|
Recovery of Unabsorbed Home Office
Overhead
Under the Eichleay Formula:
The Standby Test
Delays or suspension of a contractor's performance frequently
increase the contractor's "direct" costs of performing
the work. A contractor's "direct" costs "arise
solely because of and are attributable directly to performance
of a specific contract" (West v. All State Boiler Inc.,
146 F.3d 1368, 1372 (Fed. Cir. 1998)). Common direct costs
increased by delay or suspension are site overhead and site
supervision costs.
A contractor also incurs "indirect" costs. These
"indirect" costs "are not attributable to one
contract in particular but arise because of [the contractor's]
general operations. Indirect costs are usually those costs
that are "incurred despite construction inactivity on
a project, such as home office overhead, including accounting
and payroll services, general insurance, salaries of upper
level management, heat, electricity, taxes, depreciation'"
(All State Boiler, 146 F.3d at 1372 (quoting Interstate General
Government Contractors Inc. v. West, 12 F.3d 1053, 1058 (Fed.
Cir. 1993)). "A contractor recovers its indirect costs
by allocating them on a proportionate basis among all of its
contracts" (All State Boiler, 146 F.3d at 1372).
Calculation of damages for a contractor's daily unabsorbed
overhead costs is most commonly done using the Eichleay formula.
Named after a 1960 Armed Services Board of Contract Appeals
decision, the formula multiplies a contractor's daily unabsorbed
overhead by the number of days of government-caused performance
delay to determine the contractor's damages (Eichleay Corp.,
1960 ASBCA LEXIS 1207, 60-2 BCA (CCH) 2688, 13,568 (1960)).
Indeed, in federal construction contracts when a contractor
satisfies the prerequisites for application of the formula,
the Eichleay formula now is the exclusive acceptable method
for calculating unabsorbed home office overhead damages, except
in limited special circumstances (Wickham Contracting Co.
v. Fischer, 12 F.3d 1574, 1579-80 (Fed. Cir. 1994)).
Calculation of the damages amount under the Eichleay formula
requires three steps: (1) to find allocable contract overhead,
multiply the total overhead cost incurred during the contract
period times the ratio of billings from the delayed contract
to total billings of the firm during the contract period;
(2) to get the daily contract overhead rate, divide allocable
contract overhead by days of contract performance; and (3)
to get the amount recoverable, multiply the daily contract
overhead rate times the days of government-caused delay (Capital
Electric Co. v. United States, 729 F.2d 743, 747 (Fed. Cir.
1984)).
Recovery under the Eichleay formula, however, is not automatic
in cases where the contractor was delayed: It is "an
extraordinary remedy" (All State Boiler, 146 F.3d at
1377). First, the contractor must "show that a government-imposed
delay occurred" (Sauer Inc. v. Danzig, 224 F.3d 1340,
1348 (Fed. Cir. 2000)).
The proof of causation to recover unabsorbed overhead arising
from government delay differs for application of the Eichleay
formula from the causation proof for recovery of direct costs
arising from delay.
The two prerequisites to application of the Eichleay formula
are: (1) the contractor must be on "standby" and
(2) the contractor must be "unable to take on other work"
(Interstate General, 12 F.3d at 1056.)
The "standby" test "focuses on the delay or
suspension of contract performance for an uncertain duration,
during which a contractor is required to remain ready to perform"
(Interstate General, 12 F.3d at 1058). The contractor bears
the burden of proof on the "standby" test.
The second test, the "other work" test, is the government's
to prove. The government must demonstrate "that it was
not impractical for the contractor to take on replacement
work and thus avoid the loss" (All State Boiler, 146
F.3d at 1381).
This month we highlight a new case decision discussing the
meaning of "standby" for purposes of recovering
unabsorbed overhead resulting from government-caused delay
under the Eichleay formula, Charles G. Williams Construction
Inc. v. White, 326 F.3d 1376 (Fed. Cir., May 5, 2003).
In Williams Construction, the contractor was awarded a fixed-price
contract to improve and to renovate a government building.
The work was divided into two phases, north and south. The
government was to vacate that portion of the building phase
upon which the contractor would be working.
There were substantial delays. The government failed to vacate
the south phase timely, which caused substantial delays in
the contractor's performance. The government issued a large
number of change orders, many of which provided for additional
payment to the contractor.
There were defects in the government specifications. But there
also were deficiencies in the performance of the contractor
and of some of its subcontractors.
The contractor completed one of the phases 93 days after the
extended completion date. The government terminated the other
phase for the government's convenience.
The Armed Services Board of Contract Appeals allowed some
of the contractor's claims. However, the Board denied the
contractor's Eichleay unabsorbed home office overhead claim.
The Board held that the contractor had failed to satisfy the
"standby" test, despite the government-caused delays.
The Board found that the contractor "has not proved that
performance of the work was suspended or significantly interrupted
during the period" involved (Williams Construction, 326
F.3d at 1380). The Board found that "the site was manned
without significant interruption" by the contractor and
its subcontractors (who performed 89 percent of the work)
throughout the contract performance period (Williams Construction,
326 F.3d at 1381).
The Board placed special emphasis on the fact that both the
government's auditor and the contractor's expert witness agreed
that the contractor "did not have any reduction in their
flow of direct costs." In the words of the auditor, "[T]his
contract continued to absorb its equitable share of general
and administrative expenses; they didn't have to go out and
replace work because the work was being replaced by this additional
effort on this contract" (Williams Construction, 326
F.3d at 1380). In other words, the contractor's additional
compensated changed work was providing the direct cost and
revenue such that the home office overhead was not "unabsorbed."
The Board concluded that the contractor had not been on standby
for an uncertain duration and denied the Eichleay claim. The
contractor appealed.
On appeal, the United States Federal Circuit affirmed the
Board's finding against the contractor on the Eichleay claim.
In addition to discussing the evidence supporting the Board's
findings, the Williams Construction appellate court articulated
what evidence it believed was lacking. "There was no
evidence that on any particular day [the contractor] was unable
to do any work at all on the contract, but still was required
to remain able to resume work on short notice. Furthermore,
there was no evidence that the government directed [the contractor]
to remain so on call" (Williams Construction, 326 F.3d
at 1383).
The contractor argued that it need not prove an outright active
or constructive suspension to recover under Eichleay. The
contractor contended that recovery under the Eichleay formula
was appropriate if the contractor showed that the government
"significantly interfered with efficient performance
of the contract even though the contractor continued to perform."
While that set of facts might entitle the contractor to recover
direct costs, the Williams Construction court held that it
was insufficient to pass the Eichleay "standby"
test. In the words of the court, "As long as the contractor
is able to continue performing the contract, although not
in the same way or as efficiently or effectively as it had
anticipated it could do so, it can allocate a portion of its
indirect costs to that contract. There is accordingly no occasion
in that situation to resort to 'recovery under the Eichleay
formula', which is 'an extraordinary remedy'" (Williams
Construction, 326 F.3d at 1382).
Williams Construction is a federal contracts case. It is in
that context where use of the Eichleay formula has been most
developed. In state courts, and in federal courts applying
state law in diversity actions in our readership's geographical
region, the Eichleay formula has not been discussed often.
Its use has been approved in appropriate circumstances. (See
Aircraft Gear Corp. v. Kaman Aerospace Corp., 875 F.Supp.
485, 495-98 (N.D.Ill. 1995) (applying Connecticut law to claim
of aircraft subcontractor but where state law non-existent
or inconclusive, federal law Eichleay formula caselaw provides
guidance). The formula's use has been rejected where inappropriate
(See Marino Construction Co. v. Renner Architects, 214 Wis.
2d 589 (1997) (Eichleay formula not relevant where contractor
found to be cause of delay)).
Recovery of home office overhead sometimes has been allowed
in our region with no discussion of the Eichleay formula.
(See Fattore Co. v. Metropolitan Sewerage Commission, 505
F.2d 1 (7th Cir. 1974) (applying Wisconsin law)); Terra Engineering
& Construction Corp. v. LaCrosse County, 204 Wis. 2d 113,
1996 Wisc. App. LEXIS 925, *5 (App. Dist. 4, 1996)). Recovery
of home office overhead sometimes has been denied where the
claimant had other work even though no Eichleay test was discussed.
(See Material Service Corp. v. Michaels Pipe Line Construction,
204 Wis. 2d 110, 1996 Wisc. App. LEXIS 912, 24 (App. Dist.
1, 1995)).
|