Features
 Current Features
 Past Features





Midwest Construction's
Best of 2006 Awards

Lambert-St. Louis International Airport Expansion

Project of the Year: Transportation




The Lambert-St. Louis International Airport Expansion Program (AEP) was the result of a more than 20-year process to address airfield capacity limitations.

advertisement

AEP took shape Sept. 30, 1998, when the Federal Aviation Administration endorsed the airport's plans. The project focus was to build a third runway, parallel to Lambert's existing two major runways.

Construction broke ground in July 2001 with the goal of completing the work by late spring 2006 with a budget of $1.1 billion. The project was completed in April and within the budget.

The AEP was the largest capital improvement project in the history of St. Louis. In part due to the project's size, officials with the airport and St. Louis decided to use the project to grow the design and construction industry in the region.

They contracted with an expansion team of employees and consultants who were charged with managing the entire project. The airport's and city's goals to develop the regional design and construction industry resulted in the AEP being broken into 14 design projects, 16 major construction projects and about 80 demolition projects.

The goal of the expansion team was to coordinate these organizations and individuals to complete a program the size of which the St. Louis area had never seen.

Land-Locked Lambert

Like many existing airports, Lambert is land locked, and the land that the airport was expanding to was predominantly owned by others.

The 1,500 acres Lambert bought included more than 1,900 residences and 80 commercial properties.

After the FAA approved the project, the airport began purchasing parcels.
Construction plans and schedules were drawn up to drive up land acquisition of the properties needed for the first phases of construction.

The construction site was larger than Forest Park in St. Louis and was bordered by residences and commercial operations. As a result, operations interacted with large numbers of people, some of whom did not favor the AEP.

The general construction approach was to first relocate several major roadways so that the runway itself could be built. This entailed relocating Lindbergh Boulevard and Natural Bridge Road while they were still being used.

A series of temporary roadway bypasses were built to minimize inconvenience to the public, used and dismantled.

Adding to the complexity was the need to remove and cap a utility infrastructure designed for residences and businesses and replace it with an infrastructure to supply the unique and exacting needs of an airfield.

The AEP area also included a major utility corridor feeding much of North St. Louis County, which had to remain intact 24 hours a day, seven days a week through the five-year project.

Because land acquisition proceeded piecemeal to meet residents' and AEP needs, intricate utility cut-offs were needed to preserve service to surrounding residents and businesses while allowing construction to move ahead with building a new utility infrastructure.

Runways are generally flat, but the area in which Lambert's new runway was built was not flat. Engineers determined that 13.5 million cu. yds. of soil needed to be removed, requiring an entire storm water runoff plan be developed and executed.

A ridge originally ran perpendicular to the runway alignment to cut across the site, and a terrain fell off into a valley to the west of the ridge.

Moreover, the new location of the project was planned to be soil balanced so that no soil was removed from or brought to the site; it was moved from one area to another.

As a consequence, cuts of up to 90 ft. were made, while fills reach 90 ft. in depth. Because of the exacting requirements for runway safety, the fill area was designed to settle no more than 1.5 in. over the 30 years following the completion of construction.

Immense Excavation Work

The massive excavation work was to be executed so the platform for the runway was created and allowed to settle for 12 months before the runway itself could be built. This meant excavation year-round, even in winter.

A couple project elements were unique, including the Lindbergh Boulevard tunnel, the first traffic tunnel in Missouri. Having a high-security airfield atop a tunnel added to the design complexity.

The second key project was the runway itself, which was the first new runway at Lambert in 50 years. Construction of the runway was carried out immediately adjacent to an active airport, requiring close coordination and planning.

GPS Used

The program management team and contractors used global positioning system and total station surveying.

The data collected allowed the program manager to model a variety of surfaces. Electronics improved production rates and accuracy.

GPS devices were mounted to excavation equipment, and the computers compared the current vs. the planned grade and controlled the level of blades and the amount of soil removed from any given area.

Jury Comments: "This was one heck of a job. This is an amazing project for a public agency. Other airports could learn from this project."




Click here for more Best of 2006 Award Winners >>


 

 Click here for more Features >>


 


Sponsors

© 2008 The McGraw-Hill Companies, Inc.
All Rights Reserved