|
Payment Bonds and Arbitration:
Is the Surety Bound by the Result of a Claimant's
Arbitration with the Principal?
By John S. Mrowiec
Payment bonds are a frequent feature of construction projects.
Labor and material payment bonds are universal on public projects
because statutes mandate their use. Subject to the terms of
the payment bond, the payment bond surety is to pay when the
underlying principal fails to do so. Subject to the terms
of the bond or the statute, the surety's liability for payment
for the claimant's unpaid labor and materials is co-extensive
with the liability of its principal, the contractor placing
the bond.
Payment bond statutes and the bonds themselves usually require
the filing of a lawsuit against the payment bond surety by
a deadline provided by the statute or, sometimes, by the bond.
Otherwise, the payment bond claimant loses its rights. On
private projects (and for bonds placed by subcontractors on
public projects), the language of the bond itself typically
requires that a lawsuit be filed by a deadline defined in
the bond. But construction contracts and subcontracts often
contain provisions mandating arbitration, not lawsuits, to
enforce rights under the contract.
If there is such an arbitration provision in the subcontract,
must a claimant both arbitrate with the principal and sue
the surety? If the claimant must arbitrate with the principal
and the claimant wins in arbitration, is that arbitration
result binding on the surety? In other words, if the principal
does not pay the arbitration award, must the court in the
suit against the surety automatically declare victory for
the claimant against the surety or is the arbitration result
irrelevant to the surety's liability to the claimant?
If the surety is not bound by the results of the arbitration,
then the claimant must prosecute two proceedings to conclusion
- an arbitration and a lawsuit. Whether the surety will be
bound by the results of the arbitration is sometimes a confusing
legal question. A recent federal court decision discusses
the question in the context of a contractor-principal on a
federal construction project who failed to defend the arbitration
in United States f/u/b Frontier Construction, Inc. v. Tri-State
Management Co., 2003 U.S. Dist. LEXIS 6421 (N.D. Ill., April
16, 2003).
Tri-State Management Co. was the prime contractor for construction
of a United States Postal Service building expansion. The
prime contractor, as principal, posted a labor and materials
payment bond as it was required to do under the federal Miller
Act, 40 U.S.C. §270a et seq.
North American Specialty Insurance Co. was the surety.
Frontier Construction was a subcontractor to the prime contractor.
The subcontract contained an arbitration provision that mandated
all disputes arising under the subcontract be arbitrated.
The subcontract also provided that a court judgment was to
be entered in accordance with the arbitration award (a "consent
to confirmation" clause).
The subcontractor claimed that prime contractor failed to
pay. The subcontractor pursued two remedies: (1) a federal
court lawsuit against the prime contractor and the surety
under the Miller Act bond and counts against the prime contractor
only for breach of the subcontract and quantum meruit; and
(2) at the same time, arbitration with the prime contractor
only for breach of the subcontract.
The Frontier Construction decision does not tell us whether
the litigation was stayed pending the outcome of the arbitration.
But an arbitrator held a hearing on the arbitration between
the subcontractor and the prime contractor. The prime contractor
failed to appear and to defend.
Accordingly, the arbitrator entered an award in favor of the
subcontractor and against the prime contractor for $41,450
plus interest and $7,521 in attorneys' and arbitration fees.
In the litigation, after the arbitration award, the subcontractor
moved to confirm the award and to enter judgment against both
the prime contractor and the surety. Again, the prime contractor
did not appear and defend. Thus, the Frontier Construction
court granted that part of the subcontractor's request seeking
confirmation of the arbitration award against the prime contractor.
The surety argued that there could be no judgment entered
against the surety based solely on an arbitration award against
its principal, the prime contractor. The subcontractor argued
that as a Miller Act surety, the surety was bound by an arbitration
award against the surety's principal.
Because the governing Seventh Circuit federal appeals court
had never ruled on the issue, the subcontractor cited two
federal appellate court decisions from outside the Circuit.
The Frontier Construction court reviewed the cited cases and
found those cases to be based on a theory of "preclusion."
That is, those cases held the Miller Act surety was bound
by a result in a proceeding against its contractor-principal
"of which surety had full knowledge and opportunity to
defend." (Frontier Construction, 2003 U.S. Dist. LEXIS
6421, at 5 quoting Frederick v. United States, 386 F.2d 481,
485 n.6 (5th Cir. 1967)).
The cases cited by the subcontractor for why the surety should
be bound involved situations where the contractor-principal's
lawyers also were defending the surety - the common situation
when the contractor is solvent. In Frontier Construction,
the prime contractor had no lawyer; the surety had to hire
its own lawyers.
The Frontier Construction court noted that it was not clear
whether a Miller Act surety (as opposed to a state statutory
or non-statutory surety) ever may be bound by an arbitration
award or court judgment against the surety's principal. The
federal Miller Act provides "exclusive" federal
court jurisdiction of actions on a Miller Act bond. Some cases,
again from outside the Seventh Circuit, have held that the
Miller Act's provision for exclusive jurisdiction means that
a Miller Act surety may never be bound by an arbitration award
or state court judgment against the surety's principal.
The court in Frontier Construction determined that, in this
case, it did not matter whether one viewed the issue as one
of "preclusion" or as one of "exclusive jurisdiction."
Either the surety was entitled to defend in a federal court
lawsuit under the terms of the Miller Act or, even if that
rule did not apply, the surety cannot be bound by an arbitration
award when the surety "did not have an opportunity to
defend itself" (Frontier Construction, 2003 U.S. Dist
LEXIS 6421, at 9).
The judge in Frontier Construction said that the default
nature of the arbitration award in that case distinguished
it from the usual "preclusion" case. Because the
prime contractor-principal did not even bother to defend the
arbitration demand, the Frontier Construction court held that
the surety could not be bound by the default arbitration award.
The Frontier Construction court remarked that the subcontractor
did not argue that the surety was bound by the agreement to
arbitrate contained in the subcontract. Also, the arbitration
award, on its face, was entered only against the prime contractor,
not its surety. We do not know whether the Frontier Construction
court was implying that the case might have been decided differently
if the subcontractor had argued that the bond incorporated
the subcontract, if there legally was such an argument available.
In another case, a prime contractor's performance and payment
bond surety was held to be bound by an arbitration provision
in the owner-contractor agreement regarding a dispute between
the owner, contractor and contractor's surety (Bolingbrook
Park District v. National-Ben Franklin Insurance Co., 420
N.E.2d 741 (Ill. 3d App. Dist. 1981)). But the Bolingbrook
Park District case involved incorporation of the prime contract
into the prime contractor's performance and payment bonds,
not the question of whether a claiming subcontractor's subcontract
is incorporated into a prime contractor's payment bond.
In Frontier Construction, the surety did have "notice
of the arbitration." What is unclear about the decision
is, once the subcontractor notified the surety about the arbitration,
what extra step should the subcontractor have taken to ensure
that the surety "had an opportunity to defend?"
To maximize the argument that the surety "had an opportunity
to defend," a bond claimant can send to the surety copies
of all of the arbitration papers, orders, notices of hearing
dates and other correspondence that any participant in the
arbitration would receive. Other times, the subcontractor
might obtain the surety's agreement to be bound by the results
of the arbitration.
(The "agreement to be bound" situation is much more
common when the surety is comfortable with the principal being
able to pay any arbitration award.)
John S. Mrowiec is a partner with
Chicago-based Conway & Mrowiec, a construction and public
contracts law and litigation practice. He may be reached at
(312) 658-1100. For information, go to the firm's Web site
at www.cmcontractors.com.
|