|
2111 W. Roosevelt Rd. Office Complex
Project of the Year: Commercial (Large)
The 2111 W. Roosevelt Rd. office complex in Chicago was constructed
to meet the needs of the FBI, a government agency with exacting
requirements.
|
The agency's employees were housed in seven locations throughout
Chicago, but one complex was sought. The site had to be in
a location that allowed set-backs from the street for security.
Buildings previously on the site were demolished, and three
city blocks for the complex between Western and Damen avenues
were consolidated into one L-shaped block, partly for security.
Early in the project, utility services were scheduled to be
relocated due to the vacated easement between city blocks.
Delays in the process by the local electrical utility lead
to the first challenge: keeping the project's substantial
completion date intact.
A work-around solution was proposed. This involved approaching
the work in a different sequence, adjustments to the number
of men and equipment and adjusting the amount of man-hours
worked each week on certain tasks.
The last effect of eliminating the delay was a financial hit
to the project's contingency fund.
Elements of Design
Inside the completed building, guests are greeted by a two-level
main entry way/lobby and plaza that seamlessly blends through
a transparent, highly tensioned cable net-wall structure.
Although there are separate entrances for employees and visitors,
the plaza and lobby convey openness and neutralize the perception
of a highly secure facility.
The facade is composed of a highly articulated precast concrete
with vision glass and a blue-tinted spandrel glass that curves
along the north and south elevations. The curves allow increased
natural daylight to penetrate the office space while projecting
a professional and open appearance.
Prior to construction, the site was underused and an eyesore.
By cleaning up the site, an area that was once undesirable
has become attractive. New businesses have moved into the
neighborhood.
About 40 percent of the site is dedicated to landscaping to
create pleasant interaction between the complex's Illinois
Medical District Neighbors to the north and east, as well
as the residential and businesses to the south and west.
More than 230 shade and ornamental trees and bushes, groundcover
and perennials add to the overall pedestrian-level experience
and enjoyment.
Has Sustainable Elements
Sustainable design features include a detention basin that
is planted with native and water-tolerant grass.
The building's facade is a combination of 60 percent precast
concrete and low-emissivity glass for energy efficiency.
The concrete can be recycled at the end of its life. Interior
materials feature certified forest products for all new wood
installation, low-volatile-organic-compound sealants and paints,
post-consumer recycled rubber floor tiles, ceiling tile containing
recycled content and vinyl wall coverings that are Greenguard
indoor air quality certified.
In the aftermath of terrorist attacks in Oklahoma City and
New York, the government's need for heightened security measures
meant certain design elements were approached differently,
and many are not allowed to be publicly discussed-even now.
Engineering considerations included system redundancy throughout.
Since the critical functions of the federal agency cannot
be interrupted, power supply and HVAC systems were backed
up. Under General Services
Administration direction, a surplus GSA-owned generator from
the 2002 Olympics in Salt Lake City was paralleled with another
generator to serve the building's emergency power needs.
Along with security features, environmental protections were
included, such as the use of high-efficiency HVAC equipment
and lighting systems with occupancy sensors.
There was a 100-day hold after the project was awarded. During
the hold, steel prices skyrocketed, and the construction price
that was used to guarantee the rental rate was negatively
impacted.
The team worked to develop the same complex promised to the
GSA through collaboration in regard to other savings while
maintaining the level of quality proposed during the procurement
process. The team was able to complete the complex on time
and within budget.
Jury's Comments: "It was interesting to see this. Dollar
wise, it's pretty clear that this was a difficult project.
The other interesting element is how the lobby opens up to
the exterior.
"It is painful to work for the GSA, because the coordination
is extremely difficult. It is worth some recognition because
of the fortitude. The LEED requirements show a sophisticated
degree of planning. An FBI agent was on the site the whole
time."
Click
here for more Best of 2006 Award Winners >>
|