|
Does an 'Incorporation by Reference'
Clause
Always Include the Incorporated Contract's Arbitration Provision?
By John S. Mrowiec
In October, we discussed the dilemma of a party who is prosecuting
an upstream claim and defending claims from downstream claimants,
both subject to differing dispute forums and, thus, more expense
and potential contradictory outcomes.
This month we discuss one Indiana contractor's unsuccessful
attempt to arbitrate subcontractors' claims arising from an
owner's failure to pay, MPACT Construction Group, LLC v. Superior
Concrete Constructors, Inc., 2003 Ind. App. LEXIS 464 (1st
Dist., Mar. 26, 2003).
A general contractor and owner entered into a contract for
the construction of a travel plaza. The parties use the American
Institute of Architects A101 Agreement (1987 edition). That
agreement incorporated the American Institute of Architects,
General Conditions of the Contract for Construction A201 (1987
edition). The general conditions contain a broad arbitration
provision.
The general contractor entered into various subcontracts.
The subcontract form did not include an express arbitration
clause or any other express provision regarding subcontractors'
rights and remedies.
What the subcontracts did provide was an "incorporation
by reference" cause as follows:
"Contractor has heretofore entered into a General Contract
with Owner
inclusive of, but not limited to the project
plans and specifications, schedules, drawings and amendments
by addenda
which are hereby made a part of the General
Contract between the Owner and the Contractor and are hereby
made a part of this subcontract as applicable to the work
stated therein, and pursuant to the subcontractor's intent
to infer into this subcontractual agreement, with reference
to any and all of said work (emphasis by court)."
The owner failed to pay. The general contractor and most
of the subcontractors recorded mechanics liens. One of the
subcontractors filed suit to foreclose its lien against the
owner's property and for breach of the subcontract against
the general contractor. The other subcontractors and the general
contractor filed various cross-claims.
The general contractor then filed a motion to compel arbitration
against the owner and the subcontractors and to stay the litigation
pending the outcome of arbitration. After a hearing, the trial
court denied the contractor's motion. The denial of a motion
to compel arbitration is immediately appealable under both
Indiana's Uniform Arbitration Act and the Federal Arbitration
Act. The general contractor appealed.
On appeal, the MPACT Construction appellate court had no
problem finding that the owner was obligated to arbitrate
the dispute with the general contractor under the language
of the AIA A201 General Conditions. The question of arbitration
with the subcontractors was more difficult.
The general contractor argued that the subcontractors must
arbitrate. The subcontracts incorporated the owner-contractor
agreement. The agreement, in turn, incorporated the general
conditions. They included an arbitration provision.
The subcontractors agreed that the subcontract incorporated
the agreement and general conditions, but not in their entirety.
According to the subcontractors, those documents were incorporated
only as applicable to the specific work performed and not
regarding the arbitration provision.
The appellate court viewed the governing legal principles
under Indiana contract law to be
The party seeking to compel arbitration has the burden of
demonstrating the existence of an enforceable arbitration
agreement.
Parties are only bound to arbitrate those issues that by
clear language (not by implication) they have agreed to arbitrate.
A document incorporated by reference for a specific purpose
becomes a part of the contract only for the purpose specified
and for no other purpose.
The MPACT Construction appellate court had to decide whether
the phrase "as applicable to the work" limited the
incorporation of the general conditions. What did the subcontract
mean by incorporating the general conditions as "applicable
to the [subcontractor's] work"?
In deciding that question, the MPACT Construction court placed
special emphasis on a provision of the subcontract commonly
included in construction contracts:
"The Subcontractor acknowledges that he has read the
General Contract and all plans and specifications, together
with all amendments and addenda thereto, and is familiar therewith
and agrees to comply with and perform all provisions thereof
applicable to Subcontractor. The intent of the Contract Documents
is to include all items necessary for the proper execution
and completion of the work. The contract documents are complementary
and what is required by any one shall be binding as if required
by all (emphasis by court)."
While most in the industry probably view the highlighted
language as emphasizing the broad reach of the subcontract's
work scope, the court believed the language limited the definition
of "work." The MPACT Construction court ruled that
the phrase "applicable to the work" limited the
incorporation of the general conditions so that the arbitration
provision would not apply. The court viewed the incorporation
as including only those owner-contractor agreement and general
conditions provisions relating to "the specifications
and description of the work, as well as its performance, execution
and completion."
The result of the MPACT Construction court's appellate decision
was that the contractor-owner dispute would be arbitrated
and the contractor-subcontractor subcontract dispute and the
subcontractor mechanics lien claims would be litigated.
On somewhat similar facts, an Illinois court years earlier
reached a different result in Turner Construction Co. v. Midwest
Curtainwalls, Inc., 543 N.E. 2d 249 (Ill. 1st App. Dist. 1989).
In Midwest Curtainwalls, a subcontractor claimant wanted
to arbitrate a dispute with the general contractor. The general
contractor sought to stay the arbitration. The trial court
refused to stay the arbitration. The general contractor appealed.
In Midwest Curtainwalls, like in MPACT Construction, the
subcontract did not include an express arbitration provision
but the owner-contractor agreement did.
The flow-down provision in the Midwest Curtainwalls subcontract
read:
"With respect to the Work to be performed and furnished
by the Subcontractor hereunder, the Subcontractor agrees to
be bound to the Contractor by each and all of the terms and
provisions of the General Contract and the other Contract
Document, and to assume toward Contractor all of the duties,
obligations and responsibilities that Contractor by those
Contract Documents assumes toward the Owner, and the Subcontractor
agrees further that Contractor shall have the same rights
and remedies as against the Subcontractor as the Owner under
the terms and provisions of the General Contract and the other
Contract Documents has against Contractor with the same force
and effect as though every such duty, obligation, responsibility,
right or remedy were set forth herein in full. The term and
provisions of this Agreement with Subcontractor hereunder
are intended to be and shall be in addition to and not in
substitution for any of the terms and provision of the General
Contract and the other Contract Documents (emphasis supplied)."
The general contractor in Midwest Curtainwalls argued that
the incorporation of the rights and remedies of the general
contractor into the subcontract related only to the "work
to be performed," not to the resolution of disputes between
the general contractor and the subcontractor.
The Midwest Curtainwalls court rejected the contractor's
argument and held that the dispute must be arbitrated. In
the view of the Midwest Curtainwalls court, the limitation
of the incorporation to the "work" was meaningless:
"the relevant disputes would always arise 'with respect
to the work to be performed.'" Thus, the Midwest Curtainwalls
court could not conceive of a situation where arbitration
would not apply.
Apparently, the contractor arguing before the Indiana MPACT
Construction court did not make a similar argument or, if
it did, the court ignored it.
No reported Wisconsin court addressed the issue of whether
an arbitration provision was incorporated by reference where
the reference was in some way limited. One Wisconsin decision
held a contractor waived its right to arbitrate and tacitly
accepted the premise that an arbitration clause could be incorporated
by a general incorporation of an upstream contract, Syring
Construction Co. v. Potter, 287 N.W.2d 854 (Wis. Ct. App.
Dist. II, 1979, unpublished).
John S. Mrowiec is a partner with
Chicago-based Conway & Mrowiec, a construction and public
contracts law and litigation practice. He may be reached at
(312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|