Best Project Specialty Contracting: Citgo Lemont Refinery Coker Turnaround

Text size: A A
[ Page 1 of 2 ]

Structural repairs to a sponge coker unit at this CITGO petroleum refinery required years of planning because of a narrow window of just 30 days to execute the $9.4-million project, which involved modifications to coke chutes, coke pit walls and floors, and head decks as well as supporting columns and beams.

Photo Courtesy of STRUCTURAL
Repairs to a sponge coker unit at a Citgo petroleum refinery in Lemont, Ill., required years of planning due to a window of just 30 days to execute the project.
----- Advertising -----

Preparations included extensive training for each crew member—from labor to management—in the key areas of safety, task training and execution.

Elgin, Ill.-based concrete contractor STRUCTURAL commandeered more than 200 repair specialists, dividing work into two 12-hour shifts that operated for 30 consecutive days, logging zero safety incidents during more than 67,000 man-hours.

Among other initiatives, STRUCTURAL encouraged workers to submit observation reports documenting unsafe conditions.

As work progressed, crews repaired and strengthened more than 900 sq ft of support columns and beams on coking unit head decks, a task involving about 30 yd of concrete. Four of the six decks were completely removed and replaced with about 120 yd of concrete. Full-depth repairs were completed on angled coke chutes for six drums.

Crews repaired the coke pit by first pouring a leveling mud slab, then installing an under-drain system topped by a new reinforced concrete slab. A transition slab was built to join the new slab to the existing coke pit ramp.

One of the more significant challenges involved access to the top and bottom of head decks and angled coke chutes directly below them, circumstances that prompted deployment of a suspended deck system to access head deck beams and slabs, including swing stages with angular stirrup brackets to repair the chutes. Both systems served to protect crews at work in chute and pit areas below.

Each work area, including head decks, coke chutes, pit floors and pit walls, was assigned a dedicated project management team to develop related safety, execution and QA/QC plans.

CITGO Lemont Refinery Coker Turnaround, Lemont, Ill. Key Players

Owner: CITGO Petroleum Corp. Inc., Lemont, Ill.

Keywords:

[ Page 1 of 2 ]
----- Advertising -----
Blog: ENR Midwest Musings
ENR Midwest Musings delivers the latest news, insights and opinions about construction & design in Illinois, Indiana, Wisconsin and Missouri, as well as Iowa, Ohio, Michigan and Minnesota.
Reader Photos
Photos from ENR Photo Showcase
Dodge Lead Center
Search for local construction projects OR CALL 877-234-4246 and get a FREE Lead Now!
Search by Project Type & State





----- Advertising -----
 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.