one of which is for hospital functions.
Embrace the Patient
The key design theme was "embracing the patient,"
says Rob Schoeck, principal of Indianapolis-based BSA LifeStructures,
the architect.
"The owner, Sisters of St. Francis Health Services, wanted
to emphasize the Catholic tradition in an understated way,
with a strong focus on the patient," Schoeck says. "From
the word 'embrace,' the design perspective was to create a
low-rise facility organized around a central interior courtyard
where the chapel is located."
The hospital's towers rise only three floors, and the campus
is spread out across 54 acres.
"The courtyard is very valuable in terms of intuitively
finding your way," Schoeck says. "Consistent views
to the outside are one of the best ways to get patients and
visitors oriented."
The exterior facade of the steel-framed buildings is brick
veneer and EIFS.
While the building materials reflect simplicity, there is
a stronger emphasis on color and texture at the entrances
and in the courtyard. In these areas, wood veneer is used.
"It's a welcoming wood product that shows up at the visitors'
entry and is restated in the courtyard," says Rich Engelhardt,
associate principal of BSA.
"A large curved curtain wall at the main entrance unifies
the two towers and gives an overall low-scale harmonious impression,
not an aggressive or highly modern expression of architecture.
It's low key and gentle."
Top Projects Started 16
Interstate 70 Reconstruction
Cost: $175 Million
You know a highway project is big when it gets its own name
and logo.
The Interstate 70 reconstruction east of downtown Indianapolis
has been dubbed "Super 70" and identified on promotional
materials with a winged highway sign.
The project hit full stride in late February with the demolition
of 6 mi of the interstate's westbound lanes.
"It will be a brand-new road, with 16 in. of new concrete
and 28 new bridge decks," says Andy Dietrick, communications
director for the Indiana Department of Transportation.
While crews from Chicago-based Walsh Construction Co., the
general contractor, are rebuilding the westbound lanes, both
directions of traffic are using the eastbound side. Five traffic
lanes are open: three inbound and two outbound during the
morning rush hour, then three outbound and two inbound for
the evening rush.
A special concrete barrier down the middle is moved twice
a day, at about 10 a.m. and 10 p.m., Dietrick says.
Once the westbound lanes are completed - a milestone set for
early July - traffic will shift to the new pavement while
the eastbound lanes are demolished and rebuilt. Completion
is set for Thanksgiving.
Originally constructed in 1971, this section of I-70 is the
busiest in Indiana, carrying 180,000 vehicles daily. No lanes
are being added, but the project will yield benefits beyond
the smoother pavement.
"The biggest thing from a safety perspective is that
the inside shoulder, which now averages 7 ft and in places
is a lot less, will be 14 ft," Dietrick says.
The other significant change affects a section some have dubbed
the "cattle chute," where the highway dips under
two bridges carrying Sherman Drive and the CSX railroad, causing
low clearance, poor visibility and, at times, flooded lanes.
The reconstruction project will raise the interstate above
the road and railroad.
InDot has cut the speed limit, banned 18-wheelers and closed
interchanges throughout the work zone.
Top Projects Started 17
Clarian Arnett Hospital
Cost: $170 Million
Steel topped out in March on the Clarian Arnett Hospital
in Lafayette, Ind. As of that date, 2,618 tons of structural
steel had been erected. This 440,000-sq-ft project includes
a seven-story hospital and a two-story central energy plant.
Construction began on the 152-bed hospital in June 2006, and
substantial completion is slated for Aug. 1, 2008.
Indianapolis-based Clarian Health Partners and Lafayette-based
Arnett Health System are partnering to develop the new hospital,
which features private patient rooms and five operating rooms
with expansion capabilities.
"This partnership will increase the momentum in the development
of the Life Sciences Corridor from Lafayette to Indianapolis,"
says Daniel Evans Jr., Clarian president and CEO. "Clarian
and Indiana University are primary forces behind the life
sciences, and the partnership in Lafayette will augment the
strong collaborations and collegiality that already exist."
IU, Clarian Partnership
The partnership between Clarian and the Arnett physicians
allows for seamless transition in care between office visits
and inpatient stays.
"Bringing additional resources to Lafayette will further
enhance research and educational collaborations between Clarian,
Arnett and the IU School of Medicine which partners with Purdue
University to provide the first two years of medical education
to some of our students on the West Lafayette campus,"
says Dr. D. Craig Brater, dean of the IU School of Medicine
and vice president of Life Sciences.
The joint venture hospital will split ownership, with the
majority owned by Clarian and a minority owned by Arnett physicians-similar
to the Clarian North and Clarian West ownership models. The
existing Arnett sites will also become owned by the new joint
venture.
"This hospital is new to the community," says Larry
Roan, vice president of business development for F.A. Wilhelm
Construction Co. Inc., the contractor.
"The exterior has a red brick base with some sandstone
and glass."
Wilhelm has exceeded the goals of 15% MBE and 5% WBE participation
on the project, Roan added.
In January, Purdue University's Construction Management program
received a live Web-based field trip of the project. A camera
mounted on a hardhat with two-way headsets was live-linked
to a Purdue classroom allowing the students and tour guide
to dialogue.
Top Projects Started 18
Provena Saint Joseph Medical Center
Expansion
Cost: $145 Million
An eight-story, 199-bed addition is under way at Provena
Saint Joseph Medical Center in Joliet, Ill.
The project began in August 2006 and is scheduled for completion
in March 2009. The 243,000-sq-ft, cast-in-place concrete addition
will provide private patient rooms and will levelly connect
to every floor of the existing 475-bed hospital.
Growing Population
The project is in response to the large population growth
in Will and Grundy counties and to Provena's desire to provide
private patient rooms. The existing hospital's patient rooms
will also be converted to private rooms.
The bed tower has a new entry canopy, conference center, retail
and winter garden. The new lobby also connects to an 875-car
parking garage. The lower level includes a new loading dock,
materials management, environmental services and laboratory.
"The new tower has a curved façade and it's a
little richer in color and design elements," says Mike
Doiel, senior vice president of Chicago-based HDR Architecture.
"The plan is to go back and enhance the existing hospital
by staining the brick to update the image."
The bench curve configuration of the addition "affords
different views internally and externally on every floor,"
Doiel says. "A straight corridor is monotonousness."
The design of the bed tower also supports the hospital's move
to electronic medical records.
"Nursing stations are decentralized," Doiel says.
"They're little miniature work stations between every
two rooms."
The design considered ease of use and access for staff and
patients. To line up the floors with the existing hospital,
Doiel says the new tower needed to be cast-in-place concrete
using flat plate technology instead of a steel frame.
"Most new bed towers need higher floor to floor ratios
because of the requirements on mechanicals and higher ceiling
heights," Doiel says.
While a concrete structure is more expensive, takes longer
and is more laborious than a steel frame, it provides a thinner
profile to levelly match up floors and allow enough floor-to-floor
space for mechanicals, Doiel says.
Otherwise, a steel-framed building would have required ramps
on each floor to connect the hospital to the new tower and
would make moving equipment, beds and patients more difficult.
Patient rooms are also the same size and are stacked vertically,
giving flexibility for floor changes that may be necessary
in the future.
Top Projects Started 19
Key Lime Cove Waterpark Resort
Cost: $125 Million
Key West is coming to Gurnee, Ill., in the form of the Key
Lime Cove Waterpark Resort.
Located on a 30-acre across the highway from the Gurnee Mills
Mall and
beside Six Flags Great America, the project broke ground on
November 2006 and is slated for completion in March 2008.
According to Joe Schuchardt, senior project manager with architect
and builder Planning Design Build of Madison, Wis., the facility
will include a four-story, 424-room hotel and a 50,000 sq.
ft., indoor water park. It will encompass 425,000 gross sq.
ft.
The facility will include restaurants, 6,000-sq-ft arcade
and entertainment center, Kids Kamp children's arts and craft
center and 12,000-sq-ft "celebratory facility" designed
to accommodate weddings, parties and meetings. The hotel's
largest guest suites will accommodate up to 12 people.
"The two-story lobby will feature a streetscape to mimic
the Key West location," Schuchardt says.
Winter Construction
Construction had to get out of the ground during the bitterly
cold days of February, and space is an ongoing issue on the
site.
"It's a 30-acre site, but the lobby and the water park
are pretty tight spaces," he says.
There are several vessels and four slides planned for the
water park, which will be connected by a "lazy river."
All of this requires a large amount of underground utility
work.
"Coordination is the issue," Schuchardt says. "We
have people working on a ton of underground utilities for
the water park, while other people are working on the slides
above them," he says.
The water park is sized to accommodate a planned expansion
of the hotel and the addition of a convention center as well
as the creation of an outdoor water park facility.
Top Projects Started 20
Calumet Water Reclamation Plant
Improvements
Cost: $121 Million
A wastewater pumping station and related facilities are under
construction at Chicago's sewage treatment plant on 130th
Street.
The project involves a new pumping station to handle 600 million
gallons of wastewater a day, says Peter Nielsen, project manager
of Elgin-based IHC Construction Cos. Inc., a member of the
IHC/FHP Tectonics Joint Venture serving as the contractor.
The new structure will replace the existing pumping station
originally built in the 1930s.
"The old facility handles 600 million gallons a day,
too, but the new one will do that much more efficiently,"
he adds.
The Pump Building will contain six raw sewage pumps, each
equipped with 1,500-horsepower motors, and 64-in. and 96-in.
discharge piping and valves.
Also included in the contract is a Screen Building that "will
take the big stuff out of the flow," Nielsen says. It
will hold five 10-ft-wide screen channels, mechanically cleaned
screens and three conveyor belts.
Also part of the project is a 96-in. pump discharge line that
will connect to a grit tank to be constructed at a later date.
Clarifier tanks are also to be constructed at a future date.
Making Connections
The biggest issue the team expects to facing is constructing
three flow-diversion chambers to connect to the existing 9-ft-diameter
sewer lines.
"They can only be shut for 48 hours at a time,"
Nielsen says of the sewers.
A plan is being developed and possibly might involve constructing
bypass pumping and fluming.
The contract also includes demolition of an existing two-story
brick building and abandoned underground conduits and channels.
Mechanical systems are part of the contract and include steam-heated
air handling units and ventilation systems. The electrical
system involves medium- and low-voltage electrical power and
a 500-kilowatt emergency generator.
Roads, walkways and site grading will also be constructed
as part of the contract.
Construction activity started in December. In mid-April, a
60-ft-deep excavation had been completed.
Click here for Top Projects Completed>>
Click here for Next Feature >>
|